Tender ID
Tender Value
₹9.3 L
EMD Value
₹21,998
Closing Date
24 Mar 2026, 6:55 pmClosed
Pankaj Garg
Municipal Committee Bawani Khera
2nd time tender for Construction of Hall in Maharana partap Community Centre at MC Bawani khera
2026_HRY_508990_1
2026F75329C8 C9F9 4BC8 AB3C 87E7F3D9CA6E343ULB
Open Tender
Civil Works
Works
240 days
Bawani Khera
2 documents required · 2 mandatory
₹1,000
₹21,998
Yes
17 Mar 2026
17 Mar 2026
25 Mar 2026
17 Mar 2026
24 Mar 2026
17 Mar 2026
HSR Item 6.15.1-Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor four level, excluding cost of centering, shuttering, finishing and reinforcement : 1. 1:1.5:3 (1 cement : 1.5 coarse sand(zoneIII) : 3 graded stone aggregate 20 mm nominal size) HSR Rate(Rs.) 5969.00 Through Rate
HSR Item 10.100.2-Cement Concrete 1:8:16 Flooring 2. Cement Concrete 1:8:16 with stone aggregate 40 mm size in foundation and plinth. HSR Rate(Rs.) 1863.00 Through Rate
HSR Item 17.69.3-Interlocking Concrete Block Pavement 3. Providing and Laying 60 mm thick ISI marked Interlocking Paver Blocks conforming to IS 15658:2006/IRC SP 63: 2004 of all shapes and colours in design mix cement M 35 over the bed of 25 mm thick fine sand complete in all respect. HSR Rate(Rs.) 576.00 Through Rate
HSR Item 7.21.2-Brick work with common burnt clay nonmodular bricks of class designation 10.5 in foundation and plinth in: 2. Cement mortar 1:6 (1 cement : 6 coarse sand) HSR Rate(Rs.) 3968.00 Through Rate
HSR Item 4.14.1-Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 1. All kinds of soil. HSR Rate(Rs.) 83.00 Through Rate
HSR Item 6.1.6-Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 6. 1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) HSR Rate(Rs.) 2442.00 Through Rate
HSR Item 6.34.6-Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect above plinth level Note:- Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 6. Thermo-Mechanically Treated bars of grade Fe-500D or more. HSR Rate(Rs.) 68.00 Through Rate
HSR Item 4.33-Excavating, supplying and filling of local earth (including royalty) by mechanical transport up to a lead of 1 km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth, sides of foundation etc. complete. HSR Rate(Rs.) 138.00 Through Rate
HSR Item 3.1.2-By Mechanical Transport including loading, unloading and stacking 2. Earth HSR Rate(Rs.) 83.00 5km
HSR Item 10.1-Providing and laying of base course of floors consisting of 100 mm thick cement 1:8:16 and 100 mm sand or stone filling. HSR Rate(Rs.) 260.00 Through Rate
HSR Item 10.37.1-Providing and fixing of Kota stone slab flooring over 20 mm (average) thick base laid over and jointed with grey cement slurry mixed with pigment to match the shade of the slab, including rubbing and polishing complete with base of cement mortar 1 : 4 (1 cement : 4 coarse sand) : 1. 25 mm thick HSR Rate(Rs.) 790.00 Through Rate
HSR Item 7.22.1-Brick work with common burnt clay nonmodular bricks of class designation 10.5 in superstructure above plinth level up to floor IV level in all shapes and sizes in : 1. Cement mortar 1:4 (1 cement : 4 coarse sand) HSR Rate(Rs.) 4404.00 Through Rate
HSR Item 9.14.1-Providing and laying brick tiles over mumty roofs, grouted with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement, over 12 mm layer of cement mortar 1:3 (1 cement : 3 fine sand) and finished neat: 1. With common burnt clay non-modular brick tiles of class designation 10 HSR Rate(Rs.) 374.00 Through Rate
HSR Item 11.26.1-Pointing on tile brick work with cement mortar 1:3 (1 cement : 3 fine sand): 1. Flush/ Ruled/ Struck or weathered pointing HSR Rate(Rs.) 86.00 Through Rate
HSR Item 9.17.1-Providing gola 75x75 mm in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 stone aggregate 10 mm and down gauge), including finishing with cement mortar 1:3 (1 cement : 3 fine sand) as per standard design : 1. In 75x75 mm deep chase HSR Rate(Rs.) 112.00 Through Rate
HSR Item 6.30.5-Centering and shuttering including strutting, propping etc. and removal of form for 5. Lintels, beams, plinth beams, girders, bressumers and cantilevers HSR Rate(Rs.) 296.00 Through Rate
HSR Item 6.14.1-Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1. 1:1.5:3 (1 cement : 1.5 coarse sand (zoneIII): 3 graded stone aggregate 20 mm nominal size) HSR Rate(Rs.) 4374.00 Through Rate
HSR Item 7.21.1-Brick work with common burnt clay nonmodular bricks of class designation 10.5 in foundation and plinth in: 1. Cement mortar 1:4 (1 cement : 4 coarse sand) HSR Rate(Rs.) 4128.00 Through Rate
HSR Item 6.30.6-Centering and shuttering including strutting, propping etc. and removal of form for 6. Columns, Pillars, Piers, Abutments, Posts and Struts HSR Rate(Rs.) 262.00 Through Rate
HSR Item 6.16-Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor four level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size). HSR Rate(Rs.) 6113.00 Through Rate
HSR Item 9.57.2-Providing and fixing on wall face Unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion, (i) Single socketed pipes. 2. 110 mm diameter HSR Rate(Rs.) 200.00 Through Rate
HSR Item 6.30.3-Centering and shuttering including strutting, propping etc. and removal of form for 3. Suspended floors, roofs, landings, balconies and access platform HSR Rate(Rs.) 208.00 Through Rate
HSR Item 6.30.1-Centering and shuttering including strutting, propping etc. and removal of form for 1. Foundations, footings, bases of columns, etc. for mass concrete HSR Rate(Rs.) 156.00 Through Rate
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.88 MB
BOQ_587764.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .