Loading…
Loading…
Tender Value
₹8.0 Cr
EMD Value
₹16.0 L
Closing Date
14 May 2026, 3:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
DEN E
29 conditions · 3 needing a document upload
The tenderer must have minimum average annual contractual turnover of 'V/N' or 'V'; whichever is less, where 'V'= Advertised value of the tender in crores of Rupees and 'N'= Number of years prescribed for completion of work for which bids have been invited.
The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover.
The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
The JV shall satisfy the requirement of "Financial Eligibility" mentioned above. The "financial capacity" of the lead member of JV shall not be less than 51% of the financial eligibility criteria mentioned above. The arithmetic sum of individual "financial capacity" of all the members shall be taken as JV's "financial capacity" to satisfy this requirement. Note: Contractual payment received by a Member in an earlier JV shall be reckoned only to the extent of the concerned member's share in that JV for the purpose of satisfying compliance of the above mentioned financial eligibility criteria in the tender under consideration.
The Balance Sheet and all other financial documents attested/ certified by CAs to substantiate fulfilment of Financial Eligibility Criteria should be with UDIN, failing which the offer is likely to be rejected without any further refrence.
The tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i) Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or (ii) Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or (iii) One similar work costing not less than the amount equal to 60% of advertised value of the tender.
Definition of similar work: "Execution of P.Way work on running line".
In case of tenders for composite works (e.g. works involving more than one distinct component, such as Civil Engineering works, S&T works, Electrical works, OHE works etc. and in the case of major bridges - substructure, superstructure etc.), tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i) Three similar works each costing not less than the amount equal to 30% of advertised value of each component of tender, or (ii) Two similar works each costing not less than the amount equal to 40% of advertised value of each component of tender, or (iii) One similar work each costing not less than the amount equal to 60% of advertised value of each component of tender. Note for : Separate completed works of minimum required values shall also be considered for fulfillment of technical eligibility criteria for different components. In such cases, what constitutes a component in a composite work shall be clearly pre-defined with estimated tender cost of it, as part of the tender documents without any ambiguity.
To evaluate the technical eligibility of tenderer, only components of work as stipulated in tender documents for evaluation of technical eligibility, shall be considered. The scope of work covered in other remaining components shall be either executed by tenderer himself if he has work experience as mentioned in clause 7 of the Standard General Conditions of Contractor through subcontractor fulfilling the requirements as per clause 7 of the Standard General Conditions of Contract or jointly i.e., partly himself and remaining through subcontractor, with prior approval of Chief Engineer in writing. However, if required in tender documents by way of Special Conditions, a formal agreement duly notarised, legally enforceable in the court of law, shall be executed by the main contractor with the subcontractor for the component(s) of work proposed to be executed by the subcontractor(s), and shall be submitted along with the 1.2.1 offer for considering subletting of that scope of work towards fulfilment of technical eligibility. Such subcontractor must fulfill technical eligibility criteria as follows: The subcontractor shall have successfully completed at least one work similar to work proposed for subcontract, costing not less than 35% value of work to be subletted, in last 5 years, ending last day of month previous to the one in which tender is invited through a works contract. Note: for subletting of work costing up to Rs 50 lakh, no previous work experience of subcontractor shall be asked for by the Railway. In case after award of contract or during execution of work it becomes necessary for contractor to change subcontractor, the same shall be done with subcontractor(s) fulfilling the requirements as per clause 7 of the Standard General Conditions of Contract, with prior approval of Chief Engineer in writing.
Work experience certificate from private individual shall not be considered. However, in addition to work experience certificates issued by any Govt. Organisation, work experience certificate issued by Public listed company having average annual turnover of Rs 500 crore and above in last 3 financial years excluding the current financial year, listed on National Stock Exchange or Bombay Stock Exchange, incorporated/registered at least 5 years prior to the date of closing of tender, shall also be considered provided the work experience certificate has been issued by a person authorized by the Public listed company to issue such certificates. In case tenderer submits work experience certificate issued by public listed company, the tenderer shall also submit along with work experience certificate, the relevant copy of work order, bill of quantities, bill wise details of payment received duly certified by Chartered Accountant, TDS certificates for all payments received and copy of final/last bill paid by company in support of above work experience certificate.
Explanation for Eligibility criteria:
[1] Substantially Completed Work means an ongoing work in which payment equal to or more than 90% of the present contract value (excluding the payment made for adjustment of Price variation (PVC), if any) has been made to the contractor in that ongoing contract and no proceedings of termination of contract on Contractor's default has been initiated. The credential certificate in this regard should have been issued not prior to 60 days of date of invitation of present tender. [2] In case a work is started prior to 07 (seven) years, ending last day of month previous to the one in which tender is invited, but completed in last 07 (seven) years, ending last day of month previous to the one in which tender is invited, the completed work shall be considered for fulfillment of credentials. [3] If a work is physically completed and completion certificate to this extent is issued by the concerned organization but final bill is pending, such work shall be considered for fulfillment of credentials. [4] In case of completed work, the value of final bill (gross amount) including the PVC amount (if paid) shall be considered 1.4.1 as the completion cost of work. In case final bill is pending, only the total gross amount already paid including the PVC amount (if paid) shall be considered as the completion cost of work. In case of substantially completed work, the total gross amount already paid including the PVC amount (if paid), as mentioned in the certificate, shall be considered as the cost of substantially completed work. [5] If a bidder has successfully completed a work as subcontractor and the work experience certificate has been issued for such work to the subcontractor by a Govt. Organization or public listed company as defined in Note for Item 10.1 Para 10 of the Tender Form (Second Sheet), the same shall be considered for the purpose of fulfillment of credentials. [6] In case a work is considered similar in nature for fulfillment of technical credentials, the overall cost including the PVC amount (if paid) of that completed work or substantially completed work, shall be considered and no separate evaluation for each component of that work shall be made to decide eligibility.
[7] In case of newly formed partnership firm, the credentials of individual partners from previous propriety firm(s) or dissolved previous partnership firm(s) or split previous partnership firm(s), shall be considered only to the extent of their share in previous entity on the date of dissolution / split and their share in newly formed partnership firm. For example, a partner A had 30% share in previous entity and his share in present partnership firm is 20%. In the present tender under consideration, the credentials of partner A will be considered to the extent of 0.3*0.2*value of the work done in the previous entity. For this purpose, the tenderer shall submit along with his bid all the relevant documents which include copy of previous partnership deed(s), dissolution deed(s) and proof of surrender of PAN No.(s) in case of dissolution of partnership firm(s) etc. [8] In case of existing partnership firm, if any one or more partners quit the partnership firm, the credentials of remaining partnership firm shall be re-worked out i.e., the quitting partner(s) shall take away his credentials to the extent of his share on 1.4.2 the date of quitting the partnership firm (e.g. in a partnership firm of partners A, B & C having share 30%, 30% & 40% respectively and credentials of Rs 10 crore; in case partner C quits the firm, the credentials of this partnership firm shall remain as Rs 6 crore). For this purpose, the tenderer shall submit along with his bid all the relevant documents which include copy of previous partnership deed(s), dissolution deed(s) and proof of surrender of PAN No.(s) in case of dissolution of partnership firm(s) etc. [9] In case of existing partnership firm if any new partner(s) joins the firm without any modification in the name and PAN/TAN no. of the firm, the credentials of partnership firm shall get enhanced to the extent of credentials of newly added partner(s) on the same principles as mentioned in item 6 above. For this purpose, the tenderer shall submit along with his bid all the relevant documents which include copy of previous partnership deeds, dissolution/splitting deeds and proof of surrender of PAN No.(s) in case of dissolution of partnership firm etc.
10. Any partner in a partnership firm cannot use or claim his credentials in any other firm without leaving the partnership firm i.e., In a partnership firm of A&B partners, A or B partner cannot use credentials of partnership firm of A&B partners in any other partnership firm or propriety firm without leaving partnership firm of A&B partners. 11. In case a partner in a partnership firm is replaced due to succession as per succession law, the proportion of credentials of the previous partner will be passed on to the successor. 12. If the percentage share among partners of a partnership firm is changed, but the partners remain the same, the credentials of the firm before such modification in the share will continue to be considered for the firm as it is without any change in 1.4.3 their value. Further, in case a partner of partnership firm retires without taking away any credentials from the firm, the credentials of partnership firm shall remain the same as it is without any change in their value. 13. In a partnership firm "AB" of A&B partners, in case A also works as propriety firm "P" or partner in some other partnership firm "AX", credentials of A in propriety firm "P" or in other partnership firm "AX" earned after the date of becoming a partner of the firm AB shall not be added in partnership firm AB. 14. In case a tenderer is LLP, the credentials of tenderer shall be worked out on above lines similar to a partnership firm. 15. In case company A is merged with company B, then company B would get the credentials of company A also.]
Technical Eligibility Criteria of JV ('a' or 'b' mentioned hereunder):
(a) For Works without composite components : The technical eligibility for the work as per para 10.1 above, shall be satisfied by either the 'JV in its own name & style' or 'Lead member of the JV'. Each other (non-lead) member(s) of JV, who is/ are not satisfying the technical eligibility for the work as per para 10.1 above, shall have technical capacity of minimum 1.5.1 10% of the cost of work i.e., each non-lead member of JV member must have satisfactorily completed or substantially completed during the last 07 (seven) years, ending last day of month previous to the one in which tender is invited, one similar single work for a minimum of 10% of advertised value of the tender.
(b) For works with composite components : The technical eligibility for major component of work as per para 10.1 above, shall be satisfied by either the 'JV in its own name & style' or 'Lead member of the JV' and technical eligibility for other component(s) of work as per para 10.1 above, shall be satisfied by either the 'JV in its own name & style' or 'any member of the JV'. Each other (non-lead)member(s) of JV, who is/ are not satisfying the technical eligibility for any component of the work as per 1.5.2 para 10.1 above, shall have technical capacity of minimum 10% of the cost of any component of work mentioned in technical eligibility criteria. i.e., each other (nonlead) member of must have satisfactorily completed or substantially completed during the last 07 (seven) years, ending last day of month previous to the one in which tender is invited, one similar single work for a minimum of 10% of cost of any component of work mentioned in technical eligibility criteria.
Note : a) The Major component of the work for this purpose shall be the component of work having highest value. In cases where value of two or more component of work is same, any one work can be classified as Major component of work. b) Value of a completed work done by a 1.5.3 Member in an earlier JV shall be reckoned only to the extent of the concerned member's share in that JV for the purpose of satisfying his/her compliance to the above mentioned technical eligibility criteria in the tender under consideration.
88 conditions · 1 needing a document upload
Compliance with the GST Act, 2017 - Change in para (a) of clause 6, part I of Indian Railway Standard General Conditions of Contract, April'2022.
Before submitting a tender, the tenderer will be deemed to have satisfied himself by actual inspection of the site and locality of the works, that all conditions liable to be encountered during the execution of the works are taken into account and that the rates he enters in the tender forms are adequate and all inclusive to accord with the provisions in Clause-37 of the Standard General Conditions of Contract for the completion of works to the entire satisfaction of the Engineer.
Tenderers will examine the various provisions of The Central Goods and Services Tax Act, 2017(CGST)/ Integrated Goods and Services Tax Act, 2017(IGST)/ Union Territory Goods and Services Tax Act, 2017(UTGST)/ respective state's State Goods and Services Tax Act (SGST) also, as notified by Central/State Govt.& as amended from time to time and applicable taxes before bidding. Tenderers will ensure that full benefit of Input Tax Credit (ITC) likely to be availed by them is duly considered while quoting rates.
The successful tenderer who is liable to be registered under CGST/IGST/UTGST/SGST Act shall submit GSTIN along with other details required under CGST/IGST/UTGST/SGST Act to railway immediately after the award of contract, without which no payment shall be released to the Contractor. The Contractor shall be responsible for deposition of applicable GST to the concerned authority.
In case the successful tenderer is not liable to be registered under CGST/IGST/UTGST/ SGST Act, the railway shall deduct the applicable GST from his/their bills under reverse charge mechanism (RCM) and deposit the same to the concerned authority.
Contractor shall be liable to pay/refund the amount collected as GST to the Indian Railways along with interest and penalties, if any imposed by the authorities, in case GST input tax credit of Indian Railways is denied/rejected by the tax authortties due to reasons mentioned below but not limited to: Wrong/incorrect invoices issued by Contractor; No-filing of GST returns; Nonpayment of GST collected from Indian Railways to the authorities; Any other non-compliance done by Contractor; General Indemnity: Contractor hereby agrees to indemnify and hold harmless the Indian Railways from and against any and all losses, including loss on account of Input Tax Credit and all losses incurred by the Indian Railways relating to or arising out of or in connection with any actual or threatened claim, legal action, proceedings, prosecution or inquiry by or against the Indian Railways arising out, directly or indirectly, of failure by the contractor to comply with the provisions of GST and related laws, or based upon or arising from any failure by the Contractor. Retention Money: Any payment liable to be paid by Indian Railways to contractor against the goods or services or both supplied by such contractor to Indian Railways shall be kept on hold in case supplier makes any non-compliance of any of the GST law.
Estt. No. 56/East/KGP/2025 , Allocation: SF (PH-31).
All the bidders / tenderers should ensure that they are GST compliant and their quoted rates are as per GST law.
Tender value is inclusive of GST. Agencies must quote their rates including GST.
In the instant tender GST is applicable at the rate of 18% (Eighteen percent).
However, inter se ranking will be done on the quoted value including GST applicable on the date of opening.
In case of increase or decrease in GST rate, same will be either paid by railway or recovered from the agency as the case may be.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
In case damage is caused to OFC / Quad cable / signaling cable during execution of the work, the contractor is liable to pay a penalty for damaging the cable. Penalty shall not be levied in case of the following: (i) Detailed cable route plan not provided by concerned department or cable is not protected as per laid down procedures, (ii) The alignment of the cable does not tally with the information provided to the contractor, (iii) The cable depth is found to be less than 800 mm from normal ground level, (iv) No representative of S&T department / Rail Tel was available at site guarding the cables on the fixed pre determined date and time. Penalty to be imposed for damages to cable shall be as under: (a) Only Quad cable or Signaling cable ----- Rs.1.00 Lakh per location, (b) Only OFC ----- Rs.1.25 Lakh per location, (c) Both OFC & Quad ----- Rs.1.50 Lakh per location, (d) Electrical Cable ----- Rs.1.00 Lakh per location. (Telecom Circular No. 17/2013 issued by Railway Board vide No. 2003/Tele/RCIL/1 Pt.IX dated 24.06.2013 is binding to this contract and should be followed in spirit).
If necessary, the contractor have to make drawings/designs of the subjected work (or part of work) and have to make it approved from any recognized Govt. college/university/institution and if necessary have to make it signed by Railway officials of his own.
The contractor for carrying out any construction work in West Bengal/Jharkhand must get themselves registered from the Registering Officer under Section-7 of the Building and Other Construction Workers Act, 1996 and rules made thereto by the Jharkhand/West Bengal government and submit certificate of registration issued from the Registering Officer of the West Bengal state govt.(labour department). For enactment of this Act, the contractor shall be required to pay cess @ 1% of cost of construction work to be deducted form each bill. Cost of material shall be outside the purview of cess, when supplied under a separate schedule item.
As per latest CE s Circular No. 271, Transparency Board is to be provided at work site by the agency free of cost as per direction of Engineer-In-Charge.
In case of exigency, the contractor has to execute the work in any section of Sr. DEN/East/KGP.
All materials to be supplied by the contractor should be got approved by the Engineer-in-charge before use in the work.
Unless specifically mentioned in the schedule of rates all materials required for execution of work will be supplied by the contractor free of cost as per standard specifications and approved by the Engineer-in-charge.
Contractor will be responsible for safety of staff working on site of work. All safety measure will be taken by contractors for movement of traffic during the operation.
On Completion of the work rubbish, unused materials etc. if any should be removed and deposited at nominated place and as directed and the same are to be made neat and clean. No extra will be paid for this.
Tenderer or contractor will have to execute the work taking necessary precautions for safety of works, Passenger, traffic etc.
Necessary materials must be available in the contractor's godown to attend any break down.
Engineering Guide line (Civil) to be followed by the contractor to supervise the work. The contractor also has to provide water meter suitable to delivery pipe of pump as a part of a contract without charging any cost from the Railway.
The non schedule items should be inclusive of all lead, lift, taxes, fabrication, fitting and all other charges if any.
Tenderer/s should furnish their GST Registration No. along with the tender document.
The mode of payment through 'Letter of Credit' for all tenders having advertised value of Rs. 10 lakh and above as per Railway Board's letter No. 2018/CE-I/CT/9, Dtd.04.06.2018 has been followed . Copy attached in document.
Contractor shall not start any work without the presence of the IOW or PWI at site. In case the contractor's representative starts any work in absence of IOW or PWI, it shall be treated as unauthorized and illegal tampering with the track and shall be liable for action.
The Railway shall not guarantee any provision for supplying electrical power or road approach to the site of work or for granting of block to the FOB or blocks for OHE power or traffic or any other facilities not committed to in the schedule. Granting permission for any of these or others in any as required or demanded by the Agency shall only depend on the feasibility and situation. Therefore the Agency shall not have any claim in this regard.
Medium class sand to be used in the plastering works.
All GI Pipe line works is to be carried out only with the approved brand,medium class as per the I.S.Specification i.e. G.I.pipe of Jindal/Bansal/Tata Brand or other equivalent brand as will be approved by ADEN concerned are to be supplied and used. Meterials should be got confirm to the approval of the Engineer in charge or his authorised representative at site to ensure that only approved brand of pipes are supplied and used by the Contractor. Contractor has to produce the necessary vouchers for procurement of pipes of approved medium varieties and proper accountal of pipes will have to be maintained by I.O.W
The rates are inclusive of all taxes where applicable and other charges as leviable by the State Government/Central Government.
Tenderer has to make his own service Road for carrying materials and equipment's. No separate payment will be made for this purpose. However, Railway will allow to make such Road in the available Railway Land.
All the steel work and fitting materials like M.S plate, M.S.bolts, rivets, service bolts, nuts, washers, electrodes etc. will conform to relevant IS specifications.
All safety measure will be taken by contractors for movement of traffic during the operation.
During the course of work steel are to be got tested by the contractor at their own cost to ascertain their conformity to specification as and when required by the Engineer-in-charge or his authorized representative.
All the scrap and released materials to be returned to the Railway as per instructions given by the Engineer in - charge or his authorized representative at their nominated places after completion of the work.
The steel that will be supplied by the contractor should conform to I.S. 226/I.S. 1977 for mild steel and I.S. 1481 for rivets followed with latest corrections if any. All steel section, Rivets, Paint, etc. are to be got tested as per relevant BIS codes at the contractors expense by the Chief Chemist and Metallurgist, S.E.Railway , Kharagpur or at National Test House, Alipore, Kolkata or at IIT, Kharagpur as found convenient by the Railway. If the test results does not confirm to the relevant IS specifications, the whole lot / lots of materials shall be rejected and got removed from the site by the contractor at the contractor s cost. No payment will be made for rejected works. Manufactures test certificate is to be submitted by the contractor along with necessary purchase vouchers etc.
All the works, which are to be done under traffic block, in electrified territory, contractor will have to take all precautions for safety of track and running trains as well as safety of his labour in terms of Indian Railways P.Way manual.
The Contractor with the help of his Engineer or Diploma holder , as the case be , shall make necessary Drawings, sketches, plotting, peg markings etc. as desired by the Engineer-in-charge. No extra cost shall be claimed on this account.
The agency should depute a trained and certified supervisor duly certified by AEN.
The Contractor should be make available all the necessary tools, plants and equipment for execution of the above work at site during execution of work.
The vehicles and equipment of contractors can be drafted by Railway Administration in case of Accidents or Natural calamities involving human lives, and payment in respect of that would be made by operating the item as a non scheduled item.
No compensation towards any accident what so ever will be paid by the Railway.
Special Condition of Civil work is attached.
Special Condition of P.Way work is attached.
Special conditions of contracts for all contracts is attached.
Special conditions for Electrical portion of work :- 1. The Civil contractor should carry out the Electrical portion work by Electrical contractor having valid electrical license. 2. The work will be executed under supervision of SSE(Electrical) of concerned section and all the measurements, MB related to electrical work will be recorded by him. 3. All the necessary drawings and Makes of Schedule items are to be got approved before supply by Sr.DEE(G)/KGP. 4. Inspection and Testing by Rites /authorized railway representative to be followed as per extant rules. 5. All the electrical equipment's will be star rated and energy efficient. 6. MCBs are to be 'C' type and MCCBs are to be microprocessor based. 7. On Account payment is to be done as per the payment conditions enclosed.
Special condition for Amrit Bharat station improvement work : -
Billing will be done by contractor's eMB on IRWCMS.
Contractor should deploy one civil graduate engineer, one civil diploma engineer and one electrical engineer (graduate/diploma) at each station.
In case of non deployment of engineer/quantity surveyor at each station, Rs. 40000/- per month per engineer will be deducted.
A quantity surveyor with working knowledge of measurement and, one surveyor with required surveying instruments and one draftsman having expertise of drafting on Auto Cad must be deputed for this work.
Within 15 days of issue of LoA, contractor will submit detailed bar chart, and also submit fortnightly progress report wrt bar chart. Penalty to the tune of Rs. 50000/- per month will be imposed for non-submission of progress report.
Payment schedule for cement, reinforcement and structural steel. 50% of accepted rate after supply at site and submission of original invoice and MTC.Balance 50% payment will be done after consumption of material at site.
Payment schedule for items involving supply and use of factory made /finished products( such as tiles, natural stones, granite, kota stone, paver block, chequered tiles, glass item, stainless steel , ACP, paint, aluminum items, galvalume sheet, ridge.40% of accepted rate after supply at site and submission of original invoice and MTC.Balance 60% payment will be done after consumption of material at site.
Contractor should also submit indemnity bond for payment as prescribed in item no 6 and 7 above in format as prescribed by Railway.
Contractor has to set up site office at each station on Railway premises having suitable facilities including office room with desktop computer and printing facility.
Formwork for all types of RCC works shall be made only with MS shuttering plates and MS pipe staging.
All architectural and Structural plans, design and proof check from reputed Govt. institutions as required during execution of work will be done by contractor, for which no additional payment will be made.
In case of cable cuts, action will be taken as per RB's letter no. 37.12 2003/Tele/RCIL/1 Pt. IX dated 24.06.2013 with updated correction slips as may be issued by RB from time to time.
The items covered under CPWD DSR-2021, CPWD Horticulture 2020 and SER-USSOR-2021 are tentative and approximate and these are considered for evaluation of DV only. However the items covered under CPWD DSR-2021, CPWD Horticulture 2020 and SER-USSOR-2021 may be altered within the scope of work as per instruction of Engineer- in Charge according to site requirement if required. Decision of Engineer in Charge in this regard will be final and binding to all.
IRGCC April-2022 with all correction slips up to date are attached.
IF required, contractor should mobillse to do night working for which they will be required to have their own sufficient lighting arrangement. No extra payment will be admissible on this account.
The Contractor with the help of his Engineer or Diploma holder , as the case be , shall make necessary Drawings, sketches, plotting, peg markings etc. as desired by the Engineer-in-charge. No extra cost shall be claimed on this account.
The quantities specified in the tender schedule are only approximate and liable to vary.
Execution of work for, Improvement of defective layout for removal of PSR - 110 KMPH , Improvement of Drainage system and Bad Bank in approach at Haur Station under Sr.DEN/East/KGP.
E-KGP-EAST-21-2026
E-KGP-EAST-21-2026
Open
Works - General
12 Months
Paschim Medinipur, West Bengal
₹0
₹16.0 L
14 May 2026
16 Apr 2026
30 Apr 2026
65 items across 3 schedules · ₹6,31,70,728.51 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| in filling in embankment, guide around buried type abutments, bridge refuges, platforms etc. with own earth conforming to Soil Class SQ1/SQ2/SQ3, after preparation as applicable, benching in banks wherever required, spreading in motor grader, bringing the moisture OMC, mechanical compaction to density and dressing of bank to final as per RDSO Specifications: IRS-0004 with latest correction 1) Foundation preparation, including additional earthwork on this, wherever required, shall be under relevant schedule item for 2) Payment for Earthwork under this be made based on the cross section calculated (i) with original of existing bank based on initial levels before doing benching and (ii) of the bank worked out with final prevailing guidelines. | — | — | — | — | |
| 1 | Class SQ2 | cum | 3000.00 | 253.42 | 7,60,260 |
| planting, including all lead & lift and required until properly rooted with. payment of only 40% will be 60% will be paid after 3 months period, only if the turfing is rooted on entire turfed area. | — | — | — | — | |
| 2 | sods, 10cm thick and 20cm square | 100 Sqm | 150.00 | 5,460.99 | 8,191.49 |
| 3 | driving and erecting in all types of wood pile 5m to 7m long without average dia. for protection of including two coats of coal tar paint as directed. Note: Payment will be actual driven length of pile. | Metre | 3000.00 | 190.4 | 5,71,200 |
| laying Non-woven Needle Punched Mechanically or Thermally bonded type for use as Separator/Filtration for formation as per RDSO Specification RDSO/2018/GE:IRS-0004 - Part I made of / Polyethylene / Polyamide or there of having apparent opening than or equal to 85 microns and at failure more than 50% in both including transportation labour, lead complete as directed by Engineer in- | — | — | — | — | |
| 4 | subgrade or prepared subgrade blanketing layer with minimum in Grab test, Trapezoidal Tear test test of 700N, 250 N and 1800 N | Sqm | 3600.00 | 170.98 | 6,15,528 |
| providing and installation of bored cast Reinforced Cement Concrete piles using piling Rig of specified diameter and pile cap of specified grade with Cement Concrete, using 20mm crushed stone aggregate and coarse approved quality, to carry a safe not less than specified, concreting batching, machine mixing, using Admixture in approved (as per IS:9103), placing with tremie off of pile top to remove laitance above cut off level etc., pumping and water complete in all respect as per drawing, specification and direction in charge. Note: 1. Payment for reinforcement shall be made Length of the pile for payment shall up to the bottom of RCC pile Cap. shall invariably be used in proportion to increase workability possible quantity of cement for of Design Mix Concrete unless it is approved citing reasons for not plasticiser at the stage of Mix Design and deduction shall be made as per item. | — | — | — | — | |
| 5 | diameter | Metre | 900.00 | 2,883.42 | 25,95,078 |
| 6 | and casting machine batched, mixed and machine vibrated Cement of specified grade as per approved Mix, mixed in Mobile Concrete Plant at site or RMC from plants, (Cast in-Situ/Pre-cast) in slab, side walls, toe wall and sumps filling head walls, thrust bed or any component using 20mm graded crushed aggregate and coarse sand of approved RCC box of any size including Plasticiser in approved proportions IS:9103), to modify workability without strength and durability, complete as and technical specifications as by Engineer in charge. N o t e : 1. for cement, reinforcement and shall be made extra under relevant Plasticiser shall invariably be used in proportion to increase workability possible quantity of cement for of Design Mix Concrete unless it is approved citing reasons at the Design and in that case deduction made as per relevant item. | cum | 300.00 | 2,880.63 | 8,64,189 |
| and shuttering including strutting, etc. and removal of form for : | — | — | — | — | |
| 7 | of bridge sub-structures, e.g. pier, wing wall, retaining wall, RCC box foundations, Abutment cap, Pier Cap, Platform & Pedestal over Pier cap, Diaphragm wall etc. up to 5m level | Sqm | 1700.00 | 674.52 | 11,46,684 |
| using Cement at Worksite | — | — | — | — | |
| 8 | Portland Cement 53 grade of brands/makes | MT | 130.00 | 8,964.18 | 11,65,343.4 |
| 9 | and laying Pitching with Stone weighing not less than 35kg each filled with spalls on slopes, laid over filter media including boulder apron in front of toe of embankment as per drawing and Technical (filter media to be paid under the relevant item). | cum | 250.00 | 1,565.26 | 3,91,315 |
| 10 | laying of coarse sand including with all labour, lead, lift, tools, crossing of tracks as per drawing and specification as directed by the in charge in case loose slush is at site of foundation before foundation or laying the filtering | cum | 300.00 | 973.1 | 2,91,930 |
| laying non pressure NP-4 Class RCC collars, jointing with 1:2 cement and sand mortar including testing of joints, earthwork with all labour and a complete job. Cement for mortar separately.(Pipes of 600mm dia will be laid using crane/hydra). | — | — | — | — | |
| 11 | 300mm dia. | Metre | 30.00 | 1,241.95 | 37,258.5 |
| Schedule total | ₹84,46,977.39 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
ACS1to9GCCApril2022.pdf
ATTACHMENT
CertificateofInformationregardingEmployment_2.pdf
ATTACHMENT
AnnexureVIA.pdf
ATTACHMENT
AnnexureVIB.pdf
ATTACHMENT
VENDERMANDATEFORM.pdf
ATTACHMENT
MinimumwagesPFESIShramikKalyanPortal.pdf
ATTACHMENT
Annexure-II.pdf
ATTACHMENT
2018_CE-I_CT_9Date04_06_2018.pdf
ATTACHMENT
2003_Tele_RCIL_1Pt.IXdated24.06.2013.pdf
ATTACHMENT
STCablecutting.pdf
ATTACHMENT
SpecialConditionofTrackRenewal2025.pdf
ATTACHMENT
CivilSpecialCondition_F.pdf
ATTACHMENT
CTIndianRailwaysStandardGeneralConditionsofContractApril- ACS 10 GCC April 2022
ATTACHMENT
BidCapacityFormat-GCC2022.pdf
ATTACHMENT
SPECIALCONDITIONSFORP.WAYWORKS11092022.pdf
ATTACHMENT
GCC_April-2022.pdf
ATTACHMENT
SpecialconditionofallcontractFF.pdf
ATTACHMENT
ACS-10025_03_04RBCE_CE-I-CTIndianRailwaysStandardGeneralConditionsofContractApril-2022AdvanceCorrectionSlipNo_10.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .