| 1 | L1₹1.4 CrAccepted-AOC | ₹1.4 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹1.4 Cr+₹3.0 L (2.10%)Rejected-Finance 18 CORPORATION ROAD DEVAKOTTAI | SIVAGANGA | TAMIL NADU | 630001 | ₹1.4 Cr+₹3.0 L (2.10%) | L2 | Rejected-Finance Above Estimate Rate |
Tender Value
₹1.5 Cr
EMD Value
₹3.0 L
Closing Date
7 Jun 2023, 3:00 pmClosed
Project Director, DRDA, Sivagangai
DRDA, Sivagangai
Construction of Minor Bridge at CH 2800 of Kandanur - Aravayal Road to Devakottai Municipality Limit Via Perattukottai, Malaiyittanvayal, Thanichaoorani, Kandadevi, Pariyanvayal in Devakottai Block at Sivagangai District
2023_RDTN_125300_1
TN16175
Open Tender
Civil Works - Bridge Construction
Item Rate
540 days
Sivagangai
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹3.0 L
8 Aug 2023
22 May 2023
7 Jun 2023
22 May 2023
7 Jun 2023
22 May 2023
Amount
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202
Removal Of Existing Bed Level Causeway
For PCC
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. (without dewatering) Foundation under Abutments & Piers [Dressing the Bed].
Earthwork excavation in all classes of soil except hardrock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling out water, providing and maintaining necessary coffferdams, sheeting, shoring, bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specifications for FOUNDATION UNDER ABUTMENTS & PIERS.
Vibrated Cement Concrete of grade M 15 using 40mm, 20mm & 10mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for Levelling Course Below Abutments Footing & Retaining Wall.
Vibrated Plain Cement Concrete of grade M 20 using 40mm, 20mm & 10mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for Footing under Abutment, Returns and Piers [Below Sill].
Vibrated Cement Concrete of grade M20 using 40mm, 20mm & 10mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for Substructure of Abutments, Piers & Wings (Above Sill level).
Vibrated Reinforced Cement Concrete of grade M30 using 20mm, 10mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants including all other incidental charges etc; complete as per relevant standard specifications, for Dirt Wall Cum Bed Block Over Abutments and Bed Block Over Piers (Above Sill level).
Providing & Fixing Seepage Pipes of 100mm PVC pipes of required lengths for abutments & wings including cost.
Providing and fixing Kraft Paper for full width of seating of deck slab and including including cost and conveyance to work site Labour for fixing the same in correct position and all other incidental charges etc., compelte.
Vibrated Reinforced Cement Concrete M-30 Grade using 20mm, 10mm ISS size HBG metal including cost and conveyance of all materials to site and cement at site but excluding cost and fabrication of steel, including labour charges for mixing, transporting, laying, curing concrete, working at heights, hire charges for tools and plants, including all other incidental charges, etc., complete for DECK SLAB AND KERBS
Providing Filter Media behind the Abutments and Wings with clean III graded material 53mm to 5.6mm to 600mm thick and well compacted in layers with smaller sized towards the soil and bigger size towards the wall including cost and conveyance to work site including all labours and other incidental charges including hire charges for tools and plants employed etc., for filter media as per MOST's (Roads Wing) specifications for Roads and Bridges " Fourth Revision Cl. 309-3-2-13 and 305 -4-4 etc., complete
Filling behind Abutment and Wings with clean gritty gravel of Ø value not less than 35° including cost and conveyance of gravel to worksite, laying, handling charges and filling in layers, tamping under optimum moisture content to get the maximum density including watering, with all leads for water and all other incidental charges etc., complete as per standard specifications.
Providing and fixing PVC EXPANSION JOINT in between Deck Slabs over Abutment and Pier as shown in the drawing including cost and conveyance of expansion joints including Shalimar pad and joint sealent etc,complete.
Vibrated Cement Concrete of grade M 15 using 40mm, 20mm & 10mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for BASECOURSE BELOW APPROACH SLAB.
Vibrated Reinforced Cement Concrete M30 Grade using 20mm 10mm ISS size HBG metal including cost and conveyance of all materials to site and cement at site but excluding cost and fabrication of steel but including form work and centering soft water labour charges for mixing, transporting, placing in position, vibrating and compacting finishing and curing concrete working at heights, hire chargs for tools and plants, including all other incidental charges etc., complete as per standard specifications for Approach Slab.
Vibrated Cement Concrete M30 using 20 & 10mm ISS size HBG metal including cost and conveyance of all materials to worksite and cement at site including all labour charges for fixing concrete, laying, vibrating, hire charges for tools and plants, compacting, curing with all leads for soft water, including all other incidental charges,formwork,cost of premoulded expansion joints and fixing the same in position etc., complete for Wearing Coat of 75mm uniform thickness Over Deck Slab and Approach Slab.
Vibrated Reinforced Cement Concrete M-35 using 20 & 10mm ISS size HBG metal including cost and conveyance of all materials to site including cement at site but excluding cost and fabrication of steel, including labour charges for mixing, transporting, laying, and curing concrete,working at heights,hire charges for tools and plants,including all other incidental charges,etc, complete for CRASH BARRIER.
Vibrated Cement Concrete M20 grade using 40mm, 20mm & 10mm ISS size HBG metal including cost and conveyance of all materials to site and cement at sitel including labour charges for mixing, transporting, laying, and curing concrete, working at heights for PCC PARAPET OVER WINGS.
Supplying and fixing GI Drainage Spouts 100 mm dia as per GOI drawing SD/205 with grating arrangements at top as shown in the drawing and 100 mm dia drainage spout projecting atleast 300m beyond the bottom of deck slab including cost and conveyance of galvanised iron pipes and flats and fixing them in position etc.,
Supply and fabrication of High Yield Strength Deformed Bar with Grade Designation Fe.500, conforming to IS:1786 2008, steel required for all RCC items of works involved in the schedule cost of steel at site fabrication labour charges for cleaning, bending tying grills, including overlapping to the required length whenever necessary and placing the reinforcement in position as specified in the drawings, including cost of binding wire, provision of spacer bars, cover blocks and all other incidental charges etc., complete, Fe.500 grade.
Approach Road
Construction of Embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5e
Construction of Embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 (Gravel shoulder)
Construction of gravel/soil-aggregate base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three wheel 80-100 kN static roller to achieve the desired density, complete as per Technical Specifications Clause 401 Grading III
Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the material with water at OMC in mechanical mix plant carriage of mixed material by tipper to site, laying in uniform layers with paver in sub base/base course on a well prepared surface and compacting with vibratory roller to achieve the desired density.
Providing and laying Bituminous Macadam with hot mix plant using crushed aggregates of grading as per Table 500.4 premixed with bituminous binder, transported to site upto a lead of 1000 m laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled to achieve the desired compaction as per Technical Specification Clause 504.
Providing and applying Prime Coat with Bitumen Emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502. (i) Low Porosity.
Providing, laying and rolling of Open-Graded Premix Carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of either Type A or Type B or Type C as per Technical Specification Clause 508.
Providing and laying Seal Coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A, Type B and Type C as per Technical Specification Clause 510
Diversion Road
Construction of Embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5
Construction of gravel/soil-aggregate base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three wheel 80-100 kN static roller to achieve the desired density, complete as per Technical Specifications Clause 401 Grading III
Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the material with water at OMC in mechanical mix plant carriage of mixed material by tipper to site, laying in uniform layers with paver in sub base/base course on a well prepared surface and compacting with vibratory roller to achieve the desired density.
Providing and laying Reinforced Cement Concrete Pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry.
Provision for Name Board
Provision for PMGSY Logo Board
Provision for Sign Board
Provision for Reflector - Traffic signs
Provision for Citizen Information Board
Provision for Maintenance Board
Retaining wall
Earthwork excavation in all classes of soil except hardrock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling out water, providing and maintaining necessary coffferdams, sheeting, shoring, bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specifications for FOUNDATION UNDER RETAINING WALL.
Vibrated Cement Concrete of grade M 15 using 40mm, 20mm & 10mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for Levelling Course Below Retaining Wall.
Vibrated Cement Concrete of grade M20 using 40mm, 20mm & 10mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for FOOTINGS OF RETAINING WALLS.
Vibrated Cement Concrete of grade M20 using 40mm, 20mm & 10mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for STEM OF RETAINING WALLS.
Providing & Fixing Seepage Pipes of 100mm PVC pipes of required lengths for abutments & wings including cost
Apron
Earthwork excavation in all classes of soil except hardrock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling out water, providing and maintaining necessary coffferdams, sheeting, shoring, bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specifications for Rigid Apron
Vibrated Cement Concrete of grade M 15 using 40mm, 20mm & 10mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for Levelling Course Below Rigid Apron
Vibrated Cement Concrete of grade M20 using 40mm, 20mm & 10mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for RIGID APRON
Vibrated Cement Concrete of grade M20 using 40mm, 20mm & 10mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for CUT OFF WALL
Towards the charges for routline maintenance of the bridge work executed under PMGSY including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRCSP- 20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
V Meenal And Co
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .