Loading…
Loading…
Tender ID
Tender Value
₹14.9 Cr
EMD Value
₹8.9 L
Closing Date
5 Mar 2026, 3:00 pmClosed
Yes (up to 3 members)
No
Two Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
90 days
Expenditure
(PH-31)
DEN E
29 conditions · 3 needing a document upload
The tenderer must have minimum average annual contractual turnover of 'V/N' or 'V'; whichever is less, where 'V'= Advertised value of the tender in crores of Rupees and 'N'= Number of years prescribed for completion of work for which bids have been invited.
The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover.
The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
The JV shall satisfy the requirement of "Financial Eligibility" mentioned above. The "financial capacity" of the lead member of JV shall not be less than 51% of the financial eligibility criteria mentioned above. The arithmetic sum of individual "financial capacity" of all the members shall be taken as JV's "financial capacity" to satisfy this requirement. Note: Contractual payment received by a Member in an earlier JV shall be reckoned only to the extent of the concerned member's share in that JV for the purpose of satisfying compliance of the above mentioned financial eligibility criteria in the tender under consideration.
The Balance Sheet and all other financial documents attested/ certified by CAs to substantiate fulfilment of Financial Eligibility Criteria should be with UDIN, failing which the offer is likely to be rejected without any further refrence.
The tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i) Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or (ii) Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or (iii) One similar work costing not less than the amount equal to 60% of advertised value of the tender.
Definition of similar work: "Execution of P.Way work on running line".
In case of tenders for composite works (e.g. works involving more than one distinct component, such as Civil Engineering works, S&T works, Electrical works, OHE works etc. and in the case of major bridges - substructure, superstructure etc.), tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i) Three similar works each costing not less than the amount equal to 30% of advertised value of each component of tender, or (ii) Two similar works each costing not less than the amount equal to 40% of advertised value of each component of tender, or (iii) One similar work each costing not less than the amount equal to 60% of advertised value of each component of tender. Note for : Separate completed works of minimum required values shall also be considered for fulfillment of technical eligibility criteria for different components. In such cases, what constitutes a component in a composite work shall be clearly pre-defined with estimated tender cost of it, as part of the tender documents without any ambiguity.
To evaluate the technical eligibility of tenderer, only components of work as stipulated in tender documents for evaluation of technical eligibility, shall be considered. The scope of work covered in other remaining components shall be either executed by tenderer himself if he has work experience as mentioned in clause 7 of the Standard General Conditions of Contractor through subcontractor fulfilling the requirements as per clause 7 of the Standard General Conditions of Contract or jointly i.e., partly himself and remaining through subcontractor, with prior approval of Chief Engineer in writing. However, if required in tender documents by way of Special Conditions, a formal agreement duly notarised, legally enforceable in the court of law, shall be executed by the main contractor with the subcontractor for the component(s) of work proposed to be executed by the subcontractor(s), and shall be submitted along with the 1.2.1 offer for considering subletting of that scope of work towards fulfilment of technical eligibility. Such subcontractor must fulfill technical eligibility criteria as follows: The subcontractor shall have successfully completed at least one work similar to work proposed for subcontract, costing not less than 35% value of work to be subletted, in last 5 years, ending last day of month previous to the one in which tender is invited through a works contract. Note: for subletting of work costing up to Rs 50 lakh, no previous work experience of subcontractor shall be asked for by the Railway. In case after award of contract or during execution of work it becomes necessary for contractor to change subcontractor, the same shall be done with subcontractor(s) fulfilling the requirements as per clause 7 of the Standard General Conditions of Contract, with prior approval of Chief Engineer in writing.
Work experience certificate from private individual shall not be considered. However, in addition to work experience certificates issued by any Govt. Organisation, work experience certificate issued by Public listed company having average annual turnover of Rs 500 crore and above in last 3 financial years excluding the current financial year, listed on National Stock Exchange or Bombay Stock Exchange, incorporated/registered at least 5 years prior to the date of closing of tender, shall also be considered provided the work experience certificate has been issued by a person authorized by the Public listed company to issue such certificates. In case tenderer submits work experience certificate issued by public listed company, the tenderer shall also submit along with work experience certificate, the relevant copy of work order, bill of quantities, bill wise details of payment received duly certified by Chartered Accountant, TDS certificates for all payments received and copy of final/last bill paid by company in support of above work experience certificate.
Explanation for Eligibility criteria:
[1] Substantially Completed Work means an ongoing work in which payment equal to or more than 90% of the present contract value (excluding the payment made for adjustment of Price variation (PVC), if any) has been made to the contractor in that ongoing contract and no proceedings of termination of contract on Contractor's default has been initiated. The credential certificate in this regard should have been issued not prior to 60 days of date of invitation of present tender. [2] In case a work is started prior to 07 (seven) years, ending last day of month previous to the one in which tender is invited, but completed in last 07 (seven) years, ending last day of month previous to the one in which tender is invited, the completed work shall be considered for fulfillment of credentials. [3] If a work is physically completed and completion certificate to this extent is issued by the concerned organization but final bill is pending, such work shall be considered for fulfillment of credentials. [4] In case of completed work, the value of final bill (gross amount) including the PVC amount (if paid) shall be considered 1.4.1 as the completion cost of work. In case final bill is pending, only the total gross amount already paid including the PVC amount (if paid) shall be considered as the completion cost of work. In case of substantially completed work, the total gross amount already paid including the PVC amount (if paid), as mentioned in the certificate, shall be considered as the cost of substantially completed work. [5] If a bidder has successfully completed a work as subcontractor and the work experience certificate has been issued for such work to the subcontractor by a Govt. Organization or public listed company as defined in Note for Item 10.1 Para 10 of the Tender Form (Second Sheet), the same shall be considered for the purpose of fulfillment of credentials. [6] In case a work is considered similar in nature for fulfillment of technical credentials, the overall cost including the PVC amount (if paid) of that completed work or substantially completed work, shall be considered and no separate evaluation for each component of that work shall be made to decide eligibility.
[7] In case of newly formed partnership firm, the credentials of individual partners from previous propriety firm(s) or dissolved previous partnership firm(s) or split previous partnership firm(s), shall be considered only to the extent of their share in previous entity on the date of dissolution / split and their share in newly formed partnership firm. For example, a partner A had 30% share in previous entity and his share in present partnership firm is 20%. In the present tender under consideration, the credentials of partner A will be considered to the extent of 0.3*0.2*value of the work done in the previous entity. For this purpose, the tenderer shall submit along with his bid all the relevant documents which include copy of previous partnership deed(s), dissolution deed(s) and proof of surrender of PAN No.(s) in case of dissolution of partnership firm(s) etc. [8] In case of existing partnership firm, if any one or more partners quit the partnership firm, the credentials of remaining partnership firm shall be re-worked out i.e., the quitting partner(s) shall take away his credentials to the extent of his share on 1.4.2 the date of quitting the partnership firm (e.g. in a partnership firm of partners A, B & C having share 30%, 30% & 40% respectively and credentials of Rs 10 crore; in case partner C quits the firm, the credentials of this partnership firm shall remain as Rs 6 crore). For this purpose, the tenderer shall submit along with his bid all the relevant documents which include copy of previous partnership deed(s), dissolution deed(s) and proof of surrender of PAN No.(s) in case of dissolution of partnership firm(s) etc. [9] In case of existing partnership firm if any new partner(s) joins the firm without any modification in the name and PAN/TAN no. of the firm, the credentials of partnership firm shall get enhanced to the extent of credentials of newly added partner(s) on the same principles as mentioned in item 6 above. For this purpose, the tenderer shall submit along with his bid all the relevant documents which include copy of previous partnership deeds, dissolution/splitting deeds and proof of surrender of PAN No.(s) in case of dissolution of partnership firm etc.
10. Any partner in a partnership firm cannot use or claim his credentials in any other firm without leaving the partnership firm i.e., In a partnership firm of A&B partners, A or B partner cannot use credentials of partnership firm of A&B partners in any other partnership firm or propriety firm without leaving partnership firm of A&B partners. 11. In case a partner in a partnership firm is replaced due to succession as per succession law, the proportion of credentials of the previous partner will be passed on to the successor. 12. If the percentage share among partners of a partnership firm is changed, but the partners remain the same, the credentials of the firm before such modification in the share will continue to be considered for the firm as it is without any change in 1.4.3 their value. Further, in case a partner of partnership firm retires without taking away any credentials from the firm, the credentials of partnership firm shall remain the same as it is without any change in their value. 13. In a partnership firm "AB" of A&B partners, in case A also works as propriety firm "P" or partner in some other partnership firm "AX", credentials of A in propriety firm "P" or in other partnership firm "AX" earned after the date of becoming a partner of the firm AB shall not be added in partnership firm AB. 14. In case a tenderer is LLP, the credentials of tenderer shall be worked out on above lines similar to a partnership firm. 15. In case company A is merged with company B, then company B would get the credentials of company A also.]
Technical Eligibility Criteria of JV ('a' or 'b' mentioned hereunder):
(a) For Works without composite components : The technical eligibility for the work as per para 10.1 above, shall be satisfied by either the 'JV in its own name & style' or 'Lead member of the JV'. Each other (non-lead) member(s) of JV, who is/ are not satisfying the technical eligibility for the work as per para 10.1 above, shall have technical capacity of minimum 1.5.1 10% of the cost of work i.e., each non-lead member of JV member must have satisfactorily completed or substantially completed during the last 07 (seven) years, ending last day of month previous to the one in which tender is invited, one similar single work for a minimum of 10% of advertised value of the tender.
(b) For works with composite components : The technical eligibility for major component of work as per para 10.1 above, shall be satisfied by either the 'JV in its own name & style' or 'Lead member of the JV' and technical eligibility for other component(s) of work as per para 10.1 above, shall be satisfied by either the 'JV in its own name & style' or 'any member of the JV'. Each other (non-lead)member(s) of JV, who is/ are not satisfying the technical eligibility for any component of the work as per 1.5.2 para 10.1 above, shall have technical capacity of minimum 10% of the cost of any component of work mentioned in technical eligibility criteria. i.e., each other (nonlead) member of must have satisfactorily completed or substantially completed during the last 07 (seven) years, ending last day of month previous to the one in which tender is invited, one similar single work for a minimum of 10% of cost of any component of work mentioned in technical eligibility criteria.
Note : a) The Major component of the work for this purpose shall be the component of work having highest value. In cases where value of two or more component of work is same, any one work can be classified as Major component of work. b) Value of a completed work done by a 1.5.3 Member in an earlier JV shall be reckoned only to the extent of the concerned member's share in that JV for the purpose of satisfying his/her compliance to the above mentioned technical eligibility criteria in the tender under consideration.
88 conditions · 1 needing a document upload
Compliance with the GST Act, 2017 - Change in para (a) of clause 6, part I of Indian Railway Standard General Conditions of Contract, April'2022.
Before submitting a tender, the tenderer will be deemed to have satisfied himself by actual inspection of the site and locality of the works, that all conditions liable to be encountered during the execution of the works are taken into account and that the rates he enters in the tender forms are adequate and all inclusive to accord with the provisions in Clause-37 of the Standard General Conditions of Contract for the completion of works to the entire satisfaction of the Engineer.
Tenderers will examine the various provisions of The Central Goods and Services Tax Act, 2017(CGST)/ Integrated Goods and Services Tax Act, 2017(IGST)/ Union Territory Goods and Services Tax Act, 2017(UTGST)/ respective state's State Goods and Services Tax Act (SGST) also, as notified by Central/State Govt.& as amended from time to time and applicable taxes before bidding. Tenderers will ensure that full benefit of Input Tax Credit (ITC) likely to be availed by them is duly considered while quoting rates.
The successful tenderer who is liable to be registered under CGST/IGST/UTGST/SGST Act shall submit GSTIN along with other details required under CGST/IGST/UTGST/SGST Act to railway immediately after the award of contract, without which no payment shall be released to the Contractor. The Contractor shall be responsible for deposition of applicable GST to the concerned authority.
In case the successful tenderer is not liable to be registered under CGST/IGST/UTGST/ SGST Act, the railway shall deduct the applicable GST from his/their bills under reverse charge mechanism (RCM) and deposit the same to the concerned authority.
Contractor shall be liable to pay/refund the amount collected as GST to the Indian Railways along with interest and penalties, if any imposed by the authorities, in case GST input tax credit of Indian Railways is denied/rejected by the tax authortties due to reasons mentioned below but not limited to: Wrong/incorrect invoices issued by Contractor; No-filing of GST returns; Nonpayment of GST collected from Indian Railways to the authorities; Any other non-compliance done by Contractor; General Indemnity: Contractor hereby agrees to indemnify and hold harmless the Indian Railways from and against any and all losses, including loss on account of Input Tax Credit and all losses incurred by the Indian Railways relating to or arising out of or in connection with any actual or threatened claim, legal action, proceedings, prosecution or inquiry by or against the Indian Railways arising out, directly or indirectly, of failure by the contractor to comply with the provisions of GST and related laws, or based upon or arising from any failure by the Contractor. Retention Money: Any payment liable to be paid by Indian Railways to contractor against the goods or services or both supplied by such contractor to Indian Railways shall be kept on hold in case supplier makes any non-compliance of any of the GST law.
1) Estt. No. 53/East/KGP/2025, Allocation: SF (PH-31). Rs.56530250.08/- ID- 12.03.31.24.3.52.023 2) Estt. No. 58/East/KGP/2025, Allocation: SF (PH-31). Rs.50664205.20 ID- 12.03.31.24.3.52.027 3) Estt. No. 57/East/KGP/2025, Allocation: SF (PH-31). Rs.41731539.10/- ID12.03.31.24.3.52.025
All the bidders / tenderers should ensure that they are GST compliant and their quoted rates are as per GST law.
Tender value is inclusive of GST. Agencies must quote their rates including GST.
In the instant tender GST is applicable at the rate of 18% (Eighteen percent).
However, inter se ranking will be done on the quoted value including GST applicable on the date of opening.
In case of increase or decrease in GST rate, same will be either paid by railway or recovered from the agency as the case may be.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
In case damage is caused to OFC / Quad cable / signaling cable during execution of the work, the contractor is liable to pay a penalty for damaging the cable. Penalty shall not be levied in case of the following: (i) Detailed cable route plan not provided by concerned department or cable is not protected as per laid down procedures, (ii) The alignment of the cable does not tally with the information provided to the contractor, (iii) The cable depth is found to be less than 800 mm from normal ground level, (iv) No representative of S&T department / Rail Tel was available at site guarding the cables on the fixed pre determined date and time. Penalty to be imposed for damages to cable shall be as under: (a) Only Quad cable or Signaling cable ----- Rs.1.00 Lakh per location, (b) Only OFC ----- Rs.1.25 Lakh per location, (c) Both OFC & Quad ----- Rs.1.50 Lakh per location, (d) Electrical Cable ----- Rs.1.00 Lakh per location. (Telecom Circular No. 17/2013 issued by Railway Board vide No. 2003/Tele/RCIL/1 Pt.IX dated 24.06.2013 is binding to this contract and should be followed in spirit).
If necessary, the contractor have to make drawings/designs of the subjected work (or part of work) and have to make it approved from any recognized Govt. college/university/institution and if necessary have to make it signed by Railway officials of his own.
The contractor for carrying out any construction work in West Bengal/Jharkhand must get themselves registered from the Registering Officer under Section-7 of the Building and Other Construction Workers Act, 1996 and rules made thereto by the Jharkhand/West Bengal government and submit certificate of registration issued from the Registering Officer of the West Bengal state govt.(labour department). For enactment of this Act, the contractor shall be required to pay cess @ 1% of cost of construction work to be deducted form each bill. Cost of material shall be outside the purview of cess, when supplied under a separate schedule item.
As per latest CE s Circular No. 271, Transparency Board is to be provided at work site by the agency free of cost as per direction of Engineer-In-Charge.
In case of exigency, the contractor has to execute the work in any section of Sr. DEN/East/KGP.
All materials to be supplied by the contractor should be got approved by the Engineer-in-charge before use in the work.
Unless specifically mentioned in the schedule of rates all materials required for execution of work will be supplied by the contractor free of cost as per standard specifications and approved by the Engineer-in-charge.
Contractor will be responsible for safety of staff working on site of work. All safety measure will be taken by contractors for movement of traffic during the operation.
On Completion of the work rubbish, unused materials etc. if any should be removed and deposited at nominated place and as directed and the same are to be made neat and clean. No extra will be paid for this.
Tenderer or contractor will have to execute the work taking necessary precautions for safety of works, Passenger, traffic etc.
Necessary materials must be available in the contractor's godown to attend any break down.
Engineering Guide line (Civil) to be followed by the contractor to supervise the work. The contractor also has to provide water meter suitable to delivery pipe of pump as a part of a contract without charging any cost from the Railway.
The non schedule items should be inclusive of all lead, lift, taxes, fabrication, fitting and all other charges if any.
Tenderer/s should furnish their GST Registration No. along with the tender document.
The mode of payment through 'Letter of Credit' for all tenders having advertised value of Rs. 10 lakh and above as per Railway Board's letter No. 2018/CE-I/CT/9, Dtd.04.06.2018 has been followed . Copy attached in document.
Contractor shall not start any work without the presence of the IOW or PWI at site. In case the contractor's representative starts any work in absence of IOW or PWI, it shall be treated as unauthorized and illegal tampering with the track and shall be liable for action.
The Railway shall not guarantee any provision for supplying electrical power or road approach to the site of work or for granting of block to the FOB or blocks for OHE power or traffic or any other facilities not committed to in the schedule. Granting permission for any of these or others in any as required or demanded by the Agency shall only depend on the feasibility and situation. Therefore the Agency shall not have any claim in this regard.
Medium class sand to be used in the plastering works.
All GI Pipe line works is to be carried out only with the approved brand,medium class as per the I.S.Specification i.e. G.I.pipe of Jindal/Bansal/Tata Brand or other equivalent brand as will be approved by ADEN concerned are to be supplied and used. Meterials should be got confirm to the approval of the Engineer in charge or his authorised representative at site to ensure that only approved brand of pipes are supplied and used by the Contractor. Contractor has to produce the necessary vouchers for procurement of pipes of approved medium varieties and proper accountal of pipes will have to be maintained by I.O.W
The rates are inclusive of all taxes where applicable and other charges as leviable by the State Government/Central Government.
Tenderer has to make his own service Road for carrying materials and equipment's. No separate payment will be made for this purpose. However, Railway will allow to make such Road in the available Railway Land.
All the steel work and fitting materials like M.S plate, M.S.bolts, rivets, service bolts, nuts, washers, electrodes etc. will conform to relevant IS specifications.
All safety measure will be taken by contractors for movement of traffic during the operation.
During the course of work steel are to be got tested by the contractor at their own cost to ascertain their conformity to specification as and when required by the Engineer-in-charge or his authorized representative.
All the scrap and released materials to be returned to the Railway as per instructions given by the Engineer in - charge or his authorized representative at their nominated places after completion of the work.
The steel that will be supplied by the contractor should conform to I.S. 226/I.S. 1977 for mild steel and I.S. 1481 for rivets followed with latest corrections if any. All steel section, Rivets, Paint, etc. are to be got tested as per relevant BIS codes at the contractors expense by the Chief Chemist and Metallurgist, S.E.Railway , Kharagpur or at National Test House, Alipore, Kolkata or at IIT, Kharagpur as found convenient by the Railway. If the test results does not confirm to the relevant IS specifications, the whole lot / lots of materials shall be rejected and got removed from the site by the contractor at the contractor s cost. No payment will be made for rejected works. Manufactures test certificate is to be submitted by the contractor along with necessary purchase vouchers etc.
All the works, which are to be done under traffic block, in electrified territory, contractor will have to take all precautions for safety of track and running trains as well as safety of his labour in terms of Indian Railways P.Way manual.
The Contractor with the help of his Engineer or Diploma holder , as the case be , shall make necessary Drawings, sketches, plotting, peg markings etc. as desired by the Engineer-in-charge. No extra cost shall be claimed on this account.
The agency should depute a trained and certified supervisor duly certified by AEN.
The Contractor should be make available all the necessary tools, plants and equipment for execution of the above work at site during execution of work.
The vehicles and equipment of contractors can be drafted by Railway Administration in case of Accidents or Natural calamities involving human lives, and payment in respect of that would be made by operating the item as a non scheduled item.
No compensation towards any accident what so ever will be paid by the Railway.
Special Condition of Civil work is attached.
Special Condition of P.Way work is attached.
Special conditions of contracts for all contracts is attached.
Special conditions for Electrical portion of work :- 1. The Civil contractor should carry out the Electrical portion work by Electrical contractor having valid electrical license. 2. The work will be executed under supervision of SSE(Electrical) of concerned section and all the measurements, MB related to electrical work will be recorded by him. 3. All the necessary drawings and Makes of Schedule items are to be got approved before supply by Sr.DEE(G)/KGP. 4. Inspection and Testing by Rites /authorized railway representative to be followed as per extant rules. 5. All the electrical equipment's will be star rated and energy efficient. 6. MCBs are to be 'C' type and MCCBs are to be microprocessor based. 7. On Account payment is to be done as per the payment conditions enclosed.
Special condition for Amrit Bharat station improvement work : -
Billing will be done by contractor's eMB on IRWCMS.
Contractor should deploy one civil graduate engineer, one civil diploma engineer and one electrical engineer (graduate/diploma) at each station.
In case of non deployment of engineer/quantity surveyor at each station, Rs. 40000/- per month per engineer will be deducted.
A quantity surveyor with working knowledge of measurement and, one surveyor with required surveying instruments and one draftsman having expertise of drafting on Auto Cad must be deputed for this work.
Within 15 days of issue of LoA, contractor will submit detailed bar chart, and also submit fortnightly progress report wrt bar chart. Penalty to the tune of Rs. 50000/- per month will be imposed for non-submission of progress report.
Payment schedule for cement, reinforcement and structural steel. 50% of accepted rate after supply at site and submission of original invoice and MTC.Balance 50% payment will be done after consumption of material at site.
Payment schedule for items involving supply and use of factory made /finished products( such as tiles, natural stones, granite, kota stone, paver block, chequered tiles, glass item, stainless steel , ACP, paint, aluminum items, galvalume sheet, ridge.40% of accepted rate after supply at site and submission of original invoice and MTC.Balance 60% payment will be done after consumption of material at site.
Contractor should also submit indemnity bond for payment as prescribed in item no 6 and 7 above in format as prescribed by Railway.
Contractor has to set up site office at each station on Railway premises having suitable facilities including office room with desktop computer and printing facility.
Formwork for all types of RCC works shall be made only with MS shuttering plates and MS pipe staging.
All architectural and Structural plans, design and proof check from reputed Govt. institutions as required during execution of work will be done by contractor, for which no additional payment will be made.
In case of cable cuts, action will be taken as per RB's letter no. 37.12 2003/Tele/RCIL/1 Pt. IX dated 24.06.2013 with updated correction slips as may be issued by RB from time to time.
The items covered under CPWD DSR-2021, CPWD Horticulture 2020 and SER-USSOR-2021 are tentative and approximate and these are considered for evaluation of DV only. However the items covered under CPWD DSR-2021, CPWD Horticulture 2020 and SER-USSOR-2021 may be altered within the scope of work as per instruction of Engineer- in Charge according to site requirement if required. Decision of Engineer in Charge in this regard will be final and binding to all.
IRGCC April-2022 with all correction slips up to date are attached.
IF required, contractor should mobillse to do night working for which they will be required to have their own sufficient lighting arrangement. No extra payment will be admissible on this account.
The Contractor with the help of his Engineer or Diploma holder , as the case be , shall make necessary Drawings, sketches, plotting, peg markings etc. as desired by the Engineer-in-charge. No extra cost shall be claimed on this account.
The quantities specified in the tender schedule are only approximate and liable to vary.
1)Deulti Yard : Improvement of defective layout for removal of PSR -110 KMPH.2) Fuleswar Yard : Improvement of defective layout on UP Main Line for removal of PSR - 110 KMPH , Improvement of Drainage system 3) Andul Yard : Removal of PSR 110 kmph by Yard remodeling, Also improvement of Drainage system
E-KGP-EAST-07-2026~SER
E-KGP-EAST-07-2026
Open
Works - General
15 Months
Paschim Medinipur, West Bengal
₹0
₹8.9 L
5 Mar 2026
27 Jan 2026
19 Feb 2026
133 items across 5 schedules · ₹13,60,01,392.91 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| Under Traffic Block: Dismantling of existing BG turnouts, diamond crossings and derailing switches with all types of rails and sleeper layout, removing rails, switches, crossings, sleepers & fastenings, leveling of ballast to correct profile & stacking all the released materials, sleepers, fastenings, rails, switches & crossings including segregating & stacking at specified locations in a neat and countable manner, within the lead of 250m & all lift, clear of infringements, crossing of track, if any complete, as directed. Note: 1. This item shall be operated only when existing turnout is replaced either with new turnout in case of TTR or with plain track when existing turnout is no more required at that location. 2. Rail cutting will be paid extra under relevant item. 3. Laying of new turnout or plain track on prepared ballast bed, as required, shall be paid separately under relevant item. | — | — | — | — | |
| 1 | 1 in 12 Turnout (Under Traffic Block) | Set | 15.00 | 35,521.8 | 5,32,827 |
| Assembling complete BG Turnout on staging, clear of infringements, to correct gauge and alignment as per standard drawings with all types of rail sections over PSC sleepers at specified locations, duly leading rails, special sleepers, switches, crossings with a maximum lead of 500m, all lift & crossing of track as required and testing points with S&T staff for throw of switch etc. at station yard after levelling surface complete including lubrication of all fastenings, complete in all respect. Note: 1.Rail cutting and Drilling shall be paid separately 2. Required P.Way fittings/fastenings shall be supplied at the SSE/P.Way stores. | — | — | — | — | |
| 2 | 1 in 8½ Turnout | Set | 26.00 | 38,935.18 | 10,12,314.68 |
| Laying and linking of turnouts of all types including diamond crossings & Derailing switches with 52Kg / 60Kg rail section on PSC sleepers on prepared ballast bed for New lines or during total closure of section at indicated location as per standard drawing, duly leading sleepers, rails, switches, crossings, fastenings including rail cutting, drilling, fixing of all components, fittings with housing of tongue rails as per requirement of signaling, preparing ballast bed, filling and spreading of ballast as required, linking of turnout with track, attending track parameters including lifting, providing one round of packing to make track fit for 20 kmph speed including lubrication of fittings/fastenings, complete as directed by Engineer in-charge. | — | — | — | — | |
| 3 | 1 in 8½ Turnouts | Set | 21.00 | 43,746.23 | 9,18,670.83 |
| 4 | 1 in 12 Turnouts | Set | 10.00 | 51,034.51 | 5,10,345.1 |
| Lifting for increase in ballast cushion of existing points & crossing layouts up to 75mm or part thereof including approach and exit sleepers including one round of through packing, correcting the disturbed sleeper spacing, tightening of fittings, boxing of ballast and ramping out on either side at slope not steeper than 1 in 1000 or as directed. Note: Item will be paid only when lifting is 50mm or more. | — | — | — | — | |
| 5 | 1 in 8½ Points & Crossing | Set | 32.00 | 13,434.74 | 4,29,911.68 |
| Manual deep screening of Plain track/ turnouts as per procedure prescribed in IRPWM, June 2020 or latest, on PSC sleepers of any density and throwing away screened muck arising out of screening on toe of bank or on cess, if low or on spoil banks above top of cutting (including throwing and leveling, if required beyond minimum 5m from the edge of cutting which are up to 3m deep or alternatively carting it up to 50m for disposing it off beyond cutting or platforms) as per direction of Engineer in-charge, including cutting cess for effective drainage on both sides, one round of kutcha packing with screened ballast and further attending to track parameter to make track fit for 20 kmph speed complete in all respect. Note : Payment shall be made for length along main line only for turnouts. | — | — | — | — | |
| 6 | Depth of 300 mm below bottom of sleeper for Turnouts | TRM | 8750.00 | 931.29 | 81,48,787.5 |
| 7 | Lifting and packing for regrading the existing PSC sleeper track to required height / level in stages not exceeding 75mm or part thereof at a time, providing permissible ramp for the track, insertion of moorum / sand / stone ballast uniformly under the existing track and placing the same to safe approved gradient, gauge, cushion including levelling and one round of through packing to allow train movement at restricted speed of 30 kmph for a specified length with all leads & lifts and fixing, marking, painting rail level pegs at every 30m interval. Note: Lifting of track shall be done in stages as per procedure prescribed in latest edition of IRPWM to get the proposed final level as per approved working profile, as directed by Engineer in-charge. | TRM | 35000.00 | 178.8 | 62,58,000 |
| Unloading of ballast from Railway's Hopper Wagons, quantity distribution as per pre- defined site requirement, clearing infringements/jammed ballast, distributing the unloaded ballast uniformly over the track, profiling and boxing following all prescribed safety norms. | — | — | — | — | |
| 8 | Under Traffic Block Conditions: | cum | 4000.00 | 52.67 | 2,10,680 |
| 9 | Unloading of sand / quarry dust during block from Railway's wagons other than Hopper wagons by opening the doors of boxes and pulling & pushing down sand with rake irons / phowrahs taking out jammed sand and distributing unloaded sand uniformly over the track. | cum | 1750.00 | 112.16 | 1,96,280 |
| 10 | Cess repair/widening work as per RDSO Specifications and guidelines RDSO/2020/GE: IRS-0004 or latest in running line with suitable soil to the designed profile The work shall include uprooting and disposing of all the vegetation, benching at every 30 Cm vertical height, earthwork in benching portion and compaction using suitable slope vibratory Rollers/Compactors etc. to achieve prescribed MDD. Note: 1. Payment of cess repairs shall be based on the quantities worked out from the cross sectional calculations only and worked out from the initial ground levels before doing benching and final levels as done for new embankment. The earth work in benching portion shall not be paid extra as the same has been included in the rate. 2. The earth work shall be started only after Completing of the benching and certified. 3. The benching Work shall be done for a maximum height of 1.50 m at any time based on the progress of earthwork starting from toe of the embankment. | cum | 21000.00 | 303.63 | 63,76,230 |
| 11 | Extra over item 113010 for earth-work for making cess on other side of the track (when no approaches available along track or no road vehicles to work at site) by dumping contractor's own earth, collected along toe of bank of any height on to other side of track & side slope of the existing bank by head load, duly crossing of tracks with all contractor's materials, labour, tools, plant including loading of earth in baskets, lifting, leading to the non-cess side of bank including crossing of tracks & dumping etc. and as directed by the Engineer in-charge. | cum | 21000.00 | 30.36 | 6,37,560 |
| Linking of BG track (except at LC, Bridges and SEJs) with any type of rail section and sleeper of specified density, on ballast bed spread and compacted with suitable roller, over prepared formation including leading free rails/welded panels available along the alignment on to formation, leading and spreading all fittings and fastenings, spreading of sleepers at specified spacing, squaring, placing of rails over sleepers and fixing rails to sleepers with all types of fittings and fastenings to correct gauge & alignment, lubrication of fittings and fastenings with contractor's grease as per IRPWM standards with contractors labour, tools, consumables, with all lead, lifts etc. complete and raising, levelling and initial packing of track to make it fit for 30 kmph and meet other prerequisites prescribed in Indian Railway Track Machine Manual for deployment of Tamping Machine. Note: 1.Rail cutting and Hole drilling shall be paid separately. 2.Spreading of ballast and compaction shall be paid separately under relevant item. | — | — | — | — | |
| 12 | For sleeper density of 1660 sleepers per km | TRM | 6225.00 | 279.3 | 17,38,642.5 |
| Shifting / Slewing the existing or newly assembled track of any rail section with any type of sleepers and any density under line block to correct locations & alignment and attending to one round kutcha packing to run safely at 20KMPH speed with all contractors tools and consumables complete and as directed by Engineer in-charge. | — | — | — | — | |
| 13 | Maximum Shifting / Slewing up to 1 metre | TRM | 3000.00 | 207.53 | 6,22,590 |
| 14 | Maximum Shifting / Slewing for more than 1 metre & up to 2 metres | TRM | 2000.00 | 249.07 | 4,98,140 |
| 15 | Construction of Sanded Dead End as per RDSO's Drawing no. RT-347 (with all amendments) with brick-work using country bricks or CC bricks in mud mortar and filling with river coarse sand, surrounding rails and filling around. Note: Cost of brick and sand is not included in the rate. | Each | 26.00 | 11,059.85 | 2,87,556.1 |
| Through packing of track, as per procedure prescribed in latest edition of Indian Railways Permanent Way Manual | — | — | — | — | |
| 16 | For PSC sleeper Track with Sleeper Density of 1540 Sleepers/Km or more | TRM | 29500.00 | 104.43 | 30,80,685 |
| Dismantling of existing switch by removing switches, sleepers, fixtures and stacking all released materials, removing ballast and muck by excavating up to required depth, preparation of formation bed, laying of pre- assembled switch by Railway's T-28 machine, linking of track with all fittings, filling ballast duly screened, aligning, packing, adjusting, opening & housing of switch, testing operation of switch assembly and attending track parameters so as to make track fit for 20 kmph speed including disposing off muck to indicated places after the block working etc. complete. Note: Rate includes making necessary preparation for T-28 machine working/movement such as providing and removing rail closures, preparation of approaches, transportation and laying of wooden sleepers/blocks, etc. | — | — | — | — | |
| 17 | 1 in 8½ Switch | Each | 3.00 | 22,806.24 | 68,418.72 |
| 18 | 1 in 12 Switch | Each | 8.00 | 25,852.67 | 2,06,821.36 |
| Cutting of rails with Rail Cutting Machine (Saw type) in all types of rail sections with contractor's tools & plants, equipment, consumable with all lead & lift etc. complete, as directed by Engineer in-charge. Rail Cutting Machine (Saw type) will be as per RDSO Specification No. TM/SM/4, dated 24.04.1991. Note: This item shall only be used in specific circumstances on specific order of Engineer-in-Charge. | — | — | — | — | |
| 19 | 60 Kg - 90 UTS - Outside Track | Each | 4800.00 | 267.67 | 12,84,816 |
| Drilling holes of 16 mm to 32 mm dia. with Rail Drilling machine including chamfering with appropriate chamfering tools in all types of rail section with contractor's tools & plants, equipment, consumable with all lead & lift etc. complete, as directed by Engineer in-charge. Rail Drilling Machine will be as per RDSO Specification No. TM/SM/3, dated 24.04.1991. | — | — | — | — | |
| 20 | Outside Track | Each | 3200.00 | 53.88 | 1,72,416 |
| Unloading of rails of any section and length up to 13 metre, in neat manner for Railway usage from departmental material train (DMT) or contractor's / Railway's Truck/trailer including lead up to 50 metre, lift up to 5 metre and stacking in prescribed manner. | — | — | — | — | |
| 21 | From wagons during period of traffic block where handling by mechanical means is not possible | MT | 5400.00 | 176.56 | 9,53,424 |
| Loading, leading and unloading of PSC Sleepers of 52Kg / 60Kg by Railway's Rail Dolly/ Dip Lorry to the nominated location under traffic in case road carriage is not possible for different leads and lift up to 5 metres. | — | — | — | — | |
| 22 | For lead up to 500 metres | MT | 7500.00 | 300 | 22,50,000 |
| 23 | For lead beyond 500 metre and up to 1 Km | MT | 8100.00 | 444.11 | 35,97,291 |
| 24 | Extra to Items no. 172032 for lead beyond 1 Km for every subsequent Km or part thereof and up to 10 Km | MT | 8100.00 | 46.05 | 3,73,005 |
| Loading, leading and unloading of all types of P.Way fittings and all other miscellaneous material except Rails, sleepers, switches, crossings, SEJs and Glued Joints by road vehicles for different leads. Note: Lead shall be the shortest motorable road length between the points of loading and unloading. | — | — | — | — | |
| 25 | Lead up to 5 Km | MT | 6200.00 | 168.25 | 10,43,150 |
| 26 | Lead beyond 5 Km and up to 10 km | MT | 6200.00 | 210.86 | 13,07,332 |
| 27 | Lead beyond 10 Km and up to 20 km | MT | 6200.00 | 269.08 | 16,68,296 |
| Transportation of Rails, sleepers, switches, crossings, SEJs and Glued Joints by road vehicles for different leads. Note: 1. Lead shall be the shortest motorable road length between the points of loading and unloading. 2. Loading and unloading shall be paid extra under relevant items. | — | — | — | — | |
| 28 | Lead up to 5 Km | MT | 6200.00 | 53.41 | 3,31,142 |
| 29 | Lead beyond 5 Km and up to 10 km | MT | 6200.00 | 96.02 | 5,95,324 |
| 30 | Lead beyond 10 Km and up to 20 km | MT | 6200.00 | 154.24 | 9,56,288 |
| Unloading of 52kg / 60kg PSC line and special sleepers up to 2.75 metre length in Depot / Station / Mid-section between stations in neat manner for Railway usage from departmental material train (DMT) or contractor's / Railway's Truck/Trailer with crane or any other means including crossing of one track and lead up to 250 metre & lift up to 5 metre with contractor's labour, tools & plants, machinery, consumables etc. Note: In case of any damage to sleeper during loading, penalty @ 50% of the all inclusive cost of sleeper shall be levied. | — | — | — | — | |
| 31 | From DMT - Not involving traffic block or on lines, not opened to traffic | MT | 11250.00 | 118.53 | 13,33,462.5 |
| 32 | From Truck / Trailer | MT | 11250.00 | 87.5 | 9,84,375 |
| Unloading of 52kg / 60kg PSC special sleepers beyond 2.75 metre length in Depot / Station / Mid-section between stations in neat manner for Railway usage from departmental material train (DMT) or contractor's / Railway's Truck/Trailer with crane or any other means including crossing of one track and lead up to 50 metre & lift up to 5 metre with contractor's labour, tools & plants, machinery, consumables etc. Note: In case of any damage to sleeper during loading, penalty @ 50% of the all inclusive cost of sleeper shall be levied. | — | — | — | — | |
| 33 | From DMT - During period of traffic block | MT | 11250.00 | 211.76 | 23,82,300 |
| Spreading of New / SH , normal or wider base PSC sleepers from stack along track on either side for different leads with all lifts by any means. | — | — | — | — | |
| 34 | For a lead up to 500m | Each | 11250.00 | 69.46 | 7,81,425 |
| Collection, segregation and stacking of various scattered P.Way materials at nominated stacking location with serviceable and un-serviceable ones separately within a lead up to 500 metre and lift up to 5 metre including crossing of track(s) wherever necessary as directed by Engineer-in-Charge. | — | — | — | — | |
| 35 | Rails, switches, crossings, SEJ, Glued Joints, Check Rails etc. | MT | 6900.00 | 381.86 | 26,34,834 |
| 36 | All type of PSC sleepers | MT | 6900.00 | 416.98 | 28,77,162 |
| Hiring of machinery for minor miscellaneous works for short duration including operator/driver, fuel, lubricants and consumable. The contractor shall arrange all statutory permits as required by rules and regulations prevailing in the area of work. Payment shall be made for actual working hours at site. | — | — | — | — | |
| 37 | JCB Backhoe Loaders 3DX Plus or similar with minimum 1.10 cum bucket capacity | Hour | 160.00 | 808.46 | 1,29,353.6 |
| 38 | Hydra or similar tyre mounted Pick-n-Carry crane of 12T capacity for misc. works of handling of material | Hour | 160.00 | 940.74 | 1,50,518.4 |
| 39 | Tractor with Trolley for local transportation or other misc. works. | Hour | 160.00 | 230.79 | 36,926.4 |
| Schedule total | ₹5,75,77,301.37 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .