| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.1 LAccepted-AOC | ₹8.1 L Quoted ₹6.8 L | L1 | Accepted-AOC Quoted as lowest Bidder |
| 2 | L2₹7.8 L+₹1.0 L (14.8%)Rejected-Finance | ₹7.8 L+₹1.0 L (14.8%) | L2 | Rejected-Finance Higher than lowest Bidder |
| 3 | L3₹8.0 L+₹1.1 L (16.6%)Rejected-Finance | ₹8.0 L+₹1.1 L (16.6%) | L3 | Rejected-Finance Higher than lowest Bidder |
Tender Value
₹9.3 L
EMD Value
₹18,692
Closing Date
1 Jun 2026, 5:00 pmClosed
Zonal Chief Engineer, JVVNl, Bharatpur
132 KV GSS, Near Motijheel, Bharatpur
CONSTRUCTION OF 33 11 KV GSS AT DABAK AND ERECTION OF ASSOCIATED 33 KV AND 11 KV LINES ON ARC BASIS under AEN HTM JPD DEEG under Deeg Circle
2026_JVVNL_560257_1
JPD/ZCE(B/Z)/JVVNL/TN-67
Open Tender
Electrical Works
Percentage
Deeg, Dabak
Please refer Tender Documents
3 documents required · 3 mandatory
₹2,950
Accounts Officer, JVVNL, Bharatpur
₹18,692
7 Jul 2026
20 May 2026
2 Jun 2026
20 May 2026
1 Jun 2026
20 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Part - A - For the construction of 33/11 KV Sub-Station with 1 x 5 MVA Power T/F in Dabak | - | - | - | - |
| 2 | Excavation of pit in Hard soil | - | - | - | - |
| 3 | (A) Height of poles/R.S.Joist/M.S. Rail Size of pit | - | - | - | - |
| 4 | 9 Mtr/ 1.2mx0.6mx1.50 m deep | 42 | Pit | 102.29 | ₹4,296.18 |
| 5 | (C)Stay set/Depth of pit | - | - | - | - |
| 6 | 8'x 3/4" -0.75x0.5x1.6 m | 4 | Pit | 79.97 | ₹319.88 |
| 7 | Earth work excavation and foundation of platfrom of transformers and brakers including dressing of sides and ramming of bottoms .Liftup to 1.5 Meter including taking out the excavated soil and depositing and refilling of jhiri, watering and ramming and disposal of surplus excavated soil as directed with in a lead of 50 Meter. | - | - | - | - |
| 8 | Hard soil mixed with boulders | 30 | Cum | 107.88 | ₹3,236.4 |
| 9 | Providing and laying cement concrete including compaction etc, complete using stone aggregate 40 mm nominal size (hand broken ) in foundation plinth excluding the cost of shuttering using 1 cement:5 sand:10 aggregate mix. | 15 | Cum | 2,371.19 | ₹35,567.85 |
| 10 | Plaster on new surface on walls in cement ,sand mortar 1:6 including racking of joint etc. complete fine finsh 25 mm thick. | 48 | Sq.Mtr | 128.32 | ₹6,159.36 |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.16 MB
Specification67.pdf
Tender Documents • 2.32 MB
BOQ_997289.xls
BOQ • 0.41 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .