| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹7.6 LAccepted-AOC 76 58 A1 KAMARAJ NAGAR SALEM CAMP METTUR DAM 636 452 | METTUR DAM | SALEM | TAMIL NADU | 636452 | ₹7.6 L Quoted ₹7.0 L | 1 | Accepted-AOC L1 |
| 2 | 2₹7.3 LRejected-AOC H 6 HOUSING BOARD UNIT MATHAVANKUTTAI P O METTUR DAM 636 452 | METTUR DAM | SALEM | TAMIL NADU | 636452 | ₹7.3 L | 2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | Jose Enterprises L1 | R K ENGINEERING CONTRACTOR L2 |
|---|---|---|---|---|---|
| 1.00 | Charges for removing of sacrificing heating elements. | 144 | Nos. | 609 ₹87,696 Lowest | 639 ₹92,016 |
| 2.00 | Charges for renewal of sacrificing heating elements ( 200 mm height)Loading and transporting from central stores to boiler area, unloading and lifting the new Sacrificing baskets from ground floor to 16 m area, moving the basket from one end of APH to center of APH's, lifting to 20m level, moving basket inside the APH, lowering to APH rotor area and positioning inside the rotor segment properly. | 144 | Nos. | 1,987 ₹2,86,128 Lowest | 2,084 ₹3,00,096 |
| 3.00 | Charges for dismantling the hot/ intermediate end basket removal door in theflue gas path above APH rotor, providing gantry arrangements for lifting the hot/intermediate end baskets and Fitting back the hot end basket removal door and refitting after completion of work. | 48 | Nos. | 104 ₹4,992 Lowest | 109 ₹5,232 |
| 4.00 | Lifting the deteriorated hot/ intermediate end baskets from rotor and removing the basket outside of the APH, Lowering to 16 m level and moving the baskets to outer end of APH and lowering the baskets to '0' m level in between PA & FD fans. | 48 | Nos. | 2,324 ₹1,11,552 Lowest | 2,437 ₹1,16,976 |
| 5.00 | Renewal of intermediate end heating elements ( 850 mm height) | 48 | Nos. | 3,312 ₹1,58,976 Lowest | 3,474 ₹1,66,752 |
| 6.00 | Loading of deteriorated hot/intermediate baskets on the lorry using departmental crane and transporting to central stores and unloading for devolution. | 48 | Nos. | 373 ₹17,904 Lowest | 392 ₹18,816 |
| 7.00 | Transporting charges for retrieved baskets devolution | 1 | LS | 9,180 ₹9,180 Lowest | 9,630 ₹9,630 |
| 8.00 | Cutting gas | 1 | Set | 3,765 ₹3,765 Lowest | 3,949 ₹3,949 |
| 9.00 | Welding rod | 14 | Kg | 459 ₹6,426 Lowest | 482 ₹6,748 |
| 10.00 | Consumables and T & Ps | 1 | LS | 10,873 ₹10,873 Lowest | 11,406 ₹11,406 |
Tender Value
Refer Docs
EMD Value
₹7,300
Closing Date
18 Feb 2026, 2:00 pmClosed
Superintending Engineer /Mechanical-I/MTPS-I
Office of the Superintending Engineer / Mechanical -I Mettur Thermal Power Station- I Mettur Dam-636406
MTPS I BM Unit I AOH 2026 2027 Renewal of Various types of heating elements in APH 1A and 1B and other related works
2026_EB_651017_1
CE / MTPS-I / SE / M-I / BM /OT.491 / 2025-26
Open Tender
Power/Energy Projects/Products
Works
20 days
Mettur Thermal Power Station-I / Mettur Dam
As per the Tender Specifications
4 documents required · 4 mandatory
₹0
₹7,300
Yes
1 Aug 2026
4 Feb 2026
19 Feb 2026
4 Feb 2026
18 Feb 2026
4 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Charges for removing of sacrificing heating elements. | 144 | Nos. | - | - |
| 2 | Charges for renewal of sacrificing heating elements ( 200 mm height)Loading and transporting from central stores to boiler area, unloading and lifting the new Sacrificing baskets from ground floor to 16 m area, moving the basket from one end of APH to center of APH's, lifting to 20m level, moving basket inside the APH, lowering to APH rotor area and positioning inside the rotor segment properly. | 144 | Nos. | - | - |
| 3 | Charges for dismantling the hot/ intermediate end basket removal door in theflue gas path above APH rotor, providing gantry arrangements for lifting the hot/intermediate end baskets and Fitting back the hot end basket removal door and refitting after completion of work. | 48 | Nos. | - | - |
| 4 | Lifting the deteriorated hot/ intermediate end baskets from rotor and removing the basket outside of the APH, Lowering to 16 m level and moving the baskets to outer end of APH and lowering the baskets to '0' m level in between PA & FD fans. | 48 | Nos. | - | - |
| 5 | Renewal of intermediate end heating elements ( 850 mm height) | 48 | Nos. | - | - |
| 6 | Loading of deteriorated hot/intermediate baskets on the lorry using departmental crane and transporting to central stores and unloading for devolution. | 48 | Nos. | - | - |
| 7 | Transporting charges for retrieved baskets devolution | 1 | LS | - | - |
| 8 | Cutting gas | 1 | Set | - | - |
| 9 | Welding rod | 14 | Kg | - | - |
| 10 | Consumables and T & Ps | 1 | LS | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.PDF
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.79 MB
BOQ_780749.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].