Loading…
Loading…
Tender Value
₹1.1 Cr
EMD Value
₹2.2 L
Closing Date
24 Apr 2026, 11:00 amClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
GENERAL
14 conditions · 3 needing a document upload
The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure- VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet. Other terms and conditions shall follow clause-10 of GCC, April 2022 and Advance Correction Slip No.1 of GCC, April 2022 Note: No Technical & Financial credential are required for tenders having advertised value up to Rs. 50 Lakh
Definition Of Similar Work : - Execution of any HT or LT Electrical work.
27 conditions · 5 needing a document upload
Documents to be uploaded only in the website by the Tenderer Following Annexures duly filled and signed are to be uploaded online only prior to Closing of Tender. Original copy of all the documents to be submitted to office within 7 days whenever demanded by the Railway. Otherwise, Railway reserves rights to Reject/Accept such tender/offer without any reference to the tenderer/tenderers. Annexures are available at Upload/View Document menu in Home Page of IREPS portal for works tender.
The details of the works completed by the tenderer during the last three years to be filled in Annexure-I(a) & Details of contractual payment received by the Tenderer during the last 3 (three) financial years including the current financial year to be filled & submitted in Annexure-I(b).
The details of Plants and Machinery with the tenderer to be filled in Annexure- II.
Details of Personnel and Organization of the Tenderer to be filled in Annexure-III.
Details of Works presently on hand of the Tenderer to be filled in Annexure- IV.
The details regarding Association of Railway Officer s with the tenderer to be filled in Annexure- V.
List of the Arbitration cases of the Tenderer during last Five years to be filled in Annexure-VI.
List of the Court cases of the Tenderer during last Five years to be filled in Annexure- VII.
NEFT MANDATE FORM. All Payments to the agency including the refund of the Earnest Money of the unsuccessful bidder preferably will be remitted through NEFT. The Tenderer is required to submit Bank details and A/C No. etc. in Annexure- VIII.
Documents to be uploaded in the website by the Tenderer : Online payments have been made and no documents are to be deposited.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Tenderer shall upload scanned copy of valid PAN and GSTIN in PDF format.
Demand for the Financial Criteria, Association of Railway Officers, List of Arbitration cases, Court cases and Mandate for NEFT are to be uploaded with a scanned copy duly filled in and signed as per annexure no. IV, V, VI, VII and VIII respectively. These Annexures are available in View Document menu at Home page and is downloadable. The details of the uploaded documents should be produced whenever demanded for verification on written request at any point of time of the tender and contract within 7 days.Otherwise, Railway reserves rights to Reject/Accept such tender/offer without any reference to the tenderer/tenderer's.
Annexure:- IV, V , VI, VII and VIII.
Asansol Division - Provision of Standby cable from AT to CLS panel at different station over the ASN division.
EL-07-26
EL-07-26
Open
Works - General
12 Months
Paschim Bardhaman, West Bengal
₹0
₹2.2 L
24 Apr 2026
1 Apr 2026
10 Apr 2026
75 items across 1 schedule
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| — | — | — | 1,10,38,567.4 | ||
| — | 20.00 | — | — | ||
| Price of installation,testing & commissioning of CLS panel with Tranaportation, loading and unloading. | — | — | — | 33,024 | |
| — | 25000.00 | — | — | ||
| Price for Cable trenching laying & filling with bricks & sand. | — | — | — | 44,57,500 | |
| — | 2000.00 | — | — | ||
| Price for Cable laying on wall/Structure by MS/ Clamps nuts & bolts. | — | — | — | 1,15,400 | |
| — | 2100.00 | — | — | ||
| Price for cable laying on groove cutting on floor or wall. | — | — | — | 1,01,850 | |
| — | 1000.00 | — | — | ||
| Price for supply of GI pipe 50mm dia, medium gauge & cable laying through GI pipe for Track/road/drain crossing. | — | — | — | 3,97,000 | |
| — | 200.00 | — | — | ||
| Price for supply of 3m long 50 mm dia. medium gauge GI pipe & cable laying through GI pipe for protection. | — | — | — | 2,49,800 | |
| — | 2000.00 | — | — | ||
| Price for laying of LT cable through the HDPE pipe 50 mm Diameter PE100 as perIS 4984 or Latest for Platform surface cable laying of min 1 feet depth including supply of HDPE pipe. | — | — | — | 5,44,400 | |
| — | 1900.00 | — | — | ||
| Price for construction of driving and reception pits to laying of 75 mm dia HDPE pipes (PE80,PN6,IS:4984- 1995)(with supply of HDPE pipe) by Micro-tunneling method under the road, foothpath, rail track etc. As per required depth to laying and inserting HT/LT XLPE cable through HDPE pipes | — | — | — | 18,17,065 | |
| — | 20.00 | — | — | ||
| Price for supply ,fixing, connection of busbar chamber 4 way of capacity 100A wall mounted including connection of LT cable with proper lugs and cable gland etc. | — | — | — | 2,22,000 | |
| — | 30.00 | — | — | ||
| Price for supply , installation,testing and commissioning of 100A LT outdoor panel location box. | — | — | — | 1,85,056.8 | |
| — | 30.00 | — | — | ||
| Price for supply,installation, testing & commissioning of LT outdoor type 200A location Box. | — | — | — | 3,27,454.5 | |
| — | 28.00 | — | — | ||
| Price for supply and fixing of indoor type JB | — | — | — | 18,295.2 | |
| — | 30.00 | — | — | ||
| Price for supply and fixing of SP MCB DB 4 way along with MCB 6-32A& DP isolator 40A. | — | — | — | 48,699 | |
| — | 30.00 | — | — | ||
| Price for supply & fixing of 3 phase 4 way MCB DB with 100A isolator | — | — | — | 1,61,778 | |
| — | 30.00 | — | — | ||
| Price for supply and installation of on load change over switch 63A, 4 pole, 415V, AC, 50 Hz in stainless steel enclosure. | — | — | — | 1,24,348.5 | |
| — | 30.00 | — | — | ||
| Price for Supply of MCB 63A,FP. | — | — | — | 87,706.5 | |
| — | 30.00 | — | — | ||
| Price for Supply of MCB 32A,DP. | — | — | — | 25,549.8 | |
| — | 60.00 | — | — | ||
| Price for erection, testing, electrical connection of MCB FP 63A in SS enclosure, industrial interlocking socket or MCB DP 32A in SS enclosure. | — | — | — | 11,642.4 | |
| — | 30.00 | — | — | ||
| Price for supply & fixing of outdoor type PVC JB( size350mm x 250 mm x 150 mm) with 4 poles studs and supply and fixing of MCCB 63 A, 25 KA, Double pole inside PVC JB. | — | — | — | 78,000 | |
| — | 100.00 | — | — | ||
| Price for supply of wiring materials & PVC conduit/concealed wiring charges of Light point / Fan point/ Ex. Fan point. | — | — | — | 39,850 | |
| — | 100.00 | — | — | ||
| Price for supply of T8(1x18w)/T8(1x20W) LED batten tube light including built -in- driver. | — | — | — | 24,800 | |
| — | 100.00 | — | — | ||
| Price for erection, testing, electrical connection and commissioning of indoor LED T8 (1x18W) or T8(1x20W) fitting along with lamp. | — | — | — | 8,475 | |
| — | 500.00 | — | — | ||
| Price for supply of wiring materials & PVC conduit / concealed wiring charges of main wiring. | — | — | — | 64,375 | |
| — | 2000.00 | — | — | ||
| Price for supply of wiring materials & PVC conduit / concealed wiring charges of sub- wiring. | — | — | — | 1,86,400 | |
| — | 100.00 | — | — | ||
| Price for supply of wiring material & concealed/PVC conduit wiring charges for 5 Amps plug point with modular switch. | — | — | — | 27,200 | |
| — | 50.00 | — | — | ||
| Price for supply of wiring materials & PVC conduit / concealed wiring charges for 15A plug point with modular switch | — | — | — | 26,060 | |
| — | 50.00 | — | — | ||
| Price for supply & fixing of outdoor type JB.(size350mmx250mmx150mm). | — | — | — | 45,250 | |
| — | 50.00 | — | — | ||
| Price for supply & fixing of indoor type JB of size 350mm x 250mm x 150mm. | — | — | — | 49,500 | |
| — | 15.00 | — | — | ||
| Price for supply of main switch 100A (ICTPN), 415V AC, 50Hz. | — | — | — | 93,990 | |
| — | 21.00 | — | — | ||
| Supply of 4 pole, 6 way, 240V AC, 50 Hz, 63 A Capacity Rotary Switch suitable and retrofittable into SUNTRON Make existing 10 KVA CLS Panel. | — | — | — | 41,951.7 | |
| — | 30.00 | — | — | ||
| Price for supply of main switch 63 amp, 415V, 50Hz. | — | — | — | 1,33,650 | |
| — | 30.00 | — | — | ||
| Price for supply, erection, testing, electrical connection and commissioning of 63 A change over switch. | — | — | — | 1,18,800 | |
| — | 10.00 | — | — | ||
| Price for supply of Main switch with disconnector fuse three pole & neutral 100Amp, 415 V, 50 Hz (with din type fuse) in Sheet steel encloser | — | — | — | 74,260 | |
| — | 25.00 | — | — | ||
| Price for erection, testing & commissioning of ICTPN main switch 100A | — | — | — | 6,206 | |
| — | 60.00 | — | — | ||
| Price for supply of GI pipe 50mm dia. 3m long med. gauge along with earthing arrangement. | — | — | — | 1,04,280 | |
| — | 50.00 | — | — | ||
| Price for provision of maintenance free chemical earthing . | — | — | — | 7,03,750 | |
| — | 50.00 | — | — | ||
| Price for supply of Control Unit/Auto Change Over unit for Auto Change Over penel Aux supply 3* 230V +/-20%, under voltage setting 20%, over voltage setting 20%,change over delay time 3 sec, Power on LED indication, Timer on LED indication. | — | — | — | 2,83,200 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
TechComp-IIIIII1.pdf
ATTACHMENT
ComlCompliance-U-IVVVIVIIVIII1.pdf
ATTACHMENT
CheckList_511_1.pdf
ATTACHMENT
GCC-April2022.pdf
ATTACHMENT
GCC April 2022 Adv Correction S 1
ATTACHMENT
GCC April 2022 Adv Correction S 2
ATTACHMENT
GCC April 2022 Adv Correction S 3
ATTACHMENT
GCC April 2022 Adv Correction S 4
ATTACHMENT
GCC April 2022 Adv Correction S 5
ATTACHMENT
GCC April 2022 Adv Correction S 6
ATTACHMENT
FormatforcertificateANNEXURE-V.pdf
ATTACHMENT
SpecialConditionofcontractonlabourdata.pdf Special Condition of contract on la
ATTACHMENT
FormatofGuaranteeBond.pdf
ATTACHMENT
MasterTenderDocumentNew.pdf
ATTACHMENT
GCC April 2022 Adv Correction S 7
ATTACHMENT
GCC April 2022 Adv Correction S 8
ATTACHMENT
GCC April 2022 Adv Correction S 9
ATTACHMENT
GCC April 2022 Adv Correction S 10
ATTACHMENT
GCC April 2022 Adv Correction S 11
ATTACHMENT
NewGenl.condition.pdf
ATTACHMENT
AnnexureVIB.pdf
ATTACHMENT
PreliminaryCondition.pdf
ATTACHMENT
GeneralSpecification-ANNEXUREM.pdf
ATTACHMENT
Explantorynote_2.pdf
ATTACHMENT
GCCApril-2022AdvanceCorrectionSlipNo.1.pdf
ATTACHMENT
GCCApril-2022AdvanceCorrectionSlipNo.2.pdf
ATTACHMENT
GCCApril-2022AdvanceCorrectionSlipNo.3.pdf
ATTACHMENT
GCCApril-2022AdvanceCorrectionSlipNo.4.pdf
ATTACHMENT
GCCApril-2022AdvanceCorrectionSlipNo.5.pdf
ATTACHMENT
GCCApril-2022AdvanceCorrectionSlipNo.6.pdf
ATTACHMENT
SpecialConditionofcontractonlabourdata.pdf
ATTACHMENT
GCCApril-2022AdvanceCorrectionSlipNo.7.pdf
ATTACHMENT
GCCApril-2022AdvanceCorrectionSlipNo.8.pdf
ATTACHMENT
GCCApril-2022AdvanceCorrectionSlipNo.9.pdf
ATTACHMENT
GCCApril-2022AdvanceCorrectionSlipNo.10.pdf
ATTACHMENT
GCCApril-2022AdvanceCorrectionSlipNo.11.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .