| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.7 CrAccepted-AOC H 99 6TH CROSS STREET R M COLONY DINDIGUL | ₹6.7 Cr | L1 | Accepted-AOC Work order |
| 2 | L2₹6.8 Cr+₹7.1 L (1.05%)Rejected-Finance MADURAI MADURAI TAMIL NADU | MADURAI | TAMIL NADU | 625001 | ₹6.8 Cr+₹7.1 L (1.05%) | L2 | Rejected-Finance Rejected |
Tender Value
Refer Docs
EMD Value
₹6.9 L
Closing Date
25 Jun 2025, 3:00 pmClosed
The Project Director,DRDA,Dindigul
The Project Director,DRDA,Dindigul
Upgradation Strengthening the Roads 2 Nos in Package No TN05-03 Natham Block of Dindigul District Under SASCI 2025-2026 Roads
2025_RDTN_570941_1
DPIR.No. 2866-2025- DATE 06.06.2025
Open Tender
Civil Works
Item Wise
270 days
DRDA
Upgradation Strengthening the Roads 2 Nos in Package No TN05-03 Natham Block of Dindigul District Under SASCI 2025-2026 Roads
3 documents required · 3 mandatory
₹0
₹6.9 L
DRDA,DINDIGUL
2 Aug 2025
19 Jun 2025
25 Jun 2025
19 Jun 2025
25 Jun 2025
19 Jun 2025
20 Jun 2025
Amount
1.Strengthening of the road from Othinipatti to Odugampatti (via) Panchayampatti, Palapatti in Kuttupatti Panchayat KM 2/300 - 5/500, (R-61). Estimate Amount : RS.122.42 LAKHS
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp.
Earth work excavation from borrow pits for filling in all classes of soils, such as gravelly soil hard red earth shales, murrams gravel stoney earth and earth mixed with 50% lair sized boulders and hard gravel soil exept sand and hard rock requiring blasting as per SS 20A (Box cutting)
Picking 5cm to 10cm Old metalled surface including all charges etc complete
Providing and Laying Gravel to a compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
Applying TACK COAT over Primed WBM/WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Providing and fixing of KM stones for standard specification
Providing and fixing of HM stones for standard specification
Providin 60cm Equilateral Trainagle Cautionary signboard
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
2.Strengthening of the road at L.Malaiyur road in Lingavadi KM 0/000 - 3/835 (R-190) Estimate Amount : RS.595.66 LAKHS
Providing and Laying Gravel to a compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Supplying and erecting centering shuttering including necessary supports for planesurface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etcusing mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mildsteel angles of size 25mmx25mmx3mm for boarding laid over silver oak (countrywood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre andsupported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centrecomplete complying with standard specifications and as directed by departmentalofficers including conveyance of all materials to site and proper centering etc complete.
Cement concrete 1:3:6 mix using 20mm ISS metal including cost andconveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for bed blocks for 10 cum
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse with Expansion joints
Providing 60cm Equilateral triangle cautionary sign board
Providing Side Drain at Ch. Of 0/500-1/000
Cemant Concrete 1:3:6 using 40mm gauge hard broken stone jelly for foundation including watering necessary and laid in layers not more than 15cm thick compacting etc,
Cement concrete 1:2:4 mix using 20mm I SS size hard granite broken metal from approved quarry including cost and conveyance of all materials to site including cost of cement and including all labour charges etc., complete as directed by the Engineer
Providing Side Drain at Ch. Of 1/0-2/000
Cemant Concrete 1:3:6 using 40mm gauge hard broken stone jelly for foundation including watering necessary and laid in layers not more than 15cm thick compacting etc,
Cement concrete 1:2:4 mix using 20mm I SS size hard granite broken metal from approved quarry including cost and conveyance of all materials to site including cost of cement and including all labour charges etc., complete as directed by the Engineer
Providing Side Drain at Ch. Of 2/0-3/000
Cemant Concrete 1:3:6 using 40mm gauge hard broken stone jelly for foundation including watering necessary and laid in layers not more than 15cm thick compacting etc,
Cement concrete 1:2:4 mix using 20mm I SS size hard granite broken metal from approved quarry including cost and conveyance of all materials to site including cost of cement and including all labour charges etc., complete as directed by the Engineer
Providing Side Drain at Ch. Of 3/0-3/835
Cemant Concrete 1:3:6 using 40mm gauge hard broken stone jelly for foundation including watering necessary and laid in layers not more than 15cm thick compacting etc,
Cement concrete 1:2:4 mix using 20mm I SS size hard granite broken metal from approved quarry including cost and conveyance of all materials to site including cost of cement and including all labour charges etc., complete as directed by the Engineer
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
SRI KUMARAN CONSTRUCTION (BID ID -1379062)
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .