| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹11.4 LAdmitted-Finance | -3.50% | ₹11.4 L | L1 | Admitted-Finance |
| 2 | L2₹11.8 L+₹35,702.68 (3.12%)Admitted-Finance | -0.49% | ₹11.8 L+₹35,702.68 (3.12%) | L2 | Admitted-Finance |
| 3 | L3₹11.8 L+₹38,905.25 (3.40%)Admitted-Finance | -0.22% | ₹11.8 L+₹38,905.25 (3.40%) | L3 | Admitted-Finance |
Tender Value
₹14.0 L
EMD Value
₹1.2 L
Closing Date
8 Jun 2026, 3:00 pmClosed
Executive Engineer
Nagar Nigam Firozabad
CC road improvement work from Bhatia Canteen to Bhura Yadav house, Ward No. 23 Circular Road.
2026_DOLBU_1148317_249
05/PWD_15vitt_Rajvitt/2026-27
Open Tender
Civil Works
Percentage
Firozabad
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,400
Municipal Corporation
₹1.2 L
4 Jul 2026
18 May 2026
8 Jun 2026
18 May 2026
8 Jun 2026
18 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling cement concrete pavement by mechanical means using pneumatic tools, breakingg to pieces not exceeding 0.02 Cum in volume and stock piling at designated locations and disposal of dismantled materials up to a lead of 1000 meters, stacking serviceable and unserviceable materials separately. (PWD SOR 2025-26, Chepter-10, Item No.6 ) | 61.29 | Cum | 690 | ₹42,290.1 |
| 2 | Excavation in foundation in ordinary soil or silt (loam, clay or sand) including lift upto 1.50m and lead up to 30m and including filling watering and ramming of excavated earth in to the trenches or in to the space between the building and the side of foundation trenches or in to the plinth and removal and disposal of surplus earth as directed by the Engineer in charge up to a distance of 30m from the foundation trenches. (PWD SOR 2025-26, Chepter-4, Item No.01 Spec- 251 ). | 48.31 | cum | 150 | ₹7,246.5 |
| 3 | Grandular Sub-base with well Graded Material (Table 400.1)
(A) By Mix in Place Method
Construction of granular sub-base by providing well graded material, spreading in uniform layers wth motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheelo roller to achieve the desired density. complete as per technical spercification clause-401 (As per Analysis). | 67.18 | Cum | 3,234 | ₹2,17,260.12 |
| 4 | RCC work Providing and laying in position specified grade of reinforced cement concrete in Raft foundation, including the cost of centering, shuttering, finishing and excluding reinforcement - All work up to plinth level in :1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) (PWD SOR 2025-26, Chepter-5, Item No.9 Spec. no. 5.1). | 14.76 | cum | 8,100 | ₹1,19,556 |
| 5 | R.C.C work in Wall (any thickness) including attached plasters, buttresses, plinth and string courses, fillers, columns, pillars, abutments, post and struts etc. including the cost of centering, shuttering, finishing and excluding reinforcement All work up to plinth level in 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) upto plinth level (PWD SOR 2025-26, Chepter-5, Item No.9 Spec. no. 5.2) | 16.1 | Cum | 8,300 | ₹1,33,630 |
| 6 | CEMENT CONCRETE PAVEMENT(C.C ROAD) construction of un-reinforced plain cement concrete pavement thickness as per design, over a prepared sub base with 43 grade cement or any other type as per clause 1501.2.2 M 30 (grade) coarse and fine aggregates conforming to IS 383 maximun size of coarse aggregate not exceeding 25mm mixed in a concrete mixer of not less then 0.2 cum capacity and appropriate weight batcher using approved mix design, laid in approved fixed side fromwork .......................... 1501 (approved Quarri grit) (PWD SOR 2025-26, Chepter-12, SI N0-11). | 61.29 | CUm | 7,700 | ₹4,71,933 |
| 7 | RCC work Providing and laying in position specified grade of reinforced cement concrete, Slab including the cost of centering, shuttering, finishing and excluding reinforcement - Above plinth level upto fifth floor level in :1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) (PWDSOR 2025-26 Chapter No-05 Item No.10 Spec. No. 5.1). | 2.18 | Cum | 7,650 | ₹16,677 |
| 8 | M.S or Iron work in plain work such as reinforced concrete or reinforced brick work (When not included in and an over all rates) brought to required shape as necessary of the work and including the suply of steel and its wastage bend, hooks and authorized over lapping shall be measured upto floor to level. (As per Analysis of Rate) | 20.76 | Qtl | 7,800 | ₹1,61,928 |
| 9 | M.S Speciefication Board including painting & writing | 1 | Nos | 4,635 | ₹4,635 |
| 10 | P/F of Inogration Granite stone including writing and | 1 | Nos | 10,980 | ₹10,980 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 11.04 MB
BOQ_2152338.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .