SE EDC Mau 275101
SE EDC Mau 275101
Construction of 11 KV/L.T Line with Installation of 11 KV incoming/outgoing VCB and L.T Sub-station for giving connection to 100 bed Hospital from 33/11 KV Sub-station Tandiyanw under EDD-2nd Mau as per attached Scope of Work.
2021_PVVNV_543916_1
64/EDC(M)/2020-21
Open Tender
Electrical Works
Lump-sum
120 days
SE EDC Mau 275101
Please refer to tender Documents
2 documents required · 2 mandatory
₹590
EE ETD Mau
₹15,000
Yes
20 Feb 2021
6 Jan 2021
18 Jan 2021
6 Jan 2021
16 Jan 2021
6 Jan 2021
Amount
Cartage of 11 KV Meter Long STP From store center Mau to dump site and from dump site to work site along with loading unloading.
Cartage of ACSR Weasel conductor from store center Mau to dump site and form dump site to work site along with loading unlaoding.
Cartage of 630 KVA T/F from store center mau to dump site and from dump site to work site along with loading unloading.
Cartage of L.T. XLPE cable Size 3.50X400 mm2
Cartage of 11 KV VCB Incoming 600/300/5A and 11 KV outgoing VCB, 400/200/5A, 350 MVA Including loading and unloading safty with the help of crain.
Cartage of other line materials except pole, conductor and T/F from Store center Mau to dump Site and dump site to work site including loading and unloading.
Erection of ST Pole with all fitting by digging pits as per RESSPO Norms.
Erection of T-off Pole with all fitting by digging pits as per RESSPO Norms.
Erection of double Pole/Sectional Double Pole made of ST Pole with all fitting by digging pits as per RESSPO Norms.
Grouting and Plinthing of S.T. Pole with 1:4:8 Ratio of cement, sand and brick ballast as per RESSPO Norms.
Erection of ACSR Weasel conductor on the ST Pole Erected along with Sagging and Binding.
Constrution of Plinth suitable for 630 KVA T/F as per Resspo Norms with requisite materials.
Installation of 630 KVA T/F on Plinth after its Construction.
Erection of stay as per line diagram with its grouting.
Intallation of 11 KV VCB Incoming 600/300/5A and 11 KV outgoing VCB 400/200/5A, 350 MVA with all connection equipment.
Laying of 11 KV 3X120 mm2 XLPE cable by digging trench complete in all respect.
Installation of 11 KV pole mounted on 11 KV C.T. P.T.
Earthing of ST Pole as per Resspo Norms.
Installation of 11 KV Fuse set with materials.
Installtion of 350 MVA Bus Coupler.
Earthing of V.C.B Pannel as per Resspo Norms.
Installation of 11 KV Pilfer Proof metering cubical
Fixing of Incoming and outgoing cable joiting kit suitable for 11 KV 3x120 mm2 XLPE cable.
11 KV cable box Mouting with switch gear and T/F(kit).
Double Earthing of 630 KVA T/F.
laying of XLPE cable size 3.50x400 mm2 with the help of G.I Pipe of 6" dia be digging Trench.
Providing G.I. Pipe of 6" Dia for cabling .
Providing Nut bolt of requisite size due to non availibility in store center.
Providing clamp for top Channel, X-arm Clamp, T-off Clamp and MS angle Clamp, F-bracket due to non availibility in store.
Painting of sub station structure and all equipment.
Connection the incoming and outgoing pannels with all requisite materials as per Resspo norms.
IRSHAD ENTERPRISES
R A ENGINEERS
LUCKY ENTERPRISES
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .