| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.7 CrAccepted-AOC B WING 601 602 DELPHI BUILDING CENTRAL AVENUE HIRANANDANI BUSINESS PARK POWAI MUMBAI MAHARASHTRA 400076 | MUMBAI SUBURBAN | MAHARASHTRA | 400076 | ₹3.7 Cr Quoted ₹3.6 Cr | L1 | Accepted-AOC L1 |
| Sl No | Description | Qty | Unit | Emerson Process Management |
|---|---|---|---|---|
| 1.00SUPPLY OF Wireless Monitoring Systems for EPCM-2, P25 PROJECT at IOCL PANIPAT REFINERY as specified in Material Requisition. | ||||
| 1.01 | Design, Engineering, Manufacture, Procurement of materials and bought out items/components, assembly at shop, system engineering, internal testing, integration, Factory testing and acceptance (FAT) at manufacturer's works, Inspection (TPI), packing, delivery of the following including supply of Spares, special tools and tackles, consumables, documentation, supervision of Wireless Monitoring System at site during Installation, System powering up, pre-commissioning checks, providing commissioning back-up, works-completion, commissioning of Wireless Monitoring System, completion of SAT, handing over complete system to client, handing over of mandatory spares and post-commissioning back-up for IOCL Panipat EPCM2 Project at Panipat refinery, Panipat, India as per Material Requisition.
Itemwise % breakup for all the systems constituting the basket are indicated below:
MSB Wireless N/W- 1,2&3: 37%
SRLPGTU Wireless N/W- 1: 18%
INDMAX Wireless N/W- 1: 45% | 1 | Lot | 3,68,40,000 ₹4.3 Cr |
Tender Value
Refer Docs
Closing Date
24 Apr 2025, 3:00 pmClosed
Mr. Nilesh Sathe
tkUIPL-Mumbai
SUPPLY OF WIRELESS MONITORING SYSTEMS FOR P25 PROJECT AT IOCL PANIPAT REFINERY
2025_REFHQ_183644_1
6745-PPM-000-CA-IC72
Open Tender
Instrumentation-Goods
150 days
IOCL Panipat Refinery
Please refer Tender documents.
6 documents required · 6 mandatory
Exempted
24 Dec 2025
7 Feb 2025
25 Apr 2025
7 Feb 2025
24 Apr 2025
17 Feb 2025
SUPPLY OF Wireless Monitoring Systems for EPCM-2, P25 PROJECT at IOCL PANIPAT REFINERY as specified in Material Requisition.
Design, Engineering, Manufacture, Procurement of materials and bought out items/components, assembly at shop, system engineering, internal testing, integration, Factory testing and acceptance (FAT) at manufacturer's works, Inspection (TPI), packing, delivery of the following including supply of Spares, special tools and tackles, consumables, documentation, supervision of Wireless Monitoring System at site during Installation, System powering up, pre-commissioning checks, providing commissioning back-up, works-completion, commissioning of Wireless Monitoring System, completion of SAT, handing over complete system to client, handing over of mandatory spares and post-commissioning back-up for IOCL Panipat EPCM2 Project at Panipat refinery, Panipat, India as per Material Requisition. Itemwise % breakup for all the systems constituting the basket are indicated below: MSB Wireless N/W- 1,2&3: 37% SRLPGTU Wireless N/W- 1: 18% INDMAX Wireless N/W- 1: 45%
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid