| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.3 CrAccepted-Finance DOBHI GAYA BIHAR | ₹3.3 Cr | L1 | Accepted-Finance Lowest quoted amount |
| 2 | L2₹3.5 Cr+₹16.8 L (5.08%)Rejected-Finance D NO 8 112 NH 5 MAIN ROAD THROVAGUNTA ONGOLE MANDAL DIST PRAKASAM ANDHRA PRADESH 523262 | ONGOLE | PRAKASAM | ANDHRA PRADESH | 523262 | ₹3.5 Cr+₹16.8 L (5.08%) | L2 | Rejected-Finance Higher quoted amount |
| 3 | L3₹4.2 Cr+₹88.6 L (26.8%)Rejected-Finance 202 TIWARI CHOWK DEOGHAR COLLEGE ROAD NILKATH VIHAR SAWERA GALI DEOGHAR | DEOGHAR | JHARKHAND | 814112 | ₹4.2 Cr+₹88.6 L (26.8%) | L3 | Rejected-Finance Higher quoted amount |
| 4 | L4₹4.2 Cr+₹90.1 L (27.3%)Rejected-Finance GILANPARA DUMKA | ₹4.2 Cr+₹90.1 L (27.3%) | L4 | Rejected-Finance Higher quoted amount |
| 5 | Rejected-Technical HOUSE NO 144 NIRALA PATH CHURCH ROAD BARIDIH BASTI JAMSHEDPUR | - | - | Rejected-Technical as per SBD Cl 4.7 Sec-I |
| Sl No | Description | Qty | Unit | M/S MITRA ENGINEERING CONSTRUCTIONS L2 | SUJATA UDIT BUILDERS PVT LTD L3 | niraj kumar agarwal L4 | MS MANISHA CONSTRUCTION L1 |
|---|---|---|---|---|---|---|---|
| 1.00 | Clearing and Grubbing Road Land .(Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness.) | 1.14 | Hec. | 50,000 ₹57,000 Lowest | 92,000 ₹1,04,880 | 88,499.5 ₹1,00,889.43 | 72,569.18 ₹82,728.87 |
| 2.00 | Dismantling of flexible pavements and disposal of dismantled materials upto a leadof 1000 metres, stacking serviceable and unserviceable materials separately (i) Granular Course by Mechanical means | 65.25 | Cum | 37 ₹2,414.25 | 40 ₹2,610 | 38.9 ₹2,538.23 | 31.9 ₹2,081.48 Lowest |
| 3.00 | Dismantling of flexible pavements and disposal of dismantled materials upto a leadof 1000 metres, stacking serviceable and unserviceable materials separately (i) Bitumnous Course byMechanical means | 15.4 | Cum | 230 ₹3,542 | 250 ₹3,850 | 234 ₹3,603.6 | 191.88 ₹2,954.95 Lowest |
| 4.00 | Excavation for road work in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and tranporting to the embankment location within all lifts and lead upto 1000 m(A) Ordinary Soil | 2,698.69 | Cum | 62 ₹1,67,318.78 | 64 ₹1,72,716.16 | 62.4 ₹1,68,398.26 | 51.17 ₹1,38,091.97 Lowest |
| 5.00 | Construction of Embankment with approved material obtained from Borrow pits with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of Table 300-2. | 7,120.79 | Cum | 129 ₹9,18,581.91 | 140 ₹9,96,910.6 | 129.9 ₹9,24,990.62 | 106.52 ₹7,58,506.55 Lowest |
| 6.00 | Construction of Embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Table 300-2. | 3,727.89 | Cum | 61 ₹2,27,401.29 | 65 ₹2,42,312.85 | 61.48 ₹2,29,190.68 | 50.41 ₹1,87,922.93 Lowest |
| 7.00 | Construction of sub-grade and earthen shoulders with approved material obtained from Borrow pits with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of Table 300-2. | 4,529.1 | Cum | 130 ₹5,88,783 | 135 ₹6,11,428.5 | 131.3 ₹5,94,670.83 | 107.67 ₹4,87,648.2 Lowest |
| 8.00 | Plant mix method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401.0 (v) for grading V Material | 1,240.32 | Cum | 1,950 ₹24,18,624 Lowest | 2,540 ₹31,50,412.8 | 3,000 ₹37,20,960 | 1,985.78 ₹24,63,002.65 |
| 9.00 | Wet Mix Macadam ( Plant Mix Method)(Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.) | 843.03 | Cum | 2,250 ₹18,96,817.5 Lowest | 3,200 ₹26,97,696 | 4,000 ₹33,72,120 | 2,504.94 ₹21,11,739.57 |
| 10.00 | Prime Coat over WMM/ WBM (Providing and applying primer coat with SS1 grade bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means.) | 3,372.12 | Sqm | 60 ₹2,02,327.2 Lowest | 85 ₹2,86,630.2 | 80.62 ₹2,71,860.31 | 66.11 ₹2,22,930.85 |
Tender Value
₹4.0 Cr
EMD Value
₹4.0 L
Closing Date
31 Mar 2026, 12:00 pmClosed
Executive Engineer, RCD, Road Division, Deoghar
O/O Executive Engineer, RCD, Road Division, Deoghar
Reconstruction Work of Parallel Road of Alignment from Chain No.- 558 to 579 of Punasi main canal (Total Length- 0.570 KM) under Road Division, Deoghar
2026_CECOM_111149_1
RCD/DEOGHAR/302/2025-26 (1st Call)
Open Tender
Civil Works
Item Rate
120 days
Chain No.- 558 to 579 of Punasi main canal
Please refer Tender documents.
3 documents required · 3 mandatory
₹10,000
₹4.0 L
16 Sept 2026
11 Mar 2026
2 Apr 2026
11 Mar 2026
31 Mar 2026
11 Mar 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing and Grubbing Road Land .(Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness.) | 1.14 | Hec. | - | - |
| 2 | Dismantling of flexible pavements and disposal of dismantled materials upto a leadof 1000 metres, stacking serviceable and unserviceable materials separately (i) Granular Course by Mechanical means | 65.25 | Cum | - | - |
| 3 | Dismantling of flexible pavements and disposal of dismantled materials upto a leadof 1000 metres, stacking serviceable and unserviceable materials separately (i) Bitumnous Course byMechanical means | 15.4 | Cum | - | - |
| 4 | Excavation for road work in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and tranporting to the embankment location within all lifts and lead upto 1000 m(A) Ordinary Soil | 2,698.69 | Cum | - | - |
| 5 | Construction of Embankment with approved material obtained from Borrow pits with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of Table 300-2. | 7,120.79 | Cum | - | - |
| 6 | Construction of Embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Table 300-2. | 3,727.89 | Cum | - | - |
| 7 | Construction of sub-grade and earthen shoulders with approved material obtained from Borrow pits with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of Table 300-2. | 4,529.1 | Cum | - | - |
| 8 | Plant mix method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401.0 (v) for grading V Material | 1,240.32 | Cum | - | - |
| 9 | Wet Mix Macadam ( Plant Mix Method)(Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.) | 843.03 | Cum | - | - |
| 10 | Prime Coat over WMM/ WBM (Providing and applying primer coat with SS1 grade bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means.) | 3,372.12 | Sqm | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.24 MB
SBD302.pdf
Tender Documents • 4.93 MB
BOQ_150148.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .