GEMC-511687770631081
Awarded to Gurmeet Singh
₹39.8 L
Products
| Product | Brand / Model | HSN | Quantity | Unit Price | Amount |
|---|---|---|---|---|---|
| 6.Steel work in built up tubular | - | HSN not specified by seller | 2,250 Kg | ₹167 | 375,750 |
| 4.Centering and shuttering including strutting, propping etc. | - | HSN not specified by seller | 39 Sqm | ₹250 | 9,750 |
| 2.Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering | - | HSN not specified by seller | 1 CUM | ₹4,409 | 4,409 |
| 13.Carriage of material by transportation Sand for 15 kms av. Distance | - | HSN not specified by seller | 5 M | ₹280 | 1,400 |
| 1.Earth work in bulk excavation by manual means over areas | - | HSN not specified by seller | 25 Cum | ₹519 | 12,975 |
| 12.Carriage of material by transportation,Sand for 15 kms av. Distance | - | HSN not specified by seller | 7 m | ₹280 | 1,960 |
| 10.Painting with synthetic enamel paint of approved brand and manufacture to give an even shade. Two or more coats on new work. . Complete Job. | - | HSN not specified by seller | 56 Sqm | ₹120 | 6,720 |
| 8.Hire charges for Crane to erect the Unipoles. | - | HSN not specified by seller | 3 JOB | ₹9,479 | 28,437 |
| 7.Providing and fixing of retro reflective double sided over head gantry signage | - | HSN not specified by seller | 360 Sft | ₹645 | 232,200 |
| 5.Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing inposition and binding all complete. | - | HSN not specified by seller | 3,850 Kg | ₹78.50 | 302,225 |
| 3.Reinforced cement concrete work in walls | - | HSN not specified by seller | 6 CUM | ₹8,539 | 51,234 |
| 2.Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering | - | HSN not specified by seller | 3 Cum | ₹4,409 | 13,227 |
| 13.Carriage of material by transportation,Sand for 15 kms av. Distance | - | HSN not specified by seller | 15 m | ₹280 | 4,200 |
| 11.Proving and fixing of nuts and bolts of required size approved from the Engineer Incharge. Complete Job. | - | HSN not specified by seller | 32 No | ₹739 | 23,648 |
| 9.Finishing with Epoxy paint | - | HSN not specified by seller | 19 SQM | ₹185 | 3,515 |
| 8.Hire charges for Crane to erect the Unipoles and Signage on both sides. . Complete Job. | - | HSN not specified by seller | 1 Job | ₹9,479 | 9,479 |
| 6.Steel work in built up tubular | - | HSN not specified by seller | 6,850 Kg | ₹167 | 1,143,950 |
| 4.Centering and shuttering including strutting, propping etc. and removal of form work for: Foundations, footings, bases for columns | - | HSN not specified by seller | 22 SQM | ₹250 | 5,500 |
| 3.Providing and laying cement concrete in retaining walls, return walls, walls | - | HSN not specified by seller | 14 Cum | ₹8,539 | 119,546 |
| 1.Earth work in bulk excavation by manual means over areas | - | HSN not specified by seller | 42 Cum | ₹519 | 21,798 |
| 12.Carriage of material by transportation,Sand for 15 kms av. Distance | - | HSN not specified by seller | 12 m | ₹280 | 3,360 |
| 10.Painting with synthetic enamel paint of approved brand and manufacture to give an even shade. Two or more coats on new work | - | HSN not specified by seller | 19 SQM | ₹120 | 2,280 |
| 9.Finishing with Epoxy paint | - | HSN not specified by seller | 47 Sqm | ₹185 | 8,695 |
| 7.Providing and fixing of retro reflective double sided over head gantry signage | - | HSN not specified by seller | 960 Sft | ₹645 | 619,200 |
| 5.Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing inposition and binding all complete | - | HSN not specified by seller | 795 KG | ₹78.50 | 62,407.5 |
| 4.Centering and shuttering including strutting, propping etc. | - | HSN not specified by seller | 30 Sqm | ₹250 | 7,500 |
| 2.Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering | - | HSN not specified by seller | 3 Cum | ₹4,409 | 13,227 |
| 13.Carriage of material by transportation,Sand for 15 kms av. Distance | - | HSN not specified by seller | 25 m | ₹280 | 7,000 |
| 11.Proving and fixing of nuts and bolts of required size | - | HSN not specified by seller | 24 NO. | ₹739 | 17,736 |
| 10.Painting with synthetic enamel paint of approved brand and manufacture to give an even shade. Two or more coats on new work. . Complete Job. | - | HSN not specified by seller | 142 Sqm | ₹120 | 17,040 |
| 8.Hire charges for Crane to erect the Unipoles and Signage on both sides. . Complete Job. | - | HSN not specified by seller | 4 Job | ₹9,479 | 37,916 |
| 6.Steel work in built up tubular | - | HSN not specified by seller | 1,550 KG | ₹167 | 258,850 |
| 5.Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing inposition and binding all complete. | - | HSN not specified by seller | 1,850 Kg | ₹78.50 | 145,225 |
| 3.Providing and laying cement concrete in retaining walls, return walls, walls | - | HSN not specified by seller | 26 Cum | ₹8,539 | 222,014 |
| 1.Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. | - | HSN not specified by seller | 8 CUM | ₹519 | 4,152 |
| 12.Carriage of material by transportation Sand for 15 kms av. Distance | - | HSN not specified by seller | 3 M | ₹280 | 840 |
| 11.Proving and fixing of nuts and bolts of required size approved from the Engineer Incharge. Complete Job. | - | HSN not specified by seller | 80 No | ₹739 | 59,120 |
| 9.Finishing with Epoxy paint | - | HSN not specified by seller | 56 Sqm | ₹185 | 10,360 |
| 7.Providing and fixing of retro reflective double sided over head gantry signage | - | HSN not specified by seller | 180 SFT | ₹645 | 116,100 |