| # | Company | Amount | Status |
|---|---|---|---|
| 1 | ₹3.1 Craccepted-aoc | ₹3.1 Cr | accepted-aoc |
Tender Value
₹3.2 Cr
EMD Value
₹3.2 L
Closing Date
13 Mar 2026, 3:00 pmClosed
Chief Engineer, HMDA
East Wing, 7th Floor, Swarna Jayanthi Commercial Complex, Ameerpet - 500038
Widening of existing Chhath Puja/Bathukamma ghat platforms and Providing Revetment along the shoreline of Hussain Sagar lake from Buddha bhavan to Sanjeevaiah park stretch at PVNR marg, Hyderabad
683394
HMDA/DEV/CE/51/03/2025-26, Dt:23.02.2026
OPEN
Civil Engineering Works
HYDERABAD, TELANGANA
1 document required · 1 mandatory
₹11,196
₹3.2 L
28 Mar 2026
28 Feb 2026
28 Feb 2026
Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to300mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned,up to a lead of 1000 metres including removal and disposal of toporganic soil not exceeding 150 mm in thickness as per MoRT&H specification 201 (5th Revision) including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge By Mechanical Means
Earth work excavation for foundations and depositing on bank for all lifts and with an initial lead of 10m including all operational, incidental, labour charges such as shoring ,sheeting, planking, strutting, Overheads charges, T&P, Contractors profit but excluding seignorage charges, dewatering charges etc complete for finished item of work and as directed by Engineer-in-charge as per SS - 20 B (APSS 308). Ordinary soils-Mechcanical Means-Upto 3 m depth
Dismantling of existing structures of cement concrete by mechanical means, like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material,stacking the serviceable material with all lifts but excluding cost of disposal of unserviceable materials as per Technical Specification Clause 202 MORD / MORTH including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Dismantling of existing structures like brick work including disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202 MORD / MORTH including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Providing High Yield Strength Deformed HYSD Fe 500/500D/550D of different diameters for RCC works , including labour charges for straightening, cutting, bending to required sizes and shapes, placing in position with cover blocks of approved materials and size and tying and lap-splicing with binding wire of 18 SWG, forming grills for reinforcement work as per approved designs and drawings, including cost and conveyance of steel bars, including all wastages such as overlaps, couplings, chairs, spacer bars including cost and conveyance of binding wire, cover blocks and all incidental, operational, labour charges such as cutting, bending, placing in position, tying etc., including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Carting away the surplus excavated earth/dismantled material/unwanted debris etc, from the work site with a lead of 16Km including initial lead including all incidental, labour charges, overheads and contractors profit and also loading& unloding and conveyance etc. but excluding seignorage charges Complete for finished item of work and as directed by Engineer in charge.
Plain Cement concrete 1:3:6 nominal machine mixing with concrete mixture (Cement:Sand: Metal) as per IS 456 using 20mm size graded machine crushed hard granite metal (Course aggregate) from approved Quarry / source including cost and conveyance of all materials like Cement , sand, Metal, Water etc to side and inclusive of all materials all operational incidental , labour charges like machine , mixing placing of concrete compacting, curing, overhead charges and contractor profit etc excluding seigniorage charges etc. complete for foundations flooring footings bed etc.complete for finished item of work and as directed by Engineer in Charge.
Construction of M30 grade cement concrete pavement, over a prepared sub base, with 53 grade cement or any other type as per Clause 1501.2.2, coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 mictron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with sholvels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including admixtures as approved, Vaccum Drying of freshly laid cement concrete floor using 100% air tight suction mat of suitable Size and length, curing, curing compound (where specified) and water finishing to lines and grade as per Technical Specification Clause 1501 MORD, including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Providing and laying 450mm Dia Non Pressure NP-4 class (Heavy duty) R.C.C. pipes spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete, including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Manufacture, Supply and delivery of Unplasticised PVCs Pipes of dia 315 mm 6.0 kgf/sqcm conforming to IS : 4985/2000 (third revision) with bell ends (Socket) as per specification in light Grey/Natural Ivory Grey/ Any other Color (except White) inclusive of transportation to anywhere, labour charges, including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Supply and placing of Reinforced Design Mix Concrete M 25 grade corresponding to IS 456 with minimum cement content of 380 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm and down size graded machine crushed hard Granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials like cement, fine aggregate (50:50) coarse aggregate, water etc., to site, centering using Steel scaffolding pipes, jack Props, wallers, Foot plates, brackets, steel Centering Plates, etc., including all operational, incidental and labour charges such as weigh batching, machine mixing, laying concrete, curing and cost of overheads & contractors profit etc., complete but excluding cost of steel and its fabrication charges, seigniorage charges etc, complete for finished item of work and as directed by Engineer In Charge. Footings
Supply and placing of Reinforced Design Mix Concrete M 25 grade corresponding to IS 456 with minimum cement content of 380 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm and down size graded machine crushed hard Granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials like cement, fine aggregate (50:50) coarse aggregate, water etc., to site, centering using Steel scaffolding pipes, jack Props, wallers, Foot plates, brackets, steel Centering Plates, etc., including all operational, incidental and labour charges such as weigh batching, machine mixing, laying concrete, curing and cost of overheads & contractors profit etc., complete but excluding cost of steel and its fabrication charges, seigniorage charges etc, complete for finished item of work and as directed by Engineer In Charge. Bed block, band, steps
Supply and placing of Reinforced Design Mix Concrete M 25 grade corresponding to IS 456 with minimum cement content of 380 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm and down size graded machine crushed hard Granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials like cement, fine aggregate (50:50) coarse aggregate, water etc., to site, centering using Steel scaffolding pipes, jack Props, wallers, Foot plates, brackets, steel Centering Plates, etc., including all operational, incidental and labour charges such as weigh batching, machine mixing, laying concrete, curing and cost of overheads & contractors profit etc., complete but excluding cost of steel and its fabrication charges, seigniorage charges etc, complete for finished item of work and as directed by Engineer In Charge. RCC wall
Supply and placing of Reinforced Design Mix Concrete M 25 grade corresponding to IS 456 with minimum cement content of 380 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm and down size graded machine crushed hard Granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials like cement, fine aggregate (50:50) coarse aggregate, water etc., to site, centering using Steel scaffolding pipes, jack Props, wallers, Foot plates, brackets, steel Centering Plates, etc., including all operational, incidental and labour charges such as weigh batching, machine mixing, laying concrete, curing and cost of overheads & contractors profit etc., complete but excluding cost of steel and its fabrication charges, seigniorage charges etc, complete for finished item of work and as directed by Engineer In Charge. Pedestal
Supply, fabrication and fixing of Mild Steel Grating as per approved drawings duly hot dip galvanized as per IS:2629-1985, including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Dewatering of seepage water/lake water with 10HP diesel pump from excavated pits including hire charges, fuel charges, crew charges etc., including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Coarsed Rubble Stone Masonary 2nd sort in CM 1:6 using selected size stones including bond stones from approved quarry including cost of all materials at site like cement, sand, stones, water etc to site including seigneorage charges sales and other taxes on all materials all operational incidentals and labour charges including dressing of stones to required sizes, curing etc including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Supply, fabrication and fixing of Mild Steel rectangular/square/circular hollow section 240 MPA of specified size including cost of welding rods, power charges, Labour charges for erecting & fixing, cutting, placing, welding and erecting in position and fixing etc, including cost & conveyance of all materials, wastage, including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Refilling with useful excavated earth (excluding rock) in trenches, sides of foundations and basement etc with initial lead in layers not exceeding 15 cm thick, consolidating each deposited layer by watering and ramming including cost and conveyance of water to work site and including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Supply, fabrication and fixing of Mild Steel, structural steel ie, angles, channels & I-section of specified size including cost of welding rods, power charges, Labour charges for erecting & fixing, cutting, placing, welding and erecting in position and fixing etc, including cost & conveyance of all materials, wastage, including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Supply and fabrication of Mild steel plates of different sizes for supporting the various members including cost of welding rods, power charges, Labour charges for erecting & fixing, cutting, placing, welding and erecting in position and fixing etc, including cost & conveyance of all materials, wastage, including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Brick Masonry in CM 1:6 (Cement :Sand) mix using 2nd class bricks of 23x11x7Cms size having a minimum compressive strentth of 35 Kg per Sqm including cost and conveyance of all materials, like cement, sand, water, bricks, etc to site including all operational, incidental, labour charges curing, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Plastering with CM 2 coats, 12 mm thick, base coat in CM (1:5), 8mm thick and top coat in CM (1:3), 4mm thick etc, including cost and conveyance of all materials like cement, sand, water etc. to site, inclusive of lift charges, labour charges like mixing, placing, curing etc, including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Providing Artistic painting with approved colour and quality to give an even shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered material including cost of all material, conveyance charges, labour charges and incidental such as scaffolding charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Providing semi-pervious / pervious casing embankment using soil from approved borrow area in layers of 25cm before compaction including cost of all materials, machinery, labour,all operations such as excavation, sortingout, transporting, spreading in layer of specified thickness, breaking clods, sectioning, compacting each layer without watering to density control of not less than 95 percent etc., complete with initial lead upto 1 km and all lifts including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Providing and constructing dry rubble rock-toe using rubble and stone chips from approved source including cost of all materials, machinery, labour, hand packing rubble and stone chips, finishing top and sides to required slopes etc., complete with initial lead upto 50 m and all lifts including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge.
Plain Cement concrete 1:2:4 nominal machine mixing with concrete mixture (Cement:Sand: Metal) as per IS 456 using 20mm size graded machine crushed hard granite metal (Course aggregate) from approved Quarry / source including cost and conveyance of all materials like Cement , sand, Metal, Water etc to side and inclusive of all materials all operational incidental , labour charges like machine , mixing placing of concrete compacting, curing, overhead charges, T&P and contractor profit,side form work channel charges etc, excluding seigniorage charges etc. complete for foundations flooring footings bed etc.complete for finished item of work and as directed by Engineer in Charge.
Providing and constructing 225 mm thick dry rubble stone pitching including cost and coveyance of all materials,labour, hand packing, finishing etc, including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Providing 225 mm thick grounting with 1:3:6 prop using 10 mm crushed graded metal for the revetment provided including cost and conveyance of all materials to site and labour charges, including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Supply & application of one coat water based cement primer, acrylic emulsion paint weather proof water-based, modified acrylic with silicon additives exterior grade having VOC (Volatile Organic Compound) content less than 30 grams/ Lit. of approved brand and shade, making 3 coats in all to give an even shade after thourughly brushing the surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of all materials to site, including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges, scaffolding charges etc, complete for finished item of work and as directed by Engineer-in-charge complete for finished item of work.
Painting with 2 coats of ready mixed synthetic Enamel paints in all shades Grade - I having VOC (Volatile Organic Compound ) content less than 50grams/Lit. over primer coat of first quality of approved make for new iron work including cost and coneyance of all materials like paint brushes etc. to site including all labour charges for preprationof surface painting etc including all operational, incidental, labour charges, Overheads charges, T&P, Contractors profit but excluding seignorage charges etc, complete for finished item of work and as directed by Engineer-in-charge
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
BOQ platforms.xlsx
TENDER_DOCUMENT • 0.02 MB
Tender document B Ghat platforms.docx
TENDER_DOCUMENT • 0.20 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .