| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹57.6 LAdmitted-Finance | +8.00% | ₹57.6 L | L1 | Admitted-Finance |
| 2 | L2₹58.7 L+₹1.1 L (1.85%)Admitted-Finance | +10.00% | ₹58.7 L+₹1.1 L (1.85%) | L2 | Admitted-Finance |
| 3 | Rejected-Technical VILLAGE DHANI DULAT DISTT FATEHABAD VILLAGE TIBBI DHANI DULAT DISTT FATEHABAD 125106 | FATEHABAD | FATEHABAD | HARYANA | 125106 | - | - | - | Rejected-Technical Not complied with technical specification |
Tender Value
₹53.3 L
EMD Value
₹1.1 L
Closing Date
29 Jun 2026, 3:00 pmClosed
Sumit Chopra
Municipal Council Fatehabad
Construction of CC Street from H/O Joga Singh to Happy Chugh, Ashok Dhuria to Ricky Chakki wala, Rinku to Harmeet Sardar, Sardar ji to Girdhar Gopal in Bhatta Colony in ward no 21 M.C Fatehabad
2026_HRY_530091_1
20267A3FA58F E341 4654 A238 18FD8993EDCE272ULB
Open Tender
Civil Works
Works
180 days
Fatehabad
first time tender
2 documents required · 2 mandatory
₹5,000
₹1.1 L
Yes
18 Sept 2026
18 Jun 2026
29 Jun 2026
18 Jun 2026
29 Jun 2026
18 Jun 2026
18 Jun 2026 - 20 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | [10.17]Providing and laying polythene sheet under CC M-25 in road and parking complete in all respect [Through Rate] | 0.8 | Sqm | - | - |
| 2 | [17.5.3]Compacting Original Ground 3. Compaction of Earthwork
Compaction of & preparation of sub grade including loosening, levelling of earth 225 mm thick top layer, rough dressing of soil, final dressing of earth to give level, camber, watering, rolling with road roller, compacting the bed to achieve minimum dry density as given in the Table 3000-2 as per technical clause 305 of MORT&H specifications [Through Rate] | 0.4 | Sqm | - | - |
| 3 | [17.70]Removal of existing IPB by manual means and disposal of dismantled material with all lead and lift as per technical specification clause 202.3. [Through Rate] | - | Sqm | - | - |
| 4 | [21.87.1.1]Constructing brick masonry road gully chambers as per standard drawings (as per sizes given below) including dressing of beds and sides of chambers to exact profiles, 15cm thick lime concrete 16:24:100 (as per specified in item No.10.6) in foundations 1st class brick work laid in cement sand mortar 1:5, 40 mm thick cement concrete 1:2:4 topping inside the chamber with a floating coat of 1.5mm thick neat cement laid in one operation to the topping, the entire inner surface of the chamber rendered with neat cement not less than 12mm in thickness of 1:2 cement sand plaster and finished with floating coat of neat cement 1 mm thick left absolutely smooth polished and correct to templates including labour for fixing the C.I. road gully grating and frame including painting with coal tar (as Specified in item No. Item 21.48) complete to the requirement of the Engineer in-charge 1.1. Single road gully chamber - Size: 610mm x 457mm x 800mm [Through Rate] | - | Each | - | - |
| 5 | [21.93.1]Providing and fixing SFRC MANHOLE COVERS AND FRAMES MARKED WITH IS: 12592 including setting the same to correct lines and levels in 1:3 cement sand mortar over manhole including carriage loading unloading stacking handling re-handling etc. complete in all respects to the satisfaction to the Engineer-in-charge. 1. Type:- Extra Heavy Duty Set (EHD-35) 560MM Clear Opening [Through Rate] | - | Each | - | - |
| 6 | [27.51.3]Filler joint 3. Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply supported spans not exceeding 10 m to cater for a horizontal movement up to 20 mm, covered with sealant complete as per drawing and MoRT&H specifications. [Through Rate] | - | Running Metre | - | - |
| 7 | [3.1.18]By Mechanical Transport including loading, unloading and stacking 18. Disposal of moorum/building rubbish/ malba/ similar unserviceable, dismantled or waste material by mechanical transport including loading, transporting, unloading to approved municipal dumping ground for lead up to 10 km for all lifts, complete as per directions of Engineer-in-charge. [Rate] | 0.4 | cum | - | - |
| 8 | [5.23.2]Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. 2. Nominal concrete 1:2:4 or leaner mix (i/c equivalent design mix) [Through Rate] | 0.4 | cum | - | - |
| 9 | [6.1.1]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 1. 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) [Through Rate] | 0.2 | cum | - | - |
| 10 | [6.1.7]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 7. 1:5:10 (1 cement : 5 coarse sand (zone-III): 10 graded stone aggregate 40 mm nominal size) [Through Rate] | 0.8 | cum | - | - |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.70 MB
BOQ_609134.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .