Loading…
Loading…
Tender Value
₹6.4 Cr
EMD Value
₹12.8 L
Closing Date
7 Aug 2026, 3:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Deposit Work
SR.DEN/C
15 conditions · 2 needing a document upload
10.2. Financial Eligibility Criteria: The tenderer must have minimum average annual contractual turnover V/N or V whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
10. Eligibility Criteria: 10.1 Technical Eligibility Criteria: (a) The tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited:(i) Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or (ii) Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or (iii) One similar work costing not less than the amount equal to 60% of advertised value of the tender. (b) (1) In case of tenders for composite works (e.g. works involving more than one distinct component, such as Civil Engineering works, S&T works, Electrical works, OHE works etc. and in the case of major bridges - substructure, superstructure etc.), tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited:(i) Three similar works each costing not less than the amount equal to 30% of advertised value of each component of tender, or (ii) Two similar works each costing not less than the amount equal to 40% of advertised value of each component of tender, or (iii) One similar work each costing not less than the amount equal to 60% of advertised value of each component of tender. Note for b(1): Separate completed works of minimum required values shall also be considered for fulfillment of technical eligibility criteria for different components. (b)(2)In such cases, what constitutes a component in a composite work shall be clearly pre- defined with estimated tender cost of it, as part of the tender documents without any ambiguity. (b) (3) To evaluate the technical eligibility of tenderer, only components of work as stipulated in tender documents for evaluation of technical eligibility, shall be considered. The scope of work covered in other remaining components shall be either executed by tenderer himself if he has work experience as mentioned in clause 7 of the Standard General Conditions of Contractor through subcontractor fulfilling the requirements as per clause 7 of the Standard General Conditions of Contract or jointly i.e., partly himself and remaining through subcontractor, with prior approval of Chief Engineer in writing. However, if required in tender documents by way of Special Conditions, a formal agreement duly notarised, legally enforceable in the court of law, shall be executed by the main contractor with the subcontractor for the component(s) of work proposed to be executed by the subcontractor(s), and shall be submitted along with the offer for considering subletting of that scope of work towards fulfilment of technical eligibility. Such subcontractor must fulfill technical eligibility criteria as follows:The subcontractor shall have successfully completed at least one work similar to work proposed for subcontract, costing not less than 35% value of work to be subletted, in last 5 years, ending last day of month previous to the one in which tender is invited through a works contract. Note: for subletting of work costing up to Rs 50 lakh, no previous work experience of subcontractor shall be asked for by the Railway.
In case after award of contract or during execution of work it becomes necessary for contractor to change subcontractor, the same shall be done with subcontractor(s) fulfilling the requirements as per clause 7 of the Standard General Conditions of Contract, with prior approval of Chief Engineer in writing. Note for Item 10.1: Work experience certificate from private individual shall not be considered. However, in addition to work experience certificates issued by any Govt. Organisation, work experience certificate issued by Public listed company having average annual turnover of Rs 500 crore and above in last 3 financial years excluding the current financial year, listed on National Stock Exchange or Bombay Stock Exchange, incorporated/registered at least 5 years prior to the date of closing of tender, shall also be considered provided the work experience certificate has been issued by a person authorized by the Public listed company to issue such certificates. In case tenderer submits work experience certificate issued by public listed company, the tenderer shall also submit along with work experience certificate, the relevant copy of work order, bill of quantities, bill wise details of payment received duly certified by Chartered Accountant, TDS certificates for all payments received and copy of final/last bill paid by company in support of above work experience certificate.
Defination of Similar Work :- Any work involving (a) Construction of bridges including RCC/PSC/ Composite; or (b) Any Rehabilitation work of Bridges.
13 conditions · 3 needing a document upload
As per official Gazette Notification from "The Institute of Chartered Accountants of India( ICAI) (Set up by an Act of Parliament) dated 02/08/2019,Unique Document Identification Number (UDIN) has been made mandatory from 1st July, 2019 for all Audit/Assurance/Attest function.(Official Gazette Notification attached below).'ICAI has conceptualised and implemented an innovative concept called Unique Document Identification Number (UDIN). ICAI at its 379th Council Meeting held on 17th - 18th December, 2018 made generation of UDIN mandatory for every signature of Full time Practising Chartered Accountants in phased manner for the following services: 1) All Certificates with effect from 1st February, 2019 2) GST and Income Tax Audit with effect from 1st April, 2019 3) All Audit and Assurance Functions with effect from 1st July, 2019 Therefore, UDIN is being made mandatory for all Audit and Assurance Functions like Documents and Reports certified / issued by full time Practising Chartered Accountants from 1st July, 2019'.Any document verified by CA but not having UDIN No. (Wherever applicable) shall not be considered.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
The work shall be maintained after completion for a period of 48[Forty Eight] months by the contractor and he shall make good any defects, imperfection shrinkages or faults which may appear at his own cost.
Any firm recognized by Department of Industrial Policy and Promotion (DIPP) as 'Startups' shall be only exempted from payment of Bid Security. Labor Cooperative Societies shall submit only 50% of above Bid Security.
Tenderers are abiding by the General Conditions of Contract (GCC) April-2022 & any statutory modification thereof and also abide to carry out the work accordingly.
Tenderers are requested to visit the web site https//www.ireps.gov.in frequently till the closing date and time for any update.
Tenderer should have to upload only exact & specific, clear and readable documents, irrelevant documents should not be uploaded, and documents uploaded once should not be repeated
Construction of RUB (Box Size 6.0m x 5.50m) at Railway Km 278/5-6 by Pushing Method Between BRB-MLM station in DD-KWV Section under ADEN/KWV/BG. (Deposit Terms)
17-2026-SrDENC
17-2026-SrDENC
Open
Works - General
12 Months
Solapur, Maharashtra
₹0
₹12.8 L
7 Aug 2026
16 Jul 2026
24 Jul 2026
46 items across 3 schedules · ₹6,91,92,931.58 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift. | cum | 10000 | 196 | 19,60,000 |
| 2 | Add for using extra cement in the items of design mix over and above the specified cement content therein. | Quintal | 50 | 733.5 | 36,675 |
| 3 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. | Kg | 15000 | 133.7 | 20,05,500 |
| 4 | Providing and fixing mild steel round holding down bolts with nuts and washer plates complete. | Kg | 600 | 97.2 | 58,320 |
| 5 | 75 mm diameter | Metre | 200 | 248.8 | 49,760 |
| 6 | Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture | Sqm | 1000 | 226.25 | 2,26,250 |
| 7 | Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne capacity after excavating earth to an average of 22.5 cm depth, dressing to camber and consolidating with road roller including making good the undulations etc. and re- rolling the sub grade and disposal of surplus earth with lead upto 50 metres. | Sqm | 1200 | 218.9 | 2,62,680 |
| 8 | 90 mm to 45 mm size stone aggregate | cum | 150 | 2,098.4 | 3,14,760 |
| 9 | 63 mm to 45 mm size stone aggregate | cum | 150 | 1,636.05 | 2,45,407.5 |
| 10 | 53 mm to 22.4 mm size stone aggregate | cum | 150 | 1,842.3 | 2,76,345 |
| 11 | Moorum | cum | 1500 | 768.25 | 11,52,375 |
| 12 | Laying, spreading and compacting stone aggregate of specified sizes to WBM specifications in uniform thickness, hand picking, rolling with 3 wheeled road/vibratory roller 8-10 tonne capacity in stages to proper grade and camber, applying and brooming requisite type of screening / binding material to fill up interstices of coarse aggregate, watering and compacting to the required density . | cum | 1500 | 1,046.95 | 15,70,425 |
| 13 | With road roller/ hand roller | Sqm | 800 | 24.45 | 19,560 |
| 14 | Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size) in pavements, laid to required slope and camber in panels as required including consolidation finishing and tamping complete. | cum | 100 | 7,993.8 | 7,99,380 |
| 15 | Cement concrete prepared with batch mixing machine | cum | 180 | 10,529.35 | 18,95,283 |
| 16 | Stone aggregate 40 mm nominal size | Sqm | 300 | 172.35 | 51,705 |
| 17 | 1200 mm dia RCC pipes. (Laying by manual/ mechanical means) | Metre | 20 | 9,126.2 | 1,82,524 |
| Schedule total | ₹1,11,06,949.5 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
06-PCEcircular207.pdf
ATTACHMENT
07-PCEcir208.pdf
ATTACHMENT
Comprehisnsiveprocedureorderforworksitesafety_compressed.pdf
ATTACHMENT
ssc.pdf
ATTACHMENT
GCC-2022-ACS102_compressed.pdf
ATTACHMENT
GCCACS11_compressed.pdf
ATTACHMENT
SPECIALCONDITIONSOFCONTRACTCIVILWORK10.6.26.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .