| 1 | L1₹1.4 CrAccepted-AOC | ₹1.4 Cr | L1 | Accepted-AOC WORK ORDER |
| 2 | L2₹1.5 Cr+₹4.2 L (2.97%)Rejected-Finance SOUTH THOTTAM PALAKKANTHU PO DINDIGUL WEST TALUK DINDIGUL 624 019 TAMIL NADU | 624019 | ₹1.5 Cr+₹4.2 L (2.97%) | L2 | Rejected-Finance Rejected |
| Sl No | Description | Qty | Unit | P S STALIN CONTRACTOR L2 | VIHAAN CONSTRUCTIONS L1 |
|---|---|---|---|---|---|
| 1.001)Lining Canal From Silvarpatty Konankulam to Mandhaikulam H/o Silvarpatty Km 0/00 -0/420 ESTIMATE COST : 34.26 Lakhs | |||||
| 2.00 | Clearingthe Scrub jungle including all labour charges for burrying and burning etc., complete. | 457.2 | Cum | 6 ₹2,743.2 Lowest | 6 ₹2,743.2 Lowest |
| 3.00 | Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation. | 148.59 | Cum | 269 ₹39,970.71 | 262.5 ₹39,004.88 Lowest |
| 4.00 | Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. | 49.53 | Cum | 5,492 ₹2,72,018.76 | 5,333 ₹2,64,143.49 Lowest |
| 5.00 | Providing Steel Centering for RCC Slabs, beams or plain surfaces including strutting upto 3.29 m high using MS sheets, 10 guage thick of size 90cm x 60cm, Stiffened with Ms angles of size 25mm x 25mm x 3mm laid over silver oak joists of size 10 cm x 6.5 cm spaced at 90 cm c/c and supported by casurina props of 10 cm to 13cm dia spaced at 75 cm c/c and removing the centering and shuttering after specified period without damaging the concrete laid, complying with standard specification and as directed by the departmental officers.departmental officers | 990.6 | Sqm | 562 ₹5,56,717.2 | 546 ₹5,40,867.6 Lowest |
| 6.00 | RCC 1:1.5:3 (one cement, one and half M.Sand and three hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers. | 137.16 | Cum | 9,337 ₹12,80,662.92 | 9,066 ₹12,43,492.56 Lowest |
| 7.00 | Supplying and Fabricating and placing in position MS steel or ribbed for steel for all reinforced cement concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification. | 8.23 | mt | 94,651 ₹7,78,977.73 | 91,895 ₹7,56,295.85 Lowest |
| 8.00 | Provision for Name board charges | 1 | nos | 5,150 ₹5,150 | 5,000 ₹5,000 Lowest |
| 9.00 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} | 1 | GST Amount | 5,28,523.29 ₹5,28,523.29 | 5,13,278.56 ₹5,13,278.56 Lowest |
| 10.002)Lining Canal From Silvarpatty mandhaikulam to Appanampatty Kulam H/o Silvarpatty Km 0/0 -0/320 ESTIMATE COST : 59.80 Lakhs | |||||
Tender Value
Refer Docs
EMD Value
₹1.4 L
Closing Date
6 Jan 2026, 3:00 pmClosed
The Project Director DRDA Dindigul
The Project Director DRDA Dindigul
Lining canal 3 nos in Reddiyarchatram block of Dindigul District TN05-93
2026_RDTN_638503_1
Roc.No.6746-2025-Tender
Open Tender
Civil Works
Item Wise
180 days
DRDA DINDIGUL
Lining canal 3 nos in Reddiyarchatram block of Dindigul District TN05-93
2 documents required · 2 mandatory
₹0
₹1.4 L
4 Feb 2026
2 Jan 2026
6 Jan 2026
2 Jan 2026
6 Jan 2026
2 Jan 2026
1)Lining Canal From Silvarpatty Konankulam to Mandhaikulam H/o Silvarpatty Km 0/00 -0/420 ESTIMATE COST : 34.26 Lakhs
Clearingthe Scrub jungle including all labour charges for burrying and burning etc., complete.
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Providing Steel Centering for RCC Slabs, beams or plain surfaces including strutting upto 3.29 m high using MS sheets, 10 guage thick of size 90cm x 60cm, Stiffened with Ms angles of size 25mm x 25mm x 3mm laid over silver oak joists of size 10 cm x 6.5 cm spaced at 90 cm c/c and supported by casurina props of 10 cm to 13cm dia spaced at 75 cm c/c and removing the centering and shuttering after specified period without damaging the concrete laid, complying with standard specification and as directed by the departmental officers.departmental officers
RCC 1:1.5:3 (one cement, one and half M.Sand and three hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers.
Supplying and Fabricating and placing in position MS steel or ribbed for steel for all reinforced cement concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.
Provision for Name board charges
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}
2)Lining Canal From Silvarpatty mandhaikulam to Appanampatty Kulam H/o Silvarpatty Km 0/0 -0/320 ESTIMATE COST : 59.80 Lakhs
Clearingthe Scrub jungle including all labour charges for burrying and burning etc., complete.
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Providing Steel Centering for RCC Slabs, beams or plain surfaces including strutting upto 3.29 m high using MS sheets, 10 guage thick of size 90cm x 60cm, Stiffened with Ms angles of size 25mm x 25mm x 3mm laid over silver oak joists of size 10 cm x 6.5 cm spaced at 90 cm c/c and supported by casurina props of 10 cm to 13cm dia spaced at 75 cm c/c and removing the centering and shuttering after specified period without damaging the concrete laid, complying with standard specification and as directed by the departmental officers.departmental officers
RCC 1:1.5:3 (one cement, one and half M.Sand and three hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers.
Supplying and Fabricating and placing in position MS steel or ribbed for steel for all reinforced cement concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.
Provision for Name board charges
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}
3)Lining Canal From Silvarpatty mandhaikulam to Appanampatty Kulam H/o Silvarpatty Km 0/320 -0/645 ESTIMATE COST : 49.38 Lakhs
Clearingthe Scrub jungle including all labour charges for burrying and burning etc., complete.
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Providing Steel Centering for RCC Slabs, beams or plain surfaces including strutting upto 3.29 m high using MS sheets, 10 guage thick of size 90cm x 60cm, Stiffened with Ms angles of size 25mm x 25mm x 3mm laid over silver oak joists of size 10 cm x 6.5 cm spaced at 90 cm c/c and supported by casurina props of 10 cm to 13cm dia spaced at 75 cm c/c and removing the centering and shuttering after specified period without damaging the concrete laid, complying with standard specification and as directed by the departmental officers.departmental officers
RCC 1:1.5:3 (one cement, one and half M.Sand and three hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers.
Supplying and Fabricating and placing in position MS steel or ribbed for steel for all reinforced cement concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.
Provision for Name board charges
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.29 MB
BOQ_764160.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .