| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.1 CrAccepted-AOC | ₹1.1 Cr | L1 | Accepted-AOC Quoted Lowest rate and
Executed Agreement on 03.10.2022 after negotiation |
| 2 | L2₹1.1 Cr+₹5.5 L (5.09%)Rejected-Finance | ₹1.1 Cr+₹5.5 L (5.09%) | L2 | Rejected-Finance L2 |
Tender Value
₹1.1 Cr
EMD Value
₹1.1 L
Closing Date
28 Jul 2022, 3:00 pmClosed
Additional Collector (Dev)/Project Director, DRDA
O/O AC (D) / PD DRDA Thoothukudi
Thoothukudi Dt AGAMTII 21-22 Pkg NoTN/TUT-39/22-23 Rejuvenation of Water Bodies - In Theethampatti Iluppaiyurani Duraiyur Inam Maniyachi Manjanaickkanpatti R.Venkatesapuram Chathirapatti and Mooppanpatti Village Panchayat in Kovilpatti Block
2022_RDTN_237656_40
AC(D)/PD,DRDA,Tuty,Lr.No A3/2573/2022 dt.20.06.202
Open Tender
Civil Works
Item Rate
180 days
Thoothukudi District
As per Tender Schedule
4 documents required · 4 mandatory
₹0
₹1.1 L
O/O AC (D) / PD DRDA Thoothukudi
24 Nov 2022
8 Jul 2022
28 Jul 2022
8 Jul 2022
28 Jul 2022
8 Jul 2022
8 Jul 2022
Amount
Desilting of inlet supply channel ( 1km ) ( Survey No : 340/1 ) of Karisalkulam kanmai Oorani, Construction of bathing Ghat and Improvements of Oorani bund at Theethampatti Village and Panchayat) in Kovilpatti Panchayat Union of Thoothukudi District under AGAMT –II 2021-22. Package No TN/TUT-39/2022-23
Earth work excavating and depositing on bank with initial lead of 10 m & initial lift of 2m in Hard stiff clay, stiff black cotton, hard red earth, shales,murram, gravel, stoney
SDR - (Not Requiring Blasting) Earth work excavating and depositing on bank with initial lead of 10 m & initial lift of 2m in Soft disintegrated rock, laterite, soft rock or kankar,not requiring blasting.
Earth work in all soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 to 100 metre deploying earth moving machinery and tippers including benching, formation of bunds, breaking clods,sectioning etc., complete
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Random rubble masonry in cement mortar 1:5 mix with simultaneous pointing including cost and conveyance pf all materials to site and all labour charges etc complete.
Gravel backing for revetments including cost and conveyance and all labour charges etc complete - 10 cum.
Rough stone dry packing for aprons and revetments including cost and conveyance and all labour charges etc complete
Plastering with cement mortar 1:4 mix to 20 mm thick including cost and conveyance and all labour charges etc complete
Towards cost for RCC 900mm dia pipe including cost and conveyance and all labour charges etc complete
Bhathing Ghat ( Sub Estimate )
Earth work excavation in all soils such as red earth ,hard stiff clay soil, stiff black cotton soil, hard redearth,shales, murrams, gravel,hard rock not requiring blasting ete complete.,SS 20 B
Cement concrete 1:4:8 mix usin 40 mm HBGS metal inculding cost and coveyance of all materials to site including labour for mixing , laying,curing etc complete.,
Supplying errction of Centering for cover slab and sids using steel shetters and country wood propos including hire and conveyance of all materials to site and all labour charges etc complete.
Cement concrete 1:3:6 mix usin20 mm HBGS metal inculding cost and coveyance of all materials to site including labour for mixing , laying,curing etc complete.,
Protective Wall ( SUB ESTIMATE )
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 B
Cement concrete 1:4:8 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, aying and curing etc complete
Deepening and Strengthening of Maravankulam MI Tank ( Survey No : 9 ) and Construction of Retaining Wall at Koosalipatti village in Illupaiyoorani Panchayat
Clearing Light Jungle without alignment and uprooting of wild vegetation, bushes, shrubs, saplings and trees of girth upto 300mm for the strengthening of the bund and the ground shall be left in a perfectly clean condition etc., complete.
Earth work in all Soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 to 100m deploying earth moving machinery and tippers including benching, formation of bunds, breaking clods, sectioning etc., complete.
Construction of Retaining Wall (Sub Estimate)
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 B
Cement concrete 1:4:8 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Cement concrete 1:3:6 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Supplying and errecting centering for sides of protection wall including necessary supports and without shrutting etc complete
Deepening and strengthing of Duraiyoor Oorani (Survey No: 427/1) and Construction of bathing ghat at Duraiyoor Oorani in Duraiyoor Village
Earth work excavating and depositing on bank with initial lead of 10 m & initial lift of 2m in Hard stiff clay, stiff black cotton, hard red earth, shales,murram, gravel, stoney
SDR - (Not Requiring Blasting) Earth work excavating and depositing on bank with initial lead of 10 m & initial lift of 2m in Soft disintegrated rock, laterite, soft rock or kankar,not requiring blasting.
Earth work in all soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 to 100 metre deploying earth moving machinery and tippers including benching, formation of bunds, breaking clods,sectioning etc., complete
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Random rubble masonry in cement mortar 1:5 mix with simultaneous pointing including cost and conveyance pf all materials to site and all labour charges etc complete.
Gravel backing for revetments including cost and conveyance and all labour charges etc complete - 10 cum.
Rough stone dry packing for aprons and revetments including cost and conveyance and all labour charges etc complete
Plastering with cement mortar 1:4 mix to 20 mm thick including cost and conveyance and all labour charges etc complete
Towards cost for RCC 900mm dia pipe including cost and conveyance and all labour charges etc complete
Bhathing Ghat ( Sub Estimate )
Earth work excavation in all soils such as red earth ,hard stiff clay soil, stiff black cotton soil, hard redearth,shales, murrams, gravel,hard rock not requiring blasting ete complete.,SS 20 B
Cement concrete 1:4:8 mix usin 40 mm HBGS metal inculding cost and coveyance of all materials to site including labour for mixing , laying,curing etc complete.,
Supplying errction of Centering for cover slab and sids using steel shetters and country wood propos including hire and conveyance of all materials to site and all labour charges etc complete.
Cement concrete 1:3:6 mix usin20 mm HBGS metal inculding cost and coveyance of all materials to site including labour for mixing , laying,curing etc complete.,
Protective Wall ( SUB ESTIMATE )
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 B
Cement concrete 1:4:8 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, aying and curing etc complete
Deepening and Strengthening of Karisalkulam Kanmai and supply Channel ( 400 m ) ( Survey No : 53 ) at Inam Maniyachi Village
Clearing Light Jungle without alignment and uprooting of wild vegetation, bushes, shrubs, saplings and trees of girth upto 300mm for the strengthening of the bund and the ground shall be left in a perfectly clean condition etc., complete.
Earth work in all Soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 to 100m deploying earth moving machinery and tippers including benching, formation of bunds, breaking clods, sectioning etc., complete.
Construction of Toe Wall (Sub Estimate)
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 B
Cement concrete 1:4:8 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Cement concrete 1:3:6 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Cement concrete 1:2:4 mix using 20 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Supplying and errecting centering for sides of protection wall including necessary supports and without shrutting etc complete
Construction of Retaining wall (39 m) at Karisal kulam kanmai in Inam Maniyachi village and Panchayat
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 B
Collection and supply of sand and filling in to the basement including cost and conveyance to the siteand all labour charges for filling as per standard specifications
Cement concrete 1:4:8 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Cement concrete 1:3:6 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Supplying and errecting centering for sides of protection wall including necessary supports and without shrutting etc complete
Deepening and Strengthening of Manthai Veli Oorani ( Survey No : 371 ) & Construction of Bathing ghat and Retaining Wall
Earth work excavating and depositing on bank with initial lead of 10 m & initial lift of 2m in Hard stiff clay, stiff black cotton, hard red earth, shales,murram, gravel, stoney
SDR - (Not Requiring Blasting) Earth work excavating and depositing on bank with initial lead of 10 m & initial lift of 2m in Soft disintegrated rock, laterite, soft rock or kankar,not requiring blasting.
Earth work in all soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 to 100 metre deploying earth moving machinery and tippers including benching, formation of bunds, breaking clods,sectioning etc., complete
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Random rubble masonry in cement mortar 1:5 mix with simultaneous pointing including cost and conveyance pf all materials to site and all labour charges etc complete.
Gravel backing for revetments including cost and conveyance and all labour charges etc complete - 10 cum.
Rough stone dry packing for aprons and revetments including cost and conveyance and all labour charges etc complete
Plastering with cement mortar 1:4 mix to 20 mm thick including cost and conveyance and all labour charges etc complete
Towards cost for RCC 900mm dia pipe including cost and conveyance and all labour charges etc complete
Bhathing Ghat ( Sub Estimate )
Earth work excavation in all soils such as red earth ,hard stiff clay soil, stiff black cotton soil, hard redearth,shales, murrams, gravel,hard rock not requiring blasting ete complete.,SS 20 B
Cement concrete 1:4:8 mix usin 40 mm HBGS metal inculding cost and coveyance of all materials to site including labour for mixing , laying,curing etc complete.,
Supplying errction of Centering for cover slab and sids using steel shetters and country wood propos including hire and conveyance of all materials to site and all labour charges etc complete.
Cement concrete 1:3:6 mix usin20 mm HBGS metal inculding cost and coveyance of all materials to site including labour for mixing , laying,curing etc complete.,
Retainingwall ( Sub Estimate )
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 B
Collection and supply of sand and filling in to the basement including cost and conveyance to the siteand all labour charges for filling as per standard specifications
Cement concrete 1:4:8 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Cement concrete 1:3:6 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Supplying and errecting centering for sides of protection wall including necessary supports and without shrutting etc complete
Deepening and Strengthening of North Oorani ( Survey No : 291 ) and Construction of Retaining wall, Protective wall for Baby pond at R.Venkateshwarapuram Village
Clearing Light Jungle without alignment and uprooting of wild vegetation, bushes, shrubs, saplings and trees of girth upto 300mm for the strengthening of the bund and the ground shall be left in a perfectly clean condition etc., complete.
Earth work in all Soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 to 100m deploying earth moving machinery and tippers including benching, formation of bunds, breaking clods, sectioning etc., complete.
Construction of Retaining Wall (Sub Estimate)
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 B
Collection and supply of sand and filling in to the basement including cost and conveyance to the siteand all labour charges for filling as per standard specifications
Cement concrete 1:4:8 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Cement concrete 1:3:6 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Supplying and errecting centering for sides of protection wall including necessary supports and without shrutting etc complete
Construction of baby pond protective wall
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 B
Cement concrete 1:4:8 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Random rubble masonry in cm 1:5 for foundation and basement simultaneously with flush pointig including all cost and convenyence of materials all labour charges etc complete as per standard specification
Deepening and Strengthening of Neravi Oorani ( Survey No: 127 ) and Construction of Bathing ghat in Chatrapatti Panchayat
Clearing Light Jungle without alignment and uprooting of wild vegetation, bushes, shrubs, saplings and trees of girth upto 300mm for the strengthening of the bund and the ground shall be left in a perfectly clean condition etc., complete.
Earth work in all Soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 to 100m deploying earth moving machinery and tippers including benching, formation of bunds, breaking clods, sectioning etc., complete.
Protective Wall ( SUB ESTIMATE )
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 B
Cement concrete 1:4:8 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Cement concrete 1:3:6mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, aying and curing etc complete
Bhathing Ghat ( SUB ESTIMATE )
Earth work excavation in all soils such as red earth ,hard stiff clay soil, stiff black cotton soil, hard redearth,shales, murrams, gravel,hard rock not requiring blasting ete complete.,SS 20 B
Cement concrete 1:4:8 mix usin 40 mm HBGS metal inculding cost and coveyance of all materials to site including labour for mixing , laying,curing etc complete.,
Supplying errction of Centering for cover slab and sids using steel shetters and country wood propos including hire and conveyance of all materials to site and all labour charges etc complete.
Cement concrete 1:3:6 mix usin20 mm HBGS metal inculding cost and coveyance of all materials to site including labour for mixing , laying,curing etc complete.,
Retaining Wall ( SUB ESTIMATE )
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 B
Cement concrete 1:4:8 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Cement concrete 1:3:6 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Supplying and errecting centering for sides of protection wall including necessary supports and without shrutting etc complete
Deepening and Strengthening of Mayana Oorani ( Survey No : 167/3 ) and Construction of Retaining wall at Moopanpatti Village
Clearing Light Jungle without alignment and uprooting of wild vegetation, bushes, shrubs, saplings and trees of girth upto 300mm for the strengthening of the bund and the ground shall be left in a perfectly clean condition etc., complete.
Earth work in all Soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 to 100m deploying earth moving machinery and tippers including benching, formation of bunds, breaking clods, sectioning etc., complete.
Construction of Retaining Wall (Sub Estimate)
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 B
Cement concrete 1:4:8 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Cement concrete 1:3:6 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Supplying and errecting centering for sides of protection wall including necessary supports and without shrutting etc complete
Protective Wall ( SUB ESTIMATE )
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 B
Cement concrete 1:4:8 mix using 40 mm ISS HBG metal including all cost and conveyance of materials, labour charges such as compaction, curing, etc., complete as per standard specification.
Cement concrete 1:3:6mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, aying and curing etc complete
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
ANNAMALAIYAR BUILDERS
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .