| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.6 LAccepted-AOC KOTA BASTI SHAKTINAGAR P O SHAKTINAGAR DISTT SONBHADRA U P 231222 | SONBHADRA | UTTAR PRADESH | 231222 | L1 | Accepted-AOC AWARD OF WORK TO L1 BIDDER AND REJECT L2 AND L3 BIDDER DUE TO NOT L1 BIDDER | |
| 2 | Rejected-Technical DAKRA RANCHI PIN 829201 | CHATRA | JHARKHAND | 829201 | - | Rejected-Technical NOT L1 BIDDER | |
| 3 | Rejected-Technical KOHRAUL PO YOGICHIOURA DISTT SONEBHADRA UP | - | Rejected-Technical NOT L1 BIDDER |
Tender Value
₹8.6 L
EMD Value
₹10,800
Closing Date
14 Aug 2024, 11:00 amClosed
GENERAL MANAGER EXCAVATION, NCL KHADIA PROJECT
NCL KHADIA PROJECT, SHAKTINAGAR, SONEBHADRA, U.P.
Repairing of gate assembly, horizontal pulley housing and line boring of housing of pulley pins of 33 72 Somnath Dragline of Khadia Project
2024_NCL_314073_1
KHD/G.M. (Excv)/E-Tender/24-25/358
Open Tender
Excavation Department Work
Item Rate
20 days
NCL KHADIA PROJECT, SHAKTINAGAR
Please refer Tender documents.
6 documents required · 6 mandatory
₹10,800
16 Oct 2024
2 Aug 2024
16 Aug 2024
2 Aug 2024
14 Aug 2024
3 Aug 2024
2 Aug 2024 - 7 Aug 2024
Amount
Scope of Work/Technical Specifications etc.- 1. Cleaning of fairlead, drag tray and nearby area. 2. Fabrication of desired platforms. 3. Removal of 02 nos. gates and its repairing. 4. Removal of gate assembly by cutting pins with gas if required. 5. Repairing of horizontal pulleys. 6. Repairing of housing of areas nearby horizontal pulley. 7. Line boring of pin housing. 8. Repairing of drag trays and fitment of rubbing blocks. 9. Fitment of gate assemblies to the machine.
Complete cleaning of fairlead gate assly., horizontal pulley, drag rope tray and pin housing.
Labour charges for complete cleaning of fairlead gate assly., horizontal pulley, drag rope tray and pin housing including contractor's profit. Note : It includes a group of 04 nos. Semi-Skilled Fitter and 01 no. Supervisor, in 02 shifts per day for 02 days for 01 no. job.
Making of platforms/ stands for jacking to remove pins of gate assy. (04 nos.)(parallel activity).
Labour charges for making of platforms/ stands for jacking to remove pins of gate assy. (04 nos.)(parallel activity) including contractor's profit. Note : It includes a group of 02 nos. Skilled Fitter, 02 nos. Skilled Welder, 04 nos. Semi-Skilled Fitter and 01 no. Supervisor in 02 shifts per day for 02 days for 01 no. job.
Removal of gate assly by means of jacking 04 nos.
Labour charges for removal of gate assly by means of jacking 04 nos. including contractor's profit. Note : It includes a group of 02 nos. Skilled Fitter, 02 nos. Skilled Welder, 06 nos. Semi-Skilled Fitter and 01 no. Supervisor in 02 shifts per day for 02 days for 01 no. job.
Rebuilding of worn out housing Rope path.
Labour charges for rebuilding of worn out housing Rope path including contractor's profit. Note : It includes a group of 02 nos. Skilled Fitter, 02 nos. Skilled Welder, 02 nos. Semi-Skilled Fitter and 01 no. Supervisor in 02 shifts per day for 06 days for 01 no. job.
Repairing of structural cracks and assembling of vertical pulleys in fairlead gate assy (LHS& RHS).
Labour charges for repairing of structural cracks and assembling of vertical pulleys in fairlead gate assy (LHS& RHS) including contractor's profit. Note : It includes a group of 02 nos. Skilled Fitter, 02 nos. Skilled Welder, 04 nos. Semi-Skilled Fitter and 01 no. Supervisor in 02 shifts per day for 06 days for 01 no. job.
Repairing of badly worn out area near horizontal pulley (4 nos.) by means of welding(parallel activity with line boring).
Labour charges for repairing of badly worn out area near horizontal pulley(4 nos.) by means of welding(parallel activity with line boring) including contractor's profit. Note : It includes a group of 02 nos. Skilled Fitter, 02 nos. Skilled Welder, 02 nos. Semi-Skilled Fitter and 01 no. Supervisor in 02 shifts per day for 06 days for 01 no. job.
Fitment of gate assy. and 04 nos. Horizontal pulleys in machine.
Labour charges for fitment of gate assy. and 04 nos. Horizontal pulleys in machine including contractor's profit. Note : It includes a group of 02 nos. Skilled Fitter, 02 nos. Skilled Welder, 06 nos. Semi-Skilled Fitter and 01 no. Supervisor in 02 shifts per day for 04 days for 01 no. job.
Repair of drag tray including fitment of conveyor belt/rubbing block on tray(parallel activity).
Labour charges for repairing of drag tray including fitment of conveyor belt/rubbing block on tray(parallel activity) including contractor's profit. Note : It includes a group of 02 nos. Skilled Fitter, 02 nos. Skilled Welder and 02 nos. Semi-Skilled Fitter in 02 shifts per day for 06 days for 01 no. job.
Co-axial boring of built- up housing to its original size.
Charges for co-axial boring of built- up housing to its original size including contractor's profit. Note : 1.Size of housing: ID = 200mm, L = 180mm (for 8 nos.). 2.Volume to be machined= 22/7 x 1/4 (21+20) x(21-20) x 18 x 8 Cu Cm = 4638.5 Cu Cm.
Charges for bush pressing/ fitting in housing.
Hiring chargess for repairing of gate assembly, horizontal pulley housing and line boring of housing of pulley pins of 33/72 Somnath Dragline of Khadia Project.
Hiring Charges of welding machine with accessories - 02 nos. for max period of 20 days.
Hiring Charges of gas cutting set with accessories- 02 nos. for max period of 20 days.
Hiring Charges of grinders- 02 nos. for max period of 20 days.
Hiring Charges of hydraulic jacks (200 T)- 02 nos. for max period of 20 days.
Hiring Charges of misc. tools (Chipping hammers, tie rods, wedges, hammers, crowbars etc.).
Transportation charges for max. period of 20 days.
Total impact of GST for the purpose of CTC
SHASHI ENGINEERING WORKS
New Diamond Engineering Services
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_325491.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .