| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.3 CrAccepted-AOC AT PO PS BEHERA SAHI CHOUDWAR DIST CUTTACK | CUTTACK | ODISHA | 752120 | ₹1.3 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹1.3 CrSame as L1Rejected-Finance | ₹1.3 CrSame as L1 | L2 | Rejected-Finance HIGHEST |
| 3 | L3₹1.3 CrSame as L1Rejected-Finance RAJABAGICHA LABOUR COLONY PO TELENGA BAZAR DIST CUTTACK | CUTTACK | CUTTACK | ODISHA | ₹1.3 CrSame as L1 | L3 | Rejected-Finance HIGHEST |
Tender Value
₹1.3 Cr
EMD Value
₹1.3 L
Closing Date
28 May 2026, 5:00 pmClosed
EXECUTIVE OFFICER
CHOUDWAR
Construction of Urban Hata in Ward No 16 Under Choudwar Municipality
2026_ORULB_128890_1
CHM-3/2026-27
Open Tender
Civil Works - Others
Percentage
CHOUDWAR
Please refer Tender documents.
2 documents required · 2 mandatory
₹11,800
₹1.3 L
Yes
2 Jul 2026
7 May 2026
29 May 2026
7 May 2026
28 May 2026
7 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work excavation in all kind of soil within initial lead of 50 m and initial lift of 1.5 m including rough dressing and leveling the bed...etc complete in all respect and as per the direction of Engineer-in-charge. | 174.33 | cum | 299.5 | ₹52,211.84 |
| 2 | Supplying, & filling in foundation and plinth with good quality river sand including watering, ramming with cost, conveyance, royalties, taxes of all materials and cost of all labour with T&P, sundries required for the work etc., complete (Measurement will be taken on finished compacted section) as per specification and direction of Engineer-in-charge. | 342.75 | cum | 643.3 | ₹2,20,491.07 |
| 3 | C.C (1:4:8) with 4cm size HG Crusher BROKEN metal including all cost, conveyance,royalty & taxes etc.comp.to work site as per specification approved by the department & direction of E.I.C. | 92.35 | cum | 5,737.8 | ₹5,29,885.83 |
| 4 | Brick work with Fly Ash bricks of size 25cmx12cmx8cm and crushing strength not less than 75 kg/cm2 in C.M.(1:4) in foundation and plinth including all charges. | 128.22 | cum | 5,719.3 | ₹7,33,328.65 |
| 5 | Providing, lifting, hoisting and laying Reinforced Cement Concrete of M-25 grade in Column base, Column Footings, Raft Foundation,Stem of the Columns, beams, chaujja, fin, lintel, stair case, jali , shelves and slab etc as per approved designs and drawings having a minimum compressive strength ( in work test) 20N. / Square mm. in 15 cm. cubes at 28 days after mixing and test conducted in accordance with I.S. 456 and I.S. 516 using screened & washed sharp river sand for mortar and 10 mm. to 20 mm. size black hard crusher broken granite stone chips of approved quality from approved quarry, washed and cleaned to be mixed in concrete mixture with approved quality of cement including hoisting, lowering, laying and compacting concrete by using vibrators, watering and curing for 28 days including, centering and shuttering then after dismantling and removing the debrises away from the work site and finishing the exposed surface smooth providing grooves or beads wherever necessary including cost, conveyance, loading, unloading, royalties and taxes of all materials , cost of all labours, scaffolding, sundries, T&P required for the work etc. complete in all respect but the excluding cost & conveyance of M.S. rods or Tor Steel and Binding wires and labour charges for straightening, cutting, bending etc. of M.S. rods or Tor steel and binding wires and tying the grills and placing in proper position as directed by the Engineer-in-charge. (Footing) | 11.5 | cum | 6,558.2 | ₹75,419.3 |
| 5.1 | Coloumn | 12.78 | cum | 6,558.2 | ₹83,813.8 |
| 6 | Providing and fixing Centering and shuttering including strutting, propping etc. and removal of form the site after completion of respective work as the direction of engineer in charge.(Footing) | 102.24 | sqm | 248.7 | ₹25,427.09 |
| 6.1 | Column | 170.4 | sqm | 1,204.5 | ₹2,05,246.8 |
| 7 | Cutting,Straightening coiled or bent up M.S plain HYSD/TMT reinforcement bars welding or jointing if necessary bending,binding,tying the grills as required for R.C.C works,providing fan hooks where necessary and hoisting, lowering and placing in proper position according to approved designs and drawings including cost, conveyance,loading, unloading & taxes of M.S plain/HYSD/TMT reinforcement bars and binding wires of 18 to 20 gaugo required for the work and cost of all labour, sundries, T&P and scaffolding complete in all respect as directed by the Engineer in charge (payment will be made according to the actual weight of M.S plain/HYSD/TMT reinforcement bars consumed in the work only. | 28.66 | qntl | 9,250.8 | ₹2,65,127.93 |
| 8 | Providing 12mm thick cement plaster in cement mortar (1:6) in all floors finished smooth to out side smooth surface of brick walls after racking out joints, scrapping & cleaning the surface & finishing the plaster surface smooth using wooden float only to proper plumbs & level and making necessary grooves, beads & drip course to give required ornamental finish as per drawing, watering, curing, scaffolding, screening sand etc. complete with cost, conveyances, royalties, taxes of all materials and cost of all labour with T&P, sundries required for the work etc. complete as per specification & direction of Engineer-in-charge. | 325.9 | sqm | 187.8 | ₹61,204.02 |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.88 MB
BOQ_589948.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .