| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹63.0 LAccepted-AOC | ₹63.0 L | L1 | Accepted-AOC L1 |
| 2 | L2₹63.1 L+₹16,757 (0.27%)Rejected-AOC | ₹63.1 L+₹16,757 (0.27%) | L2 | Rejected-AOC L2 |
Tender Value
₹63.6 L
EMD Value
₹1.3 L
Closing Date
9 Aug 2023, 3:00 pmClosed
Additional Collector
DRDA, Cuddalore
Periodic Renewal of L059-Erumanur to Ulundurper Road via chinnvadavadi Road in Vridhachalam block
2022_RDTN_121589_2
DIPR/3802/Tender/2023/ Periodic Renewal
Open Tender
Civil Works - Roads
Item Rate
120 days
Cuddalore
As per tender
5 documents required · 5 mandatory
₹0
₹1.3 L
Yes
DRDA, Cuddalore
21 Dec 2023
25 Jul 2023
9 Aug 2023
25 Jul 2023
9 Aug 2023
27 Jul 2023
27 Jul 2023
Amount
L059-Erumanur to Ulundurper Road via chinnvadavadi km 0/0-3/421 Clearing the light jungle including al labour charges for cutting, burring, buried etc. complete.
Earth work excavation and depositing on bank within initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS .20.A
Providing and laying including cost and conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by power roller to achieve the required Proctor density at 100% compaction at Optimum moisture content and hire fuel charges for powerroller, watersprinkler and all other incidental charges such as traffic barricading and providing dangerlights etc. comp for base-course and side berms. KM 0/0-1/00
Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 50mm using 45mm IRC size HBG metal
Applying tack coat over BT surface (not treated with primer) using 2.5Kg of bituminous emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied departmentally at section stores and cost of which will be recovered at the rates as per special conditions appended herewith including conveyance of bituminous emulsion to actual work spot handling charges including labour charges for brushing, cleaning and preparing the surface for laying the tack coat and labour and machinery charges for applying the required quantity of bituminous emulsion including hire, fuel and running charges for all tools and plants employed for the work including all other incidental charges such as barricading and providing danger lights, flags etc., complete as per standard specification.
BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Provision for White washing for existing Culvert works
Provision for White washing for existing Culvert works
Provision for White washing for existing Culvert works
Provision for Road marking with hot applied thermoplastic compound with Reflectorising Glass beads on Bitumen surface etc.,
Provision for HM Stone
Provision for KM Stone
Providing Repainting informatory board
Provision for Name Board
Towards the charges for routline maintenance of the road work executed under PMGSY including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRCSP- 20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
DEVI CONSTRUCTIONS
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .