Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹16.6 LAdmitted-Finance 103 SADAR ROAD JORASHIB MANDIR NORTH BARRACKPORE KOL 700120 | NORTH BARRACKPORE | NORTH 24 PARGANAS | WEST BENGAL | 700120 | ₹16.6 L | L1 | Admitted-Finance |
| 2 | L2₹17.4 LAdmitted-Finance | ₹17.4 L | L2 | Admitted-Finance |
| 3 | L3₹18.3 LAdmitted-Finance | ₹18.3 L | L3 | Admitted-Finance |
Tender Value
₹16.6 L
EMD Value
₹33,147
Closing Date
24 Nov 2025, 9:00 amClosed
DIRECTOR GENERAL WATER SUPPLY
CMO BUILDING, 5, S N BANERJEE ROAD, KOLKATA 700013
CONSTRUCTION OF STRUCTURAL CIVIL WORK TO FACILITATE THE 2ND. PUMP MOTOR INSTALLATION AND OTHER ANCILLARY WORKS AT 3NO. PUMPING STATION AT TALLAH PUMPING STATION.
2025_KMC_938086_1
KMC/WS-CENTRAL/44/2025-2026
Open Tender
CIVIL WORKS
45 days
TALLAH PUMPING STATION STN NO.3
Please refer Tender documents.
6 documents required · 6 mandatory
₹0
₹33,147
3 Feb 2026
4 Nov 2025
26 Nov 2025
4 Nov 2025
24 Nov 2025
4 Nov 2025
Dismantling all types of plain cement concrete works, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m In ground floor including roof (b) above 150 mm. thick
Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. ( 3rd Corrigenda & addenda dated 04.06.2018)
ORDINARY CEMENT CONCRETE ( MIX 1:2:4 ) WITH GRADED STONE CHIPS ( 20 MM NOMINAL SIZE) EXCLUDING SHUTTERING AND REINFORCEMENT, IF ANY, IN GROUND FLOOR AS PER RELEVANT IS CODES (BASED ON PWD SCHEDULE OF RATES, W.E.F. 01.11.2017 WITH CORRIGENDA DT.04.06.2018)
Hire charges for engaging Air Compressor machine with minimum pressure capacity of 5.0 Kg/sq.cm arrangement including all necessary equipments and operating staff, carriage, fuel, Tools and plants all complete for cutting Road / hard crust cutting with pneumatic hammer at desired point in water supply works as per direction of EIC . a) With Pneumatic hammers For minimum engagement of 8 hrs. In a day
SUPPLYING READY MIXED CONCRETE OF M 30 GRADE WITH WELL GRADED STONE CHIPS OF 20 MM NOMINAL SIZE CONTAINING DESIGNED QUANTITY OF CEMENT PER CU.M OF WET CONCRETE PRODUCED IN COMPUTERISED BATCHING PLANT UNDER CONTROLLED CONDITION USING APPROVED SUPER PLASTISIZER, DESIGNING CONCRETE MIX FOLLOWING I.S. 10262 AND I.S. 456, TRANSPORTING THE MIX WITH AGITATION IN TRANSIT MIXER TO WORK SITE DEPOSITING THE MIX ON A PLATFORM ERECTED FOR THE PURPOSE AT REQUIRED LEVELS OF CONCRETING AND THEN PLACING THE MIX IN ITS FINAL LOCATION OF FORM WORK, COMPACTING AND CURING THE SAME COMPLETE AS PER SPECIFICATION & DIRECTION OF THE ENGINEER-IN-CHARGE INCLUDING COMPUTERISED BATCHING PLANT TRANSIT MIXER WITH ALL ACCESSORIES VIBRATORS ETC. INCLUSIVE OF ALL OTHER INCIDENTAL CHARGES IN THIS CONNECTION COMPLETE BUT EXCLUDING COST OF HIRE CHARGE OF PLATFORM AND ITS SUPPORTING STAGING WHICH WOULD BE PAID THROUGH SEPARATE ITEM. [CEMENT TO BE SUPPLIED BY THE MANUFACTURER/ SUPPLIER] IN GROUND FLOOR AND FOUNDATION.(II) WITH APPROVED CONCRETE PUMP [NOTE: 1. LIFTING CHARGE FOR ITEMS OF 12 TO 21 OF SUBHEAD B WITHOUT APPROVED CONCRETE PUMP AS PER ITEM 23 OF SUBHEAD B. 2. LIFTING CHARGE FOR ITEMS OF 12 TO 21 OF SUBHEAD B WITH APPROVED CONCRETE PUMP
BUILDING WORKS ( C ) Brickworks,Concrete Works etc.41?.Labour for straightening of coil bars of any dia including stacking
Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction.(a) For works in foundation and upto roof of ground floor/upto 4 m.(i) Tor steel/Mild Steel.I. SAIL/ TATA/RINL. (10th Corrigenda & addenda dated 22.01.2020)
Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor).(When the height of a particular floor is more than 4 m the equivalent floor height shall be taken as 4 m and extra for works beyond the initial 4 m ht. shall be allowed under 12 (e) for every 4 m or part thereof).(c) Steel shuttering or 9 to 12 mm thick approved quality ply board shuttering in any concrete work
Applying 2 coats of bonding agent with synthetic multi functional rubber emulsion having adhesive and water proofing properties by mixing with water in proportion (1 bonding agent : 4 water : 6 cement) as per Manufacturer's specification [Cement to be supplied by the Department]
M.S. structural works in columns, beams etc. with simple rolled structural members (e.g. joists, angle, channel sections conforming to IS: 226, IS: 808 & SP (6)- 1964 connected to one another with bracket, gussets, cleats as per design, direction of Engineer-incharge complete including cutting to requisite shape and length,fabrication with necessary bolting, metal arc welding conforming to IS: 816- 1969 & IS: 1995 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and erection all complete. The rate includes the cost of rolled steel section, consumables such as electrodes, gas and hire charge of all tools and plants and labour required for the work including all incidental chages such as electricity charges, labour insurance charges etc. Payment to be made on the basis of calculated weight of structural members only in finished work as per IS specified weight. Payment for gusset, bracket, cleat, rivets, bolts and nuts may be make by adding the actual weight of such items with the weight of finished structural members or 7% of weight for finished structural members weighing not less than 22.5 Kg. / m. or 15 % of weight for finished structal members weighing less than 22.5 Kg. / m. may be increased allow for bracket, cleat, rivet, bolts and nuts etc. and no seperate payment being made for these items, as per direction of Engineer In Charge. The rates are considered for a height of erection 8m. / 2nd floor level from the ground. Add 1.5% extra over the rate for each additional floor or 4m. beyond initiial 8m. or part thereof. I) For structural members of specified sections weighing less than 22.5 Kg./m (3rd Corrigenda & addenda dated 04.06.2018)
M.S. structural works in columns, beams etc. with simple rolled structural members (e.g. joists, angle, channel sections conforming to IS: 226, IS: 808 & SP (6)- 1964 connected to one another with bracket, gussets, cleats as per design, direction of Engineer-incharge complete including cutting to requisite shape and length,fabrication with necessary bolting, metal arc welding conforming to IS: 816- 1969 & IS: 1995 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and erection all complete. The rate includes the cost of rolled steel section, consumables such as electrodes, gas and hire charge of all tools and plants and labour required for the work including all incidental chages such as electricity charges, labour insurance charges etc. Payment to be made on the basis of calculated weight of structural members only in finished work as per IS specified weight. Payment for gusset, bracket, cleat, rivets, bolts and nuts may be make by adding the actual weight of such items with the weight of finished structural members or 7% of weight for finished structural members weighing not less than 22.5 Kg. / m. or 15 % of weight for finished structal members weighing less than 22.5 Kg. / m. may be increased allow for bracket, cleat, rivet, bolts and nuts etc. and no seperate payment being made for these items, as per direction of Engineer In Charge. The rates are considered for a height of erection 8m. / 2nd floor level from the ground. Add 1.5% extra over the rate for each additional floor or 4m. beyond initiial 8m. or part thereof. III) For built up sections / srtuctural members of specified sections weighing not less than 22.5 Kg./m (3rd Corrigenda & addenda dated 04.06.2018)
Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc (This item is applicable to new work or old work when the original surface has been exposed by removal of old paint.)
Coating of 'Epoxy' Resin of thickness not less than 160 micron with a lowviscosity, crystallization-resistant epoxy resin base with a reactive diluents combined with high build epoxy amine adducts as per BS 5493 standard and a polyamide or amido polyamine or any other suitable hardener. It shall react with epoxy resin at normal ambient temperature, suitable for solvent-free coatings as per recommended proportion for use on metal,concrete and wood surface to protect from corrosion as well as damagefrom chemical reaction after making the surface free from dust, oil and moisture etc. all complete as per instruction and to the satisfaction of ElC. [This item will be operated on prior permission from the concerned SE/Dy Chief Engineer]
Welding in M.S. structural work with gas or electric: (b) Continuous weld.
PROVIDING AND INSERTING NIPPLES WITH APPROVED FIXING COMPOUND AFTER DRILLING HOLES FOR GROUTING AS PER TECHNICAL SPECIFICATIONS INCLUDING SUBSEQUENT CUTTING/REMOVAL AND SEALING OF THE HOLE AS NECESSARY OF NIPPLES AFTER COMPLETION OF GROUTING WITH CEMENT/EPOXY.
Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge
Labour Rates Per Diem : 3) Mazdoor (Male). Note: (I) The above rates of labour are exclusive of 10% contractors profit and 1% Labour welfare cess which would be admissible to the Contractors, but contractual percentage will not be applicable. (II) The workersemployed on high rise building or any structure over 30 ft in height and also workers engaged in Tunnel
Labour Rates Per Diem : 3) Mazdoor (Male). Note: (I) The above rates of labour are exclusive of 10% contractors profit and 1% Labour welfare cess which would be admissible to the Contractors, but contractual percentage will not be applicable. (II) The workersemployed on high rise building or any structure over 30 ft in height and also workers engaged in Tunnel
Sub Total
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 2.21 MB
BOQ_2213734.xls
BOQ • 0.35 MB
TECHBID.pdf
Tender Documents • 2.93 MB
PRICEBID.pdf
Tender Documents • 0.99 MB
Download all tender documents and submit your bid