| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹9.1 LAccepted-AOC | L1 | Accepted-AOC ok | |
| 2 | L2₹9.4 L+₹25,822 (2.82%)Rejected-Finance | L2 | Rejected-Finance ok |
| Sl No | Description | Qty | Unit | A RAMALINGAM CONTRACTOR L2 | MOHAMED BILAL A L1 |
|---|---|---|---|---|---|
| 1.00water supply | |||||
| 1.01 | Earthwork excavation and Depositing on bank initial lead of 10 Meters and initial lift of 2 Metres in narrow trenches for laying of pipes for watersupply and sewarage works in Hard stiff clay,stiff black cotton,hard red earth,shales,murram gravel,stoney earth,earth mixed with small size boulders and hard gravelly soil to the full depth as may be directed by departmental officers etc. complete complying with standard specification.For Pipe Laying works (Distribution Main) | 1,134 | M3 | 310 ₹3,51,540 | 307 ₹3,48,138 Lowest |
| 2.00 | Supply and delivery of 110mm Dia of PVC pipes of 4 kg/cm2,Valves and Specials, including cost and conveyance to site and all labour charges etc complete per standard specification. A) 110mm Dia of PVC pipes of 4 kg/cm2 | 2,100 | Rm | 144 ₹3,02,400 | 141 ₹2,96,100 Lowest |
| 3.00 | 100 mm dia GM Gate valve | 7 | Nos | 9,684 ₹67,788 | 9,680 ₹67,760 Lowest |
| 4.00 | Conveying,Lowering,Laying and jointing the 110 mm Dia of PVC pipes 4kg / cm2 in proper gradient and alignment in the pipe line trench including all labour charges etc complete- | 2,100 | Rm | 25 ₹52,500 | 20 ₹42,000 Lowest |
| 5.00 | Refilling the excavated earth into pipe line trench after Completion of Pipe Laying,including all labour charges etc complete as per standard specification. | 1,115 | M3 | 49 ₹54,635 | 44 ₹49,060 Lowest |
| 6.00 | Plain Cement concrete Using 1:4:8 mix using 40mm ISS gauge HBG metal including cost and conveyance of all materials to work site and all labour charges for mixing, laying, Finishing and curing etc., complete as per standard specification. | 8.5 | M3 | 5,865 ₹49,852.5 | 5,860 ₹49,810 Lowest |
| 7.00 | Plain Cement concrete Using 1:2:4 mix using 20mm ISS gauge HBG metal including cost and conveyance of all materials to work site and all labour charges for mixing, laying, Finishing and curing etc., complete as per standard specification. | 8.5 | M3 | 7,290 ₹61,965 Lowest | 7,293 ₹61,990.5 |
Tender Value
Refer Docs
EMD Value
₹11,100
Closing Date
12 Sept 2025, 3:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Executive Officer Ayyampalayam Town Panchayat
Executive Officer Ayyampalayam Town Panchayat
Dindigul District Ayyampalayam Town Panchayat 15th Finance Tied IInd Inst.Extension of Distribution main at 15th Ward Veppamaram Bus stop to Pattiveeranpatti Pogum Pathai (Near APM Engineering Works) and Kuttikaradu OHT to Devarappanpatti Pogum Pa
2025_DTP_601026_1
334/2023/A-5
Open Tender
Civil Works - Water Works
Works
180 days
Ayyampalayam Town Panchayat
class II and above
2 documents required · 2 mandatory
₹0
₹11,100
20 Sept 2025
6 Sept 2025
12 Sept 2025
6 Sept 2025
12 Sept 2025
6 Sept 2025
Amount
water supply
Earthwork excavation and Depositing on bank initial lead of 10 Meters and initial lift of 2 Metres in narrow trenches for laying of pipes for watersupply and sewarage works in Hard stiff clay,stiff black cotton,hard red earth,shales,murram gravel,stoney earth,earth mixed with small size boulders and hard gravelly soil to the full depth as may be directed by departmental officers etc. complete complying with standard specification.For Pipe Laying works (Distribution Main)
Supply and delivery of 110mm Dia of PVC pipes of 4 kg/cm2,Valves and Specials, including cost and conveyance to site and all labour charges etc complete per standard specification. A) 110mm Dia of PVC pipes of 4 kg/cm2
100 mm dia GM Gate valve
Conveying,Lowering,Laying and jointing the 110 mm Dia of PVC pipes 4kg / cm2 in proper gradient and alignment in the pipe line trench including all labour charges etc complete-
Refilling the excavated earth into pipe line trench after Completion of Pipe Laying,including all labour charges etc complete as per standard specification.
Plain Cement concrete Using 1:4:8 mix using 40mm ISS gauge HBG metal including cost and conveyance of all materials to work site and all labour charges for mixing, laying, Finishing and curing etc., complete as per standard specification.
Plain Cement concrete Using 1:2:4 mix using 20mm ISS gauge HBG metal including cost and conveyance of all materials to work site and all labour charges for mixing, laying, Finishing and curing etc., complete as per standard specification.
A RAMALINGAM CONTRACTOR (BID ID -1456407)
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_718464.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .