| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹9.9 CrAccepted-Finance KH NO 17 B H U NO 74A KAUSHALPURI COLONY KHARGAPUR GOMTINAGAR LUCKNOW U P | L1 | Accepted-Finance 1st Lowest | |
| 2 | L2₹10.4 Cr+₹51.1 L (5.18%)Rejected-Finance PLOT NO 63 PAHADIYAN DISTRICT VARANASI UTTAR PRADESH | VARANASI | UTTAR PRADESH | 221001 | L2 | Rejected-Finance 2nd Lowest | |
| 3 | L3₹10.5 Cr+₹59.0 L (5.98%)Rejected-Finance CHANDAULI | UTTAR PRADESH | 221009 | L3 | Rejected-Finance 3rd Lowest |
| Sl No | Description | Qty | Unit | S.P.R.U INFRATECH PRIVATE LIMITED L2 | ARVIND KUMAR SINGH L3 | M/S NARAYAN ENTERPRISES L1 |
|---|---|---|---|---|---|---|
| 1.00 | Dismantling brick work, stone work in lime or cement mortar including stacking of materials within a distance of 60 m. As per direction of engineer in-charge. | 514.8 | Cum | 428 ₹2,20,334.4 | 445 ₹2,29,086 | 425 ₹2,18,790 Lowest |
| 2.00 | Dismantling reinforced cement concrete 1:2:4 including stacking of dismantled materials within a distance of 60m. As per direction of engineer in-charge. | 97.6 | Cum | 730 ₹71,248 Lowest | 880 ₹85,888 | 850 ₹82,960 |
| 3.00 | Earth work in foundation including all lead, lift, labour complete. As per direction of engineer in-charge. | 10,987.33 | Cum | 95 ₹10,43,796.35 Lowest | 105 ₹11,53,669.65 | 99 ₹10,87,745.67 |
| 4.00 | Laying Plain Cement Concrete in 1:2:4 with maximum size of 20 mm crushed stone ballast & Coarse sand having F.M. not less than 2.0 including all cost of labour, materials, T&P etc. compaction required for proper completion of work. As per direction of Engineer in charge. | 2,091.12 | Cum | 8,200 ₹1,71,47,184 | 7,790 ₹1,62,89,824.8 | 7,600 ₹1,58,92,512 Lowest |
| 5.00 | Providing Steel Reinforcement and cutting bending, binding including all cost of labour material & T&P etc. As per direction of Engineer in charge. | 140.67 | MT | 99,121 ₹1,39,42,954.59 | 99,000 ₹1,39,25,934 | 97,000 ₹1,36,44,602 Lowest |
| 6.00 | Laying Plain Cement Concrete in 1:1.5:3 with maximum size of 20 mm size crushed stone ballast & Coarse sand having F.M. not less than 2.0 including all cost of labour, materials, T&P etc. compaction required for proper completion of work. As per direction of Engineer in charge. | 1,820.66 | Cum | 8,767 ₹1,59,61,726.22 | 8,770 ₹1,59,67,188.2 | 8,700 ₹1,58,39,742 Lowest |
| 7.00 | C.C. in 1:1:2 with stone grit 4.75 to 20 mm size, cement and coarse sand including cost of labour material etc. complete. As per direction of Engineer in charge. | 1,559.34 | Cum | 9,557 ₹1,49,02,612.38 | 9,500 ₹1,48,13,730 Lowest | 9,500 ₹1,48,13,730 Lowest |
| 8.10 | Centering & Shuttering including cost of material, labour etc. complete, Up to span 3.0 m. As per direction of Engineer in charge. | 576.42 | Sqm. | 720 ₹4,15,022.4 Lowest | 725 ₹4,17,904.5 | 725 ₹4,17,904.5 |
| 8.20 | Centering & Shuttering including cost of material, labour etc. complete for bridge T-beam & slab, bridges, syphon and aqueduct up to 10 m. span and 5 m. staging. As per direction of Engineer in charge. | 1,622.57 | Sqm. | 1,100 ₹17,84,827 | 1,100 ₹17,84,827 | 1,000 ₹16,22,570 Lowest |
| 9.00 | Earth work on Ramp approach and Road Diversion with material and labour etc. As per direction of Engineer in charge. | 13,905.91 | Cum | 78 ₹10,84,660.98 Lowest | 100 ₹13,90,591 | 100 ₹13,90,591 |
Tender Value
₹10.6 Cr
EMD Value
₹21.2 L
Closing Date
24 Sept 2026, 2:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Superintending Engineer
S.E. 18th Circle Irrigation Works, Govindpur, Prayagraj
Construction of Pucca Works and Restoration Work of Soraon Distributary from Km 0.000 to 35.300 under the Control of Irrigation Division-I, Prayagraj. (Lot-01)
2026_UPIDC_1187038_1
04/S.E./2026-27
Open Tender
Civil Works - Canal
Item Rate
S.E. 18th Circle Irrigation Works Prayagraj
Please refer Tender documents.
2 documents required · 2 mandatory
₹6,354
₹21.2 L
Prayagraj
2 Nov 2026
18 Sept 2026
24 Sept 2026
18 Sept 2026
24 Sept 2026
18 Sept 2026
19 Sept 2026
90 days
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling brick work, stone work in lime or cement mortar including stacking of materials within a distance of 60 m. As per direction of engineer in-charge. | 514.8 | Cum | 10 | ₹5,148 |
| 2 | Dismantling reinforced cement concrete 1:2:4 including stacking of dismantled materials within a distance of 60m. As per direction of engineer in-charge. | 97.6 | Cum | 10 | ₹976 |
| 3 | Earth work in foundation including all lead, lift, labour complete. As per direction of engineer in-charge. | 10,987.33 | Cum | 10 | ₹1,09,873.3 |
| 4 | Laying Plain Cement Concrete in 1:2:4 with maximum size of 20 mm crushed stone ballast & Coarse sand having F.M. not less than 2.0 including all cost of labour, materials, T&P etc. compaction required for proper completion of work. As per direction of Engineer in charge. | 2,091.12 | Cum | 10 | ₹20,911.2 |
| 5 | Providing Steel Reinforcement and cutting bending, binding including all cost of labour material & T&P etc. As per direction of Engineer in charge. | 140.67 | MT | 10 | ₹1,406.66 |
| 6 | Laying Plain Cement Concrete in 1:1.5:3 with maximum size of 20 mm size crushed stone ballast & Coarse sand having F.M. not less than 2.0 including all cost of labour, materials, T&P etc. compaction required for proper completion of work. As per direction of Engineer in charge. | 1,820.66 | Cum | 10 | ₹18,206.6 |
| 7 | C.C. in 1:1:2 with stone grit 4.75 to 20 mm size, cement and coarse sand including cost of labour material etc. complete. As per direction of Engineer in charge. | 1,559.34 | Cum | 10 | ₹15,593.4 |
| 8.1 | Centering & Shuttering including cost of material, labour etc. complete, Up to span 3.0 m. As per direction of Engineer in charge. | 576.42 | Sqm. | 10 | ₹5,764.2 |
| 8.2 | Centering & Shuttering including cost of material, labour etc. complete for bridge T-beam & slab, bridges, syphon and aqueduct up to 10 m. span and 5 m. staging. As per direction of Engineer in charge. | 1,622.57 | Sqm. | 10 | ₹16,225.7 |
| 9 | Earth work on Ramp approach and Road Diversion with material and labour etc. As per direction of Engineer in charge. | 13,905.91 | Cum | 10 | ₹1,39,059.1 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.21 MB
BOQ_2234794.xls
BOQ • 0.34 MB
Document01.pdf
Tender Documents • 3.44 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart shows the information on this page on a best-effort basis and does not guarantee that it is accurate, complete or current. Check it against the buyer's official notice and documents before you act on it; the official record prevails. TenderKart is not liable for any loss or claim arising from the use of this information. If you notice any error or omission, please let us know at .