Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹1.9 LAccepted-AOC | 1 | Accepted-AOC L1 | |
| 2 | 2₹2.2 L+₹34,590 (18.3%)Rejected-AOC | 2 | Rejected-AOC L2 | |
| 3 | 3₹2.6 L+₹70,110.25 (37.1%)Rejected-AOC 145 1 0 NEAR OLD LIC SHIV NAGAR VILLAGE TOWN MODIPURAM CITY MEERUT MEERUT UTTAR PRADESH 250110 INDIA | MEERUT | UTTAR PRADESH | 250110 | 3 | Rejected-AOC L3 |
Tender Value
Refer Docs
EMD Value
₹3,500
Closing Date
6 May 2021, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Superintending Engineer
Electricity Transmission Circle-II, U.P. Power Transmission Corporation Ltd. 57- George Town, Prayagraj
06/ETC-II(P)/ 2021-2022
2021_UPTCL_584469_1
06/ETC-II(P)/ 2021-2022
Open Tender
Electrical Works
Item Rate
90 days
Koraon
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
EE,ETD-NAINI,PRAYAGRAJ
₹3,500
3 Dec 2021
27 Apr 2021
7 May 2021
27 Apr 2021
6 May 2021
27 Apr 2021
120 days
Amount
Shifting of Main tank of 40 MVA Transformer( Atlanta electricals Make) from unloading place to plinth upto 20 mtr. Distance including turning of tank if required.
Additional shifting of Transformer tank upto 50 mtr distance (1 Job for every 5 mtr.)
Erection of 40 MVA Transformer (Atlanta electricals Make) RTCC Panel including shifting from storage place to control Room.
Complete erection of 40 MVA Transformer (Atlanta electricals Make) including,main tank, Radiators, Conservator Tank , Bushing , Connecting pipe lines , Cooling fans ,Marshaling box , OTI , WTI , Capillary pipes etc.
Centrifuging/Dehydration of the complete Transformer oil of new Transformer by ultra high vacuum oil filtration plant after connecting the centrifuging pipes with Transformer tank to oil filtration plant,Including taking the BDV values of oil and IR values of the Transformer periodically till the required value is achieved. Including filling and topping up of the Transformer oil under vacuum in Main tank , Radiator , Conservator tank,inflation of air cell etc. and attending the oil leakages if any, with all cost of centrifuging machine , CFM operator , Lubricant,nitrogen gas for aircell etc.
Making of Delta for Neutral Earthing by due Fabrication of 3 No. 3 Meter long Electrodes of 36 / 40 mm dia. M.S. Round Bar, its piercing Under the Ground at Equal Distance of 1 Meter at 700 mm depth by digging of earth and Connecting all the 3 No. Electrodes with 75 mm × 10 mm size M.S. Flat and Taking out the M.S. Riser by due Cutting, Bending, Welding etc. of the M.S. Flat. (1 Job per Delta)
Earthing of Main Tank, Marshaling Box, OLTC Drive Mechanism Box, Transformer Neutral etc. of the above 40 MVA Transformer with the help of 75×10 mm / 50×6 mm size M.S. Flats, its Jointing with already Laid Earth Mat / Deltas at 2 Places with Necessary Modifications in Existing Support Structure for Earthing of the Neutral Bushing and then Painting of the Earthing Strips.
Jumpering of new 40MVA Transformer with assocated terminal connector & PG clamps etc. to connect with 132 kV & 33 kV Bus Bar/ CTs/LAs etc:-
HV side with single ACSR Panther Conductor
LV side with Twin ACSR Moose Conductor
Laying of Following sizes Control Cables in Cable Trenches from Marshaling box to RTCC panel ,auxilairy equipment like OSR,PRD,Buchholge relay ,MOG OLTC,MOG etc & C&R panel ,drive mechanism of OLTC to RTCC panel &Control & Relay Panels in Control Room etc. in Switchyard as per Cable Schedule including Shifting of Cables in Drums from Storage Place to the Sub Station Erection Site and Shifting Back the Balance Cables to Stores at the Sub Station:-
Termination of existing control and power cables as per cable schedule of 40 MVA Transformer and its OLTC/ RTCC panels into 40 MVA Transformer at both end and control and Relay panel, cooling fans and pumps, Marshaling box etc.using existing cable including laying, dressing and binding of additional control cables if required as per site requirement and termination along with making necessary holes using glands plate or box where ever required. Fixing of cable glands of appropriate size, providing of ferrules and cable termination as per standard practice and all other associated works as per technical specification .The work also includes assisting in complete testing of transformer.
Sampling of T/F oil , conducting following tests from NABL approved lab prior to commissioning and repeating the same job after 15 days of commisioning of transformer.(01 job for each set of tests) 1. BDV 2. PPM 3. DGA
M/s Mayur Oil Filtration
Hi-tech power transmission
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .