| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹558.0 CrAdmitted-Finance | ₹558.0 Cr | L1 | Admitted-Finance |
| 2 | L2₹699.6 CrAdmitted-Finance AFCONS HOUSE 16 SHAH INDUSTRIAL ESTATE VEERA DESAI ROAD AZADNAGAR ANDHERI W MUMBAI MAHARASHTRA INDIA400053 | MUMBAI SUBURBAN | MAHARASHTRA | 400053 | ₹699.6 Cr | L2 | Admitted-Finance |
| 3 | L3₹853.0 CrAdmitted-Finance | ₹853.0 Cr | L3 | Admitted-Finance |
| 4 | Rejected-Technical | - | - | Rejected-Technical Not Full filling PQC |
| Sl No | Description | Qty | Unit | Afcons Infrastructure Limited L2 | RKEC Projects Limited L3 | LandT GeoStructure Private Limited L1 |
|---|---|---|---|---|---|---|
| 1.00BREAKWATER WORKS | ||||||
| 1.10 | Quarry, transport and place core material in position consisting of rocks from 10kg to 300kg to the specified lines and levels for producing the finished breakwater section as shown in drawings all complete as per specifications and Section 6: Bill of quantities | 5,65,500 | Each Cum | 3,800 ₹214.9 Cr | 5,000 ₹282.8 Cr | 3,667 ₹207.4 Cr |
| 1.20 | Quarry, transport and place bedding/filter layer varying in size upto 10kg along the breakwater section in toe to the specified lines and levels as shown in drawings all complete as per specifications and Section 6: Bill of quantities | 20,000 | Each Cum | 5,670 ₹11.3 Cr | 5,000 ₹10 Cr | 3,628 ₹7.3 Cr |
| 1.30 | Quarry, transport and place rock varying in size from 300 to 1000kg along the breakwater section in toe, berm and on slopes to the specified lines and levels as shown in drawings all complete as per specifications and Section 6: Bill of quantities | 35,000 | Each Cum | 5,260 ₹18.4 Cr | 5,000 ₹17.5 Cr | 3,781 ₹13.2 Cr |
| 1.40 | Quarry, transport and place rock varying in size from 2T to 4T along the breakwater section in toe, berm and on slopes to the specified lines and levels as shown in drawings all complete as per specifications and Section 6: Bill of quantities | 1,16,000 | Each Cum | 5,070 ₹58.8 Cr | 6,000 ₹69.6 Cr | 3,716 ₹43.1 Cr |
| 1.50 | Quarry, transport and place rock varying in size from 3T to 6T along the breakwater section in toe, berm and on slopes to the specified lines and levels as shown in drawings all complete as per specifications and Section 6: Bill of quantities | 32,000 | Each Cum | 4,950 ₹15.8 Cr | 7,000 ₹22.4 Cr | 3,844 ₹12.3 Cr |
| 1.60Construction, Transportation and Placing of Accropode II M40 grade for breakwater casted from yard up to placing it at its coordinate and position i.e. including hire charges of cranes, overhead charges, labour amenities lab testing and tidal effect charges including all lead lift charges, royalty charges, loading & unloading charges, placing in position in layers using cranes, floating equipment's, divers tools, as per drawing & Technical specifications and Section 6: Bill of quantities in marine condition etc., complete as per the direction of the Employer. | ||||||
| 1.61 | Accropode II- 6.0 Cu.m | 3,050 | Each No. | 1,11,960 ₹34.1 Cr | 1,50,000 ₹45.8 Cr | 92,756 ₹28.3 Cr |
| 1.62 | Accropode II- 9.0 Cu.m | 3,000 | Each No. | 1,58,830 ₹47.6 Cr | 2,25,000 ₹67.5 Cr | 1,38,445 ₹41.5 Cr |
| 1.63 | Accropode II- 11.0 Cu.m | 1,000 | Each No. | 2,00,820 ₹20.1 Cr | 2,75,000 ₹27.5 Cr | 1,69,632 ₹17.0 Cr |
Tender Value
₹508.5 Cr
EMD Value
₹5.2 Cr
Closing Date
9 Sept 2023, 5:15 pmClosed
Binayak Pradhan,EE,HWDII,PPA
Binayak Pradhan,EE,HWDII,PPA
Construction of South BreakwaterExtension, Groynes and Breakwater Toe Protection Wallat Paradip Port
2023_MoS_761554_1
CE/HW-II-W-01/23/177
Open Tender
Civil Works
1080 days
Paradip
Refer Tender Document and e-TCN
5 documents required · 5 mandatory
₹50,000
Yes
As per Tender Document and e-TCN
₹5.2 Cr
Yes
In the Conference hall
19 Jan 2024
12 Jul 2023
11 Sept 2023
12 Jul 2023
9 Sept 2023
12 Jul 2023
12 Jul 2023 - 22 Jul 2023
28 Jul 2023
Amount
BREAKWATER WORKS
Quarry, transport and place core material in position consisting of rocks from 10kg to 300kg to the specified lines and levels for producing the finished breakwater section as shown in drawings all complete as per specifications and Section 6: Bill of quantities
Quarry, transport and place bedding/filter layer varying in size upto 10kg along the breakwater section in toe to the specified lines and levels as shown in drawings all complete as per specifications and Section 6: Bill of quantities
Quarry, transport and place rock varying in size from 300 to 1000kg along the breakwater section in toe, berm and on slopes to the specified lines and levels as shown in drawings all complete as per specifications and Section 6: Bill of quantities
Quarry, transport and place rock varying in size from 2T to 4T along the breakwater section in toe, berm and on slopes to the specified lines and levels as shown in drawings all complete as per specifications and Section 6: Bill of quantities
Quarry, transport and place rock varying in size from 3T to 6T along the breakwater section in toe, berm and on slopes to the specified lines and levels as shown in drawings all complete as per specifications and Section 6: Bill of quantities
Construction, Transportation and Placing of Accropode II M40 grade for breakwater casted from yard up to placing it at its coordinate and position i.e. including hire charges of cranes, overhead charges, labour amenities lab testing and tidal effect charges including all lead lift charges, royalty charges, loading & unloading charges, placing in position in layers using cranes, floating equipment's, divers tools, as per drawing & Technical specifications and Section 6: Bill of quantities in marine condition etc., complete as per the direction of the Employer.
Accropode II- 6.0 Cu.m
Accropode II- 9.0 Cu.m
Accropode II- 11.0 Cu.m
Wave Wall with Roadway: The Supply & place in position to lines & levels cast in-situ design mix cement concrete of grade M30 including providing formwork shuttering, machine mixing, compacting, curing of concrete, centering, including providing pockets, openings, recesses, chamfering where required and rendering if required to give a smooth and even surface in any shape, providing sealing compounds, compressible filler materials & debonding strips near joints, drain pipes, etc. complete as per specifications, drawings and Section 6: Bill of quantities and as directed with all labour and materials for the wave wall with road way but excluding the cost of steel reinforcement.
Supplying, cutting, bending and fixing in position according to drawings and as directed by the Engineer, “High Yield Strength Deformed” reinforcements of grade Fe 500D including labour, materials, tools transport, equipment, fuel etc. all complete as per specifications and Section 6: Bill of quantities
GROYNE WORKS
Quarry, transport and place core material in position consisting of rocks from 1kg to 50kg to the specified lines and levels for producing the groyne section as shown in drawings all complete as per specifications and Section 6: Bill of quantities
Quarry, transport and place bedding/filter layer varying in size upto 10kg along the groyne section to the specified lines and levels as shown in drawings all complete as per specifications and Section 6: Bill of quantities
Quarry, transport and place rock in primary layer, secondary layer, toe berm and Armour layer varying in size along the groyne section to the specified lines and levels as shown in drawings all complete as per specifications and Section 6: Bill of quantities
50 to 250 kg Secondary Layer & Toe layer
50 to 150 kg Secondary Layer & Toe layer
100 to 350 kg Secondary Layer & Toe Layer
200 to 500 kg Secondary Layer & Toe Layer
0.5 T to 1 T Armor Layer
1 T to 2 T Armor Layer
2 T to 4 T Armor Layer
3 T to 5 T Armor Layer
BREAKWATER TOE PROTECTION WORKS
Setting up the Spud Barge/Jackup barge and connected equipment over location of toe protection wall, including cost of shifting, cost of removal of obstructions, cost of all materials, labour, removal of stone/rock at the pile location, setting up hammer to alignment and correct dimensions, fuel, tools, equipments etc.complete as shown in the drawings, specifications and Section 6: Bill of quantities and as directed by the Engineer.
North Breakwater location - Pipe-Pipe Combi wall
South Breakwater location - Pipe-Pipe Combi wall
Supplying and installation / driving of vertical steel Pipe-Pipe combiwall of grade S355JR conforming to EN10025 having piles of 700mm outer dia with 20mm thick for 15m top length & 16mm thick for balance length as per the drawings. The pile length shall be measured from pile cut off level to the termination level. Item including supplying, cutting, rolling, bending, handling, transportation, associated welding, painting (above MLWS), stiffeners, labour, materials, equipment, accessories, etc., complete as per drawings, specifications and Section 6: Bill of quantities and as directed by Engineer In charge.
Providing and placing of sand filling for tubular piles including ramming, watering etc .complete as per specifications and Section 6: Bill of quantities and as directed by the Engineer In charge. (Inside tubular pile sand filling)
Providing and placing of M20 Concrete fill inside tubular piles for top 300 mm height all complete as per specifications and Section 6: Bill of quantities and as directed by the Engineer In charge.
Afcons Infrastructure Limited
RKEC Projects Limited
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 30.54 MB
BOQ_800639.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid