| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹26.7 LAdmitted-Finance 104 MITASU MANSION SHANTINAGAR PONDA GOA | SOUTH GOA | GOA | 403103 | -20.00% | ₹26.7 L | L1 | Admitted-Finance |
| 2 | L2₹30.0 L+₹3.3 L (12.5%)Admitted-Finance 146 MORKANI BANDOL VAL DABAL SANVORDEM GOA | SANVORDEM | SOUTH GOA | GOA | -9.99% | ₹30.0 L+₹3.3 L (12.5%) | L2 | Admitted-Finance |
Tender Value
₹33.3 L
EMD Value
₹66,660
Closing Date
18 Sept 2026, 5:00 pmClosed
EXECUTIVE ENGINEER
DIVISION XVI (BLDGS), P.W.D. PONDA GOA
Construction of Primary School stage shed and providing and fixing interlocking pavers in ward no.4 at Kalay Panchayat in Sanvordem Constituency (Under Tribal Sub Plan Scheme).
2026_PWD_31848_1
PWD/DIVISION XVI (BC)/TS/13/2026-2027 Line 02
Open Tender
Civil Works - Buildings
Percentage
30 days
ward no.4 at Kalay Panchayat in Sanvordem
Please refer Tender documents.
2 documents required · 2 mandatory
₹6,000
₹66,660
21 Sept 2026
12 Sept 2026
21 Sept 2026
12 Sept 2026
18 Sept 2026
12 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Earthwork in excavation by mechanical means (hydraulic excavator)/manual means in foundation pipeline trenches drain (not exceeding 1.5 m in width or 10 sq.m. on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m including getting out the excavated soil and disposal of surplus excavated soil as directed within a lead of 50 m. | |||||
| 1.01 | a) All kinds of soil | 18 | cu.m | 291 | ₹5,238 |
| 2 | Rubble packing with hard laterite stone under floors including watering ramming and consolidating etc. in pipeline trenches and other foundations complete. | 80.25 | cu.m | 2,211 | ₹1,77,432.75 |
| 3Providing & laying cement concrete 1:2:4 (1 cement: 2 coarse sand: 4 graded granitic or basaltic stone aggrt. 20 mm. nominal size) excluding cost of centering, shuttering and finishing in: | |||||
| 3.01 | a) All works upto plinth level | 55.82 | cu.m | 6,810 | ₹3,80,134.2 |
| 4Providing and laying in position (1:11/2:3) Reinforced cement conrete excluding the cost of centering, shuttering, finishing and reinfrocement (1 cement: 1½ coarse sand:3 graded stone agg 20mm nominal size) | |||||
| 4.01 | a) All works upto plinth level | 9.45 | cu.m | 7,178 | ₹67,832.1 |
| 5 | Kotah stone slab flooring over 25 mm thick in risers of steps, skirtings, dado & pillars laid on 12mm (average) thick cement mortor 1:3 (1 cement : 3 coarse sand) & jointed with grey cement slurry mixed with pigment to match the shade of the slab including rubbing & polishing complete. | 64.26 | sq.m | 1,668 | ₹1,07,185.68 |
| 6Centering & shuttering including Strutting, Propping & removal of forms for : | |||||
| 6.01 | a) Foundations, Footings, Bases for columns | 54 | sq.m | 407 | ₹21,978 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.93 MB
BOQ_32229.xls
BOQ • 0.40 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .