Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹22.3 LAccepted-AOC ACCREDITED ENGINEER BOROBAZAR T D BLOCK | JALPAIGURI | WEST BENGAL | 734001 | ₹22.3 L Quoted ₹27.3 L | L1 | Accepted-AOC L1 bidder |
| 2 | L2₹28.1 L+₹87,094.50 (3.20%)Rejected-Finance | ₹28.1 L+₹87,094.50 (3.20%) | L2 | Rejected-Finance Quoted high |
| 3 | L3₹28.2 L+₹89,344.50 (3.28%)Rejected-Finance | ₹28.2 L+₹89,344.50 (3.28%) | L3 | Rejected-Finance Quoted very high |
Tender Value
₹34.8 L
EMD Value
₹69,560
Closing Date
6 Nov 2023, 3:00 pmClosed
BDO, Sidli-Chirang Dev. Block, Sidli
O/o the BDO, Sidli-Chirang Dev. Block, Sidli
Construction of road with Earth Filling and Sand Gravelling at Thattara Middle village along with 4 Nos of RCC Box Culvert under SOPD for the year during 2023-24.
2023_BoTC_33123_1
BTC/SCDB/03/2023 - 01
Open Tender
Civil Works
Works
180 days
Sidli - Thattara
Please refer Tender documents.
3 documents required · 3 mandatory
₹1,000
₹69,560
Yes
23 Dec 2023
17 Oct 2023
7 Nov 2023
17 Oct 2023
6 Nov 2023
17 Oct 2023
17 Oct 2023 - 6 Nov 2023
Amount
Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement. (I) Private Land
Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. (ii) For Grading II Material
Earthwork in excavation for foundation trenches of walls, retaining walls, footings of column, steps, septic tank etc. including refilling (return filling) the quantity as necessary after completion of work, breaking clods in return filling, dressing, watering and ramming etc. and removal of surplus earth with all lead and lifts as directed and specified in the following classification of soils including bailing out water where necessary as directed and specified. (A) Up to a depth of 3.00m below the existing ground level. (a) In ordinary soil - Manual means(without dewatering)
Sand filling in foundation treaches as per drawing and specifications.
Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone agrregate 40mm nominal size machanically mixed, placed in foundation and compacted by vibration including curing for 14 days.
Plain /Reinforced cement croncrete works in open founation as per drawing and technical specifications A)PCC Grade M-15
Plain /Reinforced cement croncrete works in sub-structure complete as per drawing and technical specifications A)PCC Grade M-15 Height upto 5M
Supplying, fitting and placing of TMT bar (ISI marked) reinforcement in sub-structure complete as per drawing and technical specifications
Providing and laying cement croncrete wearing coat Grade 30 including reinforcement, complete as directed.
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification.
Backfilling behind abutment, wing wall and return wall complete as per drawings & technical specification. Sandy materials
Curtail wall as per drawing and technical specifications, Stone masonry in cement mortar (1:3) complete as directed.
Sola Basumatary
ANSUMWI NARZARY
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .