| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹14.9 LAccepted-AOC | L1 | Accepted-AOC Low | |
| 2 | L2₹14.9 L+₹4,186.30 (0.28%)Rejected-Finance | L2 | Rejected-Finance High |
Tender Value
₹15 L
EMD Value
₹15,000
Closing Date
12 May 2022, 3:00 pmClosed
The Block Development Officer, B.Pt
Block Development Office, West Arni
Construction of Side Drainage with Culvert at Krishnasami Nagar in Kolathur panchayat in West Arni Block of Thiruvannamalai District under MPLADS2021-22
2022_RDTN_231064_1
Roc. No. A7/1780/2022 Dt.11.04.2022_08
Open Tender
Civil Works - Others
Lump-sum
180 days
West Arni
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹15,000
Yes
13 May 2022
4 May 2022
12 May 2022
4 May 2022
12 May 2022
4 May 2022
Amount
Construction of Side Drainage with Culvert @ Krishnasami Nagar in Kolathur panchayat in West Arni Block of Thiruvannamalai District under MPLAD’S –2021-22
Earth work excavation and depositing on bank with in initial lead of 10m and lift of 2m in hard gravelly soil as per SS 20 B for foundation
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for foundation
Supplying and errection of centering for sides and soffits with M.S.sheet and country wood props including hire charges for materials and all labour charges etc complete
Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Plastering with Cement Mortar 1:4 (one cement and four sand) 20 mm. thick in all floors including curing etc., complete complying with standard specification and as directed
Construction of Culvert
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B.
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete.
Supplying and erecting centring for sides and suffits including supports and structing upto 3.29m height for plane surface in all cross bracting using MS sheets of size 90 x 60cm and 10kg stiffened with angle of size 25 x 25 x 3mm for boarding laid over silver oak joists os size 10 x 6.5mm at about 90cm C/C and supported by casuring props of 10cm 13cm dia at C/C etc., complete.
Supplying and erecting centring for sides and suffits including supports and structing upto 3.29m height for plane surface in all cross bracting using MS sheets of size 90 x 60cm and 10kg stiffened with angle of size 25 x 25 x 3mm for boarding laid over silver oak joists os size 10 x 6.5mm at about 90cm C/C and supported by casuring props of 10cm 13cm dia at C/C etc., complete.
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete.
Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete.
Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length, bending to shape and tying in position and forming grills for all R.C.C works.
Reinforced cement concrete 1:1 1/2:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete.
Construction of Community Soakpit (Vertical Filter)
Earth work excavation for foundation in all classes of soils and sub soil to full depth except in hard rock requiring blasting but inclusive of shoring strutting if required for the sides of foundation. (SDR Soil)
Cement Concrete 1:4:8 mix using 40 mm HBG metal for foundaion including watering wherever necessary and laid in layers of not more than 15cm thick. Compacting etc., complete complying with standard specifications and as directed by the departmental officers etc, complete.
Brick work in cement mortar 1:5 using country bricks of size 83/4"x41/4"x23/4" etc., complete
Plastering with cement mortar 1:5 mix to 12mm thick including cost and conveyance of all materials to site and all labour charges etc complete.
Supplying and filling with Rough Stone to a Height of 0.75m from an approved quarry including all cost and conveyance materials and all labour charges etc., complete with Standared Specification.
Supplying and filling with 40mm metal from an approved quarry including all cost and conveyance materials and all labour charges etc., complete with Standared Specification.
Supplying and filling with 20mm metal from an approved quarry including all cost and conveyance materials and all labour charges etc., complete with Standared Specification.
Supplying and filling with Char coal including all cost and conveyance materials and all labour charges etc., complete with Standared Specification.
Supplying and filling with 20mm Brick Jally from an approved quarry including all cost and conveyance materials and all labour charges etc., complete with Standared Specification.
Supplying and filling with Gravel from an approved quarry including all cost and conveyance materials and all labour charges etc., complete with Standared Specification.
Painting two coats of newly plastered wall surface with ready mixed plastic emulsion paint of first class quality and of approved colour over a priming coat including thorough scrapping materials to site and all labour charges etc complete.
Supplying and Delivery of 150mm Dia 6Ksc PVC Pipe including cost and conveyance to the site and all labour charges for filling etc., complete.
Supplying and Delivery of 1.00m Dia to a thick 0.05m including cost and conveyance to the site and all labour charges for fixing charges etc., complete
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
A. Alexsander
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .