Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.0 CrAccepted-AOC GRAM KHUSHHALPUR DIWAN SINGH TEHSIL NAGINA DISTRICT BIJNOR | BIJNOR | UTTAR PRADESH | 246701 | ₹3.0 Cr | L1 | Accepted-AOC Responsive |
| 2 | L2₹3.0 CrRejected-Finance | ₹3.0 Cr | L2 | Rejected-Finance Responsive |
Tender Value
₹3 Cr
EMD Value
₹17 L
Closing Date
13 Feb 2026, 12:00 pmClosed
SE Rampur Circle pwd rampur
Office of SE Rampur Circle pwd rampur
Repair and protection work of approach road on Kiratpur, Nagina, Harewali, Sherkot road km-28 on Kho river.
2026_CEMBD_1113384_1
497/E-Nivida-R.Circle/25-26 Dt. 20.01.2026
Open Tender
Civil Works - Bridges
Najibabad
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,354
₹17 L
Office of SE Rampur Circle pwd rampur
9 Mar 2026
7 Feb 2026
13 Feb 2026
7 Feb 2026
13 Feb 2026
7 Feb 2026
9 Feb 2026
Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2. Including cost of All material, labour cess, Royalty, T&P, all taxes but excluding cost of GST.
Supply & Laying of empty cement bags filled with local sand i/c stiching stacking at site as per direction of engineer. (Chap. No. 19, New item no. 1). Including cost of All material, labour cess, Royalty, T&P, all taxes but excluding cost of GST.
Hire Charges of J.C.B. Machine including driver with Fuel Charges etc. complete (S.I. no. 24). Including cost of All material, labour cess, Royalty, T&P, all taxes but excluding cost of GST.
Supplying of Tactor Trolly including Fuel etc. (chap. No. 2, s.no. 26). Including cost of All material, labour cess, Royalty, T&P, all taxes but excluding cost of GST.
Bracing of Ballies screen including all fitting complete for work in water. Including cost of All material, labour cess, Royalty, T&P, all taxes but excluding cost of GST.
Pilling 12 cm to 15 cm dia ballies in silty and sandy strata upto 3 m depth of ballie in water. Including cost of All material, labour cess, Royalty, T&P, all taxes but excluding cost of GST.
Supplying Euclyptus Balli, 12 cm to 15 cm dia and length 5 m long. Including cost of All material, labour cess, Royalty, T&P, all taxes but excluding cost of GST.
Excavation for roadwork in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m. Including cost of All material, labour cess, Royalty, T&P, all taxes but excluding cost of GST.
Providing and laying of boulder apron laid in wire crates with 4 mm dia GI wire conforming to IS:280 and IS:4826 in 100 mm x 100 mm mesh (woven diagonally) including 10 per cent extra for laps and joints laid with stone boulders weighing not less than 25 kg each as per drawing and technical specifications Clause 1301. Including cost of All material, labour cess, Royalty, T&P, all taxes but excluding cost of GST.
Providing and laying filter material underneath pitching in slopes complete as per drawing and technical specifications Clause 1302. Including cost of All material, labour cess, Royalty, T&P, all taxes but excluding cost of GST.
Providing and laying pitching on slopes laid over prepared filter media as per drawing and technical specifications Clause 1302. Including cost of All material, labour cess, Royalty, T&P, all taxes but excluding cost of GST.
Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. Including cost of All material, labour cess, Royalty, T&P, all taxes but excluding cost of GST.
M-150 class brick work in 1:3 cement and coarse sand mortar in foundation and plinth including supply of all materials, labour and T&P etc. required for proper completion of the work. (Chap. 6, S.no. 307). Including cost of All material, labour cess, Royalty, T&P, all taxes but excluding cost of GST.
12 mm thick plaster with 1 part of cement and 3 part ofcoarse sand over brick work including supply of all materials, labour and T&P etc. required for proper completion of work. (Chap. 13, S.no. 583). Including cost of All material, labour cess, Royalty, T&P, all taxes but excluding cost of GST.
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications.PCC M-15. Including cost of All material, labour cess, Royalty, T&P, all taxes but excluding cost of GST.
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 8.94 MB
T201.pdf
Tender Documents • 1.11 MB
BOQ_2060756.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid