| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹3.2 CrAdmitted-Finance H NO 73 OLD A G CO OPERATIVE SOCIETY RANCHI JHARKHAND 834002 | RANCHI | RANCHI | JHARKHAND | 834002 | -0.50% | ₹3.2 Cr | L1 | Admitted-Finance |
| 2 | L2₹3.2 CrAdmitted-Finance | +0.00% | ₹3.2 Cr | L2 | Admitted-Finance |
| 3 | Rejected-Technical | - | - | - | Rejected-Technical NON RESPONISVE |
| 4 | Rejected-Technical CHATRA | JHARKHAND | 825103 | - | - | - | Rejected-Technical NON RESPONISVE |
| 5 | Rejected-Technical BARHAIT SAHIBGANJ GODDA JHARKHAND 816102 UDYAM JH 21 0012278 | SAHEBGANJ | JHARKHAND | 816102 | - | - | - | Rejected-Technical NON RESPONISVE |
Tender Value
₹3.3 Cr
EMD Value
₹6.6 L
Closing Date
18 Aug 2026, 5:00 pmClosed
DISTRICT ENGINEER
db chatra
Construction of Hostel Building At-Kasturba Gandhi Balika Vidyalaya, At-Vill-Kunda, Block-Kunda
2026_ZPCHT_116984_1
NIT-37/26-27, GR NO. 02
Open Tender
Civil Works
Works
540 days
kunda
Please refer Tender documents.
2 documents required · 2 mandatory
₹10,000
₹6.6 L
24 Aug 2026
10 Aug 2026
20 Aug 2026
12 Aug 2026
18 Aug 2026
12 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling plain cement or lime concrete work including stacking of serviceable material in countable stacks within 15m lead and disposal of unserviceable materials with all leads all complete as per the direction of E/I. | 1,998.31 | cum | 955.89 | ₹19,10,164.55 |
| 2 | Dismantling R.C.C. work including stacking of serviceable material in countable stacks within 15m lead and disposal of unserviceable materials with all leads all complete as per the direction of E/I. | 314.93 | cum | 1,993.04 | ₹6,27,668.09 |
| 3 | Dismantling pucca brick or lime work including stacking of serviceable material in countable stacks within 15m lead and disposal of unserviceable materials with all leads all complete as per the direction of E/I. | 225.38 | cum | 541.67 | ₹1,22,081.58 |
| 4 | Earth work in excavation in foundation trenches in Hard soil (vide classification of soil item-A) and disposal of excavated earth as obtained to a distance up to 50 M. including all lifts, leveling, ramming the foundation trenches, removing roots of trees,, shrubs all complete as per approved design, building specification and direction of E/I.
Extra for earthwork in hard soil as per specification and direction of E/I (Vide classification of soil item_B) | 326.98 | cum | 167.33 | ₹54,713.56 |
| 5 | Filling in foundation trenches and plinth in layers not exceeding 150 mm. thick well watered, rammed, fully compacted and fine dressed with earth obtained from excavation of foundation trenches within a lead of 50 M and lift of 1.5 M all complete as per building specification and direction of E/I (Mode of measurement compacted volume). | 195.5 | cum | 55.28 | ₹10,807.24 |
| 6 | Providing designation 75A one brick flat soling joints filled with local sand including cost of watering texes royalty all complete as per building specification and direction of E/I. | 134.89 | sqm | 356.52 | ₹48,090.98 |
| 7 | Providing coarse clean sand in filling in foundation trenches or in plinth & floor including ramming & watering in layers not exceeding 150mm thick with all leads and lifts including cost of all materials, labour, royalty and taxes all complete as per building specification and direction of E/I. (Mode of measurement compacted volume). | 79.36 | cum | 589.51 | ₹46,783.51 |
| 8 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering.
All work up to plinth level:
1:3:6 (1 cement: 3 coarse sand (zone-III):6 graded stone aggregate 20 mm nominal size) | 12.13 | cum | 4,125.41 | ₹50,041.22 |
| 9 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering.
All work up to plinth level:
1:2:4 (1 cement: 2 coarse sand (zone-III):4 graded stone aggregate 20 mm nominal size) | 83 | cum | 4,598.23 | ₹3,81,653.09 |
| 10 | Making plinth protection 50mm thick of cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) over 75mm thick bed of dry brick ballast 40mm nominal size, well rammed and consolidated and grouted with fine sand, including necessary excavation, levelling & dressing & finishing the top smooth. | 163.32 | sqm | 351.75 | ₹57,447.81 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.44 MB
SBD.pdf
Tender Documents • 7.26 MB
BOQ_158115.xls
BOQ • 0.50 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].