Loading…
Loading…
Tender Value
₹410.7 Cr
EMD Value
₹2 Cr
Closing Date
5 Jun 2026, 3:00 pmClosed
Yes (up to 4 members)
Yes (up to 4 members)
Two Packet System
EPC [ Single Stage ]
No
Not Applicable
Lowest to Highest
180 days
Expenditure
Capital (Works)
GENERAL
13 conditions · 2 needing a document upload
The Bidder shall have a minimum Net Worth (the"Financial Capacity") of 5% of Estimated Project Cost at the close of the preceding Financial Year. (Refer clause No. 2.2.2.2 of RFP).
The Bidder shall have the Technical Capacity and Experience as mentioned in Clause No. 2.2.2.1, 2.2.2.3 to 2.2.2.9 of the RFP.
30 conditions · 15 needing a document upload
ANNEXURE I TO APPENDIX IA-(DETAILS OF BIDDER) The Bidder shall ensure that all the details are updated as on the due date of submission of this Bid.
APPENDIX IA (LETTER COMPRISING THE TECHNICAL BID) Clause 2.1.4, 2.11 and 3.1.6 of RFP.
APPENDIX IB (LETTER COMPRISING THE FINANCIAL BID) (Para 2.1.4, 2.11 and 3.1.6 of RFP)-The Bid shall be furnished in the format exactly as per Appendix-IA & IB i.e. Technical Bid as per Appendix IA and Financial Bid as per Appendix IB and it shall be signed by the Bidder's authorized signatory. The Bidder shall first upload all the project details as mentioned in Para No. 2.11.1 of RFP document.
APPENDIX-II (FORMAT FOR POWER OF ATTORNEY FOR SIGNING OF BID) Clause No. 2.1.5 of RFP.
ANNEXURE II TO APPENDIX IA(TECHNICAL CAPACITY OF THE BIDDER): Refer CLAUSE 2.2.2.1, 2.2.2.4 and 2.2.2.6 of RFP.
APPENDIX III- Format for power of attorney for lead member of Consortium/Joint venture CLAUSE 2.1.6 of RFP.
ANNEXURE III TO APPENDIX IA- (FINANCIAL CAPACITY OF THE BIDDER) (Refer clause 2.2.2.2, 2.2.2.8(i), 2.2.2.7(iii) of RFP) The Bidder must establish the minimum Net Worth specified in Clause 2.2.2.2 and provide details as per format at Annex-III of Appendix-IA.
APPENDIX IV (FORMAT FOR JOINT BIDDING AGREEMENT FOR (CONSORTIUM/ JOINT VENTURE) Clause 2.1.11 of RFP.
ANNEXURE IV TO APPENDIX IA (DETAILS OF ELIGIBLE PROJECTS) Refer Clause 2.2.2.1, 2.2.2.4 and 2.2.2.6 of RFP.
ANNEXURE V TO APPENDIX IA- (STATEMENT OF LEGAL CAPACITY).
APPENDIX-VII (BID SECURITY)/EMD (REFER Para 1.2.4 of RFP)The Bidder shall furnish as part of its Bid, a Bid Security, referred to in Clause 1.2.4 here in above through [e-payment Gateway of Authority OR in form of Bank Guarantee from a Bank as per format at Appendix VII].
ANNEXURE VI TO APPENDIX IA-(Guidelines of the Department of Disinvestment) The Bidder shall ensure that all the details are updated as on the due date of submission of this Bid.
ANNEXURE VII TO APPENDIX IA-(Department of Expenditure, Ministry of Finance, Government of India letterF.No.6/18/2019- PPD dated:23/07/2020 shall be referred which is enclosed as Annexure-VII of Appendix-IA) The Bidder shall ensure that all the details are updated as on the due date of submission of this Bid.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
STUDY OF DRAWINGS AND LOCAL CONDITIONS: The drawings for the works can be seen in the office of the Chief Administrative Officer, Construction, S.C.Railway, Secunderabad - 500071 or in the office of the concerned field Deputy Chief Engineer / Construction / S.C.Railway . It should be noted that these drawings are meant for general guidance only and Railway may suitably modify them during the execution of work according to the circumstances without making the Railways liable for any claims on account of such changes. If there is any variation between the description in the tender and the detailed plans, the Engineer-in-Charge will operate the correct description and his decision is final and binding on the tenderer/ Contractor. The Tenderer/Contractor is required to inspect the sites of works and acquaint himself with the site conditions, availability of approaches for transporting of men and materials, space and other factors relating to the works, availability of labour, electricity and water, etc., before quoting his rates. The extent of lead and lift involved in the execution of works and any difficulties involved in the execution of work should also be examined before formulating the rates for complete items of works described in the schedule. The Tender submitted will be deemed to have been made after such inspection.
CORRIGENDUM NOTICE ON IREPS: [I]Railway may modify the tender document by issuing online corrigendum through "www.ireps.gov.in" 15 days prior to the tender closing date. For the purpose of CORRIGENDUM in the tender, NIT period is splitted as under: (a) ADVERTISEMENT PERIOD: The time during which all information pertaining to tender shall be available but offers cannot be submitted (b) OFFER SUBMISSION PERIOD: 15 days prior to closing of tender, during which tenderers can submit their offer.
Applicable for the tenders with eligibility criteria: The offer of Tenderer(s) who do not enclose Work Experience Certificate & Financial eligibility Certificate with requisite details, and supporting documents along with their Tender to establish their credentials shall be summarily rejected, even though they are working contractors or contractors on approved list.
The offer shall be evaluated only from the certificates/documents submitted along with the tender offer.
Any Certificate /Documents offered / submitted / received after the tender opening shall not be given any credit and shall not be considered.
Railway reserves the right to verify the authenticity of the documents/information furnished.
Tenderer(s) shall note that conditional/alternate offer will not be considered and will summarily be rejected, even though such condition makes them as the lowest tenderer.
South Central Railway (Construction Organization): Engineering, Procurement and Construction (EPC) Contract for "Doubling of Track between Aurangabad Station & Gevrai Station including Electrification and Signalling and Augmentation of existing 1x25 kV TSS/SSP/SP to suit proposed second line works in connection with Aurangabad-Parbhani Doubling Project of South Central Railway in the State of Maharashtra"
EPC-07-CAO-C-SC-2026
EPC-07-CAO-C-SC-2026
Open
Works - General
30 Months
Unknown (Unspecified Location)
₹0
₹2 Cr
5 Jun 2026
24 Mar 2026
22 May 2026
87 items across 50 schedules · ₹61,53,600.75 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | Erection/Labour | MT | 17.00 | 3,465 | 58,905 |
| Schedule total | ₹58,905 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
SOR2025ExplanationNotes.pdf
ATTACHMENT
PublicProcurementPolicy19.07.2024.pdf
ATTACHMENT
FOBREFERENCE_1.pdf
ATTACHMENT
BallastprofileforLWRtrack.pdf
ATTACHMENT
BallastRetainer-4.57m-RCC-STD-153-2020.pdf
ATTACHMENT
BallastRetainer-3.66m-RCC-STD-155-2020.pdf
ATTACHMENT
PFwalldrg70-2022.pdf
ATTACHMENT
PFBoundaryWall.pdf
ATTACHMENT
IRPWM2024CorrectedUpToACS-10.pdf
ATTACHMENT
SCRGSR2020.pdf
ATTACHMENT
3.05m3.66m4.57mPSCSLAB.pdf
ATTACHMENT
6.10MPSCSLAB.pdf
ATTACHMENT
9.15MPSCSLAB.pdf
ATTACHMENT
RDSO-Footpath.pdf
ATTACHMENT
PFCover.pdf
ATTACHMENT
PILEANDWELLFOUNDATIONCODE.pdf
ATTACHMENT
PCEletterforFoundationsinRocks.pdf
ATTACHMENT
TransistionsystemonBridgeapproaches.pdf
ATTACHMENT
provisionoframponFOBsattheendofplatformasdt31.03.2014.pdf
ATTACHMENT
LOPKM112-125.pdf
ATTACHMENT
LOPKM125-143.pdf
ATTACHMENT
LOPKM143-156.pdf
ATTACHMENT
All2x25TSSSPSSPRDSOdrawings.pdf
ATTACHMENT
BafflewallandprotectivescreenRDSOdrgs.pdf
ATTACHMENT
Electricalpolicyletters.pdf
ATTACHMENT
Electricalpolicyletters2.pdf
ATTACHMENT
Electricalpolicyletters3.pdf
ATTACHMENT
ElectricalTRDdrawingslinks.pdf
ATTACHMENT
ETISPCPSICLS0020.pdf
ATTACHMENT
GEworksCircular04-2022_monitoringGEWorks.pdf
ATTACHMENT
ImportantElectricalTRDguidelinesletters.pdf
ATTACHMENT
Master_list_of_drawings_TI2023.pdf
ATTACHMENT
EMPLOYMNTOFRETIREDRAILWAYOFFICERSCERTIFICATEFORMAT.pdf
ATTACHMENT
NEFT_FORM_GCC_2022.pdf
ATTACHMENT
DETAILSOFPERSONNEL,PLANTANDMACHINERYWORKSONHANDFORMATS.pdf
ATTACHMENT
RDSOOHEPSIReportsandemp.sch.pdf
ATTACHMENT
SCADATI_SPC_RCC_SCADA_0134-pages-11.pdf
ATTACHMENT
TICIVMS2020dt22.08.2022galvanization.pdf
ATTACHMENT
CROSSSECTIONOFCENTRALDRAININSTATIONYARDS.pdf
ATTACHMENT
CrossSectionofRetainingWall.pdf
ATTACHMENT
CROSSSECTIONOFTROLLEYREFUGEINCUTTING.pdf
ATTACHMENT
CROSSSECTIONOFTROLLEYREFUGEINFILLING.pdf
ATTACHMENT
StandardHeightGuage3Sheets.pdf
ATTACHMENT
DSR_Horticulture_2020.pdf
ATTACHMENT
HYB-TypeIICAOMSGAD-367-14_1.pdf
ATTACHMENT
PLANELEVATION-TypeIIICAOMSGAD.pdf
ATTACHMENT
ModaldrgforRBGroom_1.pdf
ATTACHMENT
ModaldrgforStn.BldwithRBG.pdf
ATTACHMENT
ModalPROPOSEDMAINSITEOFFICE-250SQM.pdf
ATTACHMENT
Br.No.65RCCBOXRVNLANK-KAJG_V3_APPROVE_P116.pdf
ATTACHMENT
EPCBRNO.92-3X3.05MPSCSLABKAJG-AWBCBEAPPROVED.pdf
ATTACHMENT
MAJBR.No.79AWB-KAJGCBEAPPROVEDGAD.pdf
ATTACHMENT
Br.No.21BRCCBOXRUBRVNLANK-KAJG_V5_APPROVE_P97.pdf
ATTACHMENT
114000KMTO115000KM_1.pdf
ATTACHMENT
115000KMTO120000KM.pdf
ATTACHMENT
120000TO125000000KM.pdf
ATTACHMENT
125000KMTO130000KM.pdf
ATTACHMENT
130000KMTO135000KM.pdf
ATTACHMENT
135000KMTO140000KM.pdf
ATTACHMENT
140000KMTO145000KM_1.pdf
ATTACHMENT
145000KMTO150000KM.pdf
ATTACHMENT
AurangabadESP.pdf
ATTACHMENT
MukundwadiESP.pdf
ATTACHMENT
ChikalthanESP.pdf
ATTACHMENT
KarmadESP.pdf
ATTACHMENT
GevraiESP.pdf
ATTACHMENT
RCCDRAINAK-KNWRC_449-24.pdf
ATTACHMENT
AWBGOIRFPDocument.pdf
ATTACHMENT
VCDetails_3.pdf
ATTACHMENT
EPC_DocAWB_TO_GOI_PKG-01Schedules_Final_1.pdf
ATTACHMENT
AURANGABADSIP_SRDSTE-NED_P122.pdf
ATTACHMENT
MUKUNDWADIAPPROVEDTENTATIVESIP.pdf
ATTACHMENT
CHIKALTHANTENTATIVEAPPROVEDSIP.pdf
ATTACHMENT
GEVRAIAPPAROVEDTENTATIVESIP.pdf
ATTACHMENT
KARMADTENTATIVEAPPROVEDSIP.pdf
ATTACHMENT
ReferenceDrawings-1ST.pdf
ATTACHMENT
ReferenceDrawings-2ST.pdf
ATTACHMENT
ReferenceDrawings-3ST.pdf
ATTACHMENT
ReferenceDrawings-4ST.pdf
ATTACHMENT
BrNo139MMR-AWB-MUE.jpg_1.pdf
CORRIGENDUM
RevisedKIT-2.pdf
CORRIGENDUM
Corrigendum1-ModifiedProvisionsrevisedKIT.pdf
CORRIGENDUM
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].