Tender Value
₹10.5 L
EMD Value
₹10,500
Closing Date
30 Aug 2024, 3:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Block Development Officer (BP)
Block Development Officer (BP) Panchayat Union, Annavasal
Construction of Angadi at Vellanur in Vellanur Pt.
2024_RDTN_476755_1
2809/2023/A2 Dt.23.08.2024
Open Tender
Civil Works
Item Rate
180 days
Annavasal
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹10,500
Yes
30 Aug 2024
27 Aug 2024
30 Aug 2024
27 Aug 2024
30 Aug 2024
27 Aug 2024
27 Aug 2024 - 30 Aug 2024
Amount
Construction of Angadi at Vellanur in Vellanur panchayat.
Earth work excavation and depositing on bank with initial lead and lift in hard stiff clay soil and hard gravel soil as per standard specification SS20 B for narrow foundation.
supplying and filling in Excavated soil including all cost and conveyance and all labour charges etc , complete standard specification.
Sand filling with M- sand including cost and conveyance of all materials to site and all labour charges etc., complete.
Cement Concrete 1:4:8 mix using 40mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc., complete.
Brick Work in Cement Mortor 1:5 mix using courntry bricks including cost and conveyance of all materials to site and all labour charges etc., complete
Reinforced Cement Concrete 1:1.5:3 mix for RCC using 20mm ISS BG metal including cost and conveyance of all materials to site including all labour charges for filling etc complete.
Supplying and fabrication of steel including cost and conveyance and all labour charges etc., complete.
Centering for Sides and soffits including cost and conveyance and all labour charges etc., complete. Below gl
Centering for Sides and soffits including cost and conveyance and all labour charges etc., complete. Above GL
Plastering with cement mortor 1:5 (one cement and five sand) 12mm thick in all floor including curing etc. complete complying with standard specification.
Special ceiling plastering with cement mortor 1:3 mix to 10mm thick including cost and conveyance of all materials to site and all labour charges etc. complete.
Floor finish with granolethicpattern in cement concrete 1:2:4 mix using 10-12mm ISS metal to 25mm thick including cost and conveyance of all materials to site and all labour charges for mixing, laying, curing etc complete
White washing TWO coat using best freshly burnt white shell lime in all the floors, including cost of lime blue powder, fevicol type gums, brushes, scaffolding charges etc., complete with standard specification.
Distembering two coats with best approved distember including cost and conveyance of all materials to site and all labour charges etc complete
Painting two coats with exterior emulsion including cost and conveyance of all materials to site and all labour charges etc complete
Painting with 2 coats of new iron work including cost and conveyance of all labour charges etc.,complete.
Weathering course with one course of pressed tiles including cost and conveyance of all materials to site and all labour charges etc.,complete.
Finished with one course of pressed tiles of size 23x23x2cm with cement mortar 1:3 mix and pointed with the same oiled mortar including cost and conveyance of all materials to site and all labour charges etc complete for 10 Sqm
Supply and delivery of rolling shutter size 1.80x2.10
Supply and delivery of steel window size 0.90x1.20
Supply and delivery of ventilator size 0.90x.0.45
Supply and delivery Indian type Water Closet
Supply and fixing of toilet door 0.75x1.80
Provision for 500 Lr Sintex tank
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
M. SENTHILKUMAR (BID ID -1124571)
stage.html
html • 0.02 MB
tech_bid_open.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .