Tender ID
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹39.1 LAccepted-Finance | L1 | Accepted-Finance ACCEPTED FOR L1 | |
| 2 | L2₹40.4 L+₹1.3 L (3.44%)Rejected-Finance | L2 | Rejected-Finance REJECTED | |
| 3 | Rejected-Technical VILL TRILOK PATRER CHAK P O URELCHANDPUR P S MAGRAHAT KOLKATA 743355 | KOLKATA | MAGRAHAT | WEST BENGAL | 743355 | - | Rejected-Technical REJECTED |
Tender Value
₹39.1 L
EMD Value
₹80,000
Closing Date
19 Feb 2026, 12:00 pmClosed
DG/MKT
Office of the D.G. (MARKET DEPARTMENT) Kolkata Municipal Corporation 5, S. N BANERJEE ROAD Kolkata-700 013 West Bengal
DEVELOPMENT OF NEW COMPLEX OF S. S. HOGG MARKET IN WARD NO-46.
2026_KMC_996976_1
KMC/MKT/HOGG/06/2025-26 (2nd call)
Open Tender
CIVIL WORKS
Percentage
90 days
NEW MARKET
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹80,000
28 Feb 2026
3 Feb 2026
21 Feb 2026
3 Feb 2026
19 Feb 2026
3 Feb 2026
BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC. 1. Dismantling all types of masonry excepting cement concrete plain or reinforced, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m. (a) In ground floor including roof.
BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 2. Dismantling all types of plain cement concrete works, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m In ground floor including roof. (a) upto 150 mm. thick
BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 3. Dismantling R.C. floor, roof, beams etc including cutting rods and removing rubbish as directed within a lead of 75 m. including stacking of steel bars.(a) In ground floor including roof.
BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 2. Dismantling all types of plain cement concrete works, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m In ground floor including roof (b) above 150 mm. thick
BUILDING WORKS ( C ) Brickworks,Concrete Works etc A. BRICK WORKS 16. 125 mm. thick brick work with 1st class bricks in cement mortar (1:4) in ground floor. ( 3rd Corrigenda & addenda dated 04.06.2018)
BUILDING WORKS ( C ) Brickworks,Concrete Works etc A. BRICK WORKS 7. Brick work with 1st class bricks in cement mortar (1:4) (b) In superstructure, ground floor
BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 10. Stripping off worn out plaster and raking out joints of walls, celings etc. upto any height and in any floor including removing rubbish within a lead of 75m as directed.
SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 1.Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface](ii) With 1:4 cement mortar (b) 15 mm thick plaster
SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 1.Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface](ii) With 1:4 cement mortar (a) 20 mm thick plaster
SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 1.Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface](ii) With 1:4 cement mortar (c) 10 mm thick plaster
SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 1.Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface] i) With 1:6 cement mortar (a) 25 mm thick plaster
BUILDING WORKS(D) Flooring..A. ORIGINAL WORKS..(6)Artificial stone in floor, dado, staircase etc with cement concrete (1:2:4) with stone chips, laid in panels as directed with topping made with ordinary or white cement (as necessary) and marble dust in proportion (1:2) including smooth finishing and rounding off corners including raking out joints or roughening of concrete surface and application of cement slurry before flooring works using cement @ 1.75 kg/sq.m all complete including all materials and labour. In ground floor. 3 mm. thick topping (High polishing grinding on this item is not permitted with ordinary cement).Using grey cement.(iii) 35 mm. thick.(Add extra @1.5% for each addl. floor upto 4th floor and @1.75% for each additional floor above 4th floor for item No.5 and 6 of subhead A). (3rd Corrigenda & addenda dated 04.06.2018)
BUILDING WORKS (D) Flooring A. ORIGINAL WORKS 35. Supplying, fitting & fixing 1st quality Ceramic tiles in walls and floors to match with the existing work & 4 nos. of key stones (10mm) fixed with araldite at the back of each tile & finishing the joints with white cement mixed with colouring oxide if required to match the colour of tiles including roughening of concrete surface, if necessary or by synthetic adhesive & grout materials etc. (A) Floor With Sand Cement Mortar (1:4) 20 mm thick & 2 mm thick cement slurry at back side of tiles using cement @ 2.91 Kg/Sq.m & joint filling using white cement slurry @0.20kg/Sq.m. (a) Area of each tile upto 0.09 Sq.m (i) Coloured decorative Note: 2. Add extra for each addl, floor over the rate for item 35 & 36 of subhead A.(i) upto 4 th floor-Rs 5/ Sq.m (i) above 4 th floor-Rs 6.25/ Sq.m (3rd Corrigenda & addenda dated 04.06.2018)
BUILDING WORKS (D) Flooring A. ORIGINAL WORKS 35. Supplying, fitting & fixing 1st quality Ceramic tiles in walls and floors to match with the existing work & 4 nos. of key stones (10mm) fixed with araldite at the back of each tile & finishing the joints with white cement mixed with colouring oxide if required to match the colour of tiles including roughening of concrete surface, if necessary or by synthetic adhesive & grout materials etc. (B) Wall. With Sand Cement Mortar (1:3) 15 mm thick & 2 mm thick cement slurry at back side of tiles using cement @ 2.91 Kg/Sq.m & joint filling using white cement slurry @ 0.20kg/Sq.m. (a) Area of each tile upto 0.09 Sq.m (i) Coloured decorative. Note: 2. Add extra for each addl, floor over the rate for item 35 & 36 of subhead A. (i) upto 4 th floor-Rs 5/ Sq.m (i) above 4 th floor-Rs 6.25/ Sq.m (3rd Corrigenda & addenda dated 04.06.2018)
ORDINARY CEMENT CONCRETE ( MIX 1:1.5:3 ) WITH GRADED STONE CHIPS ( 20 MM NOMINAL SIZE) EXCLUDING SHUTTERING AND REINFORCEMENT, IF ANY, IN GROUND FLOOR AS PER RELEVANT IS CODES
BUILDING WORKS(D) Flooring..A. ORIGINAL WORKS?(20)Supplying, fitting and fixing 18 mm. to 22 mm. thick kota stone slab in wall, dado in 15 mm thick [avg] cement mortar (1:3) including making suitable arrangement to hold the stone properly by brass / copper hooks including pointing in cement mortar (1:2) (1 cement : 2 marble dust) with admixture of pigments matching the stone shade, including grinding and polishing all complete as per direction of Engineer-in-charge including cost of materials, labour, scaffolding, staging, curing complete. [Using cement slurry for bedding @4.4 kg/Sq.m and for jointing @1.8 kg/Sq.m] (3rd Corrigenda & addenda dated 04.06.2018)
BUILDING WORKS (E) ROOFING, SHEET WALLING &WATERPROOF TREATMENT . B. WATERPROOF TREATMENT 4. Supplying & laying 3mm thick pre-fabricated plastomeric water proofing membrane conforming to EN 12311-1 & ASTMD 5147, manufactured with atactic poly propylene (APP) modified premium grade asphalt , specially reinforced with non-woven polyester core with polyester reinforcement @160 gms per sqm & both faces covered with thermo-fusible polyethylene film /MineraL on top face over a coat of primer @ 0.40 lit/sqm of manufacturer's specification on smooth,clean dry surface prepared wherever required.Lap joint shall be provided of 75 mm in longitudinal & 100 mm in transverse direction and fused using LPG/ Propane torch employing extra care ensuring full bondage, complete removal of entrapped air and sealing edges into grooves in appropriate manner as per direction of Engineer -in-charge all complete including materials,labour and applicable taxes. (Payment shall be made on the basis of finished surface area.). Membrane Property: Softening Point > 150 deg C, Cold Flexibility < -6 deg C, Tensile Strength, N/cm : 600 (longitudinal), 450 (transverse), Tearing Strength, N: 300 (longitudinal), 200 (transverse)
BUILDING WORKS ( C ) Brickworks,Concrete Works etc?27?..Cement concrete (1:1.5:3) with graded stone chips 5.6 mm size with hexagonal square mesh wire netting, I.R.C. fabric mesh or X.P. M. fitted and fixed after tying the existing reinforcement on concrete without distributing the same and with proper scarping and cleaning the reinforcement and disturbed concrete with wire brush etc. after applying a coat of cement including the cost of wire netting I.R.C or X. P. M. & cost of all handling and scaffolding complete as per direction of Engineer-in -charge...a) 20 mm thick
BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. A. ORIGINAL WORKS 20. Supplying, fitting and fixing windows and ventilators with or without integrated grills conforming to IS 1038-1975 and manufactured from rolled steel sections conforming to IS 7452-1974 with non-friction projecting type, box type hinges, glazing clips, lugs locking bracket, handle plate etc, including hoisting in position, straightening if required, fixing lugs in cement concrete ( 1:2:4) with stone chips 20 mm down cutting holes and mending good damages to match with existing surface complete in all respect excluding glazing. (Add extra @ 1.2 % for each additional floors upto 4th floor and @ 1.5% for each addl. Floor above 4th floor.) In Ground floor Flash butt welded windows and ventilators (No shop priming will be allowed to facilitate inspection of workmanship) Without integrated grills. (b) Openable steel windows as per IS sizes with side hung shutters and horizotal glazing bars. [The extra rate admissible for the openable portion only] Note:- For windows and ventilators joints welded by arc welding, the above rates at (a) and (b) shall be reduced by 10%.
BUILDING WORKS (E) ROOFING, SHEET WALLING &WATERPROOF TREATMENT . A. ROOFING & SHEETWALLING 14. Supplying, fitting & fixing Zn-Al alloy (55% Al & 45% Zn) coating of 150 grams per sq. metre (followed by colour coated on both side) steel sheet work having minimum yield strength of 550 Mpa of trapizoidal profile of approved make (excluding the supporting frame work) fitted and fixed with 55 mm & 25 mm self tapping screw, EPDM Washer 16 mm dia & 3 mm th. washer etc. complete with 150 mm end lap and one corrugation minimum side lap. (Payment to be made on area of finished work). (i) In Roof:- a) With 0.5 mm thick sheet
PLUMBING WORKS (A)-(III) CPVC PIPE WORKS AND FITTINGS (A)-(III) CPVC PIPE WORKS AND FITTINGS Supplying, fitting and fixing CPVC (Chlorinated Polyvinyl Chloride) pipes of approved make conforming to IS-15778: 2007 . with all necessary accessories,specials viz.socket,bend,tee,union,cross,elbo,nipple,longscrew, reducing socket,reducing tee, short piece etc.fitted with holder bats clamps, including cutting pipes,fitting, fixing etc.complete in all respect including cost of all necessary fittings as required,jointing materials in any position above ground. (Payment will be made on the centre line measurements of total pipe line including all specials. No separate payment will be made for accesories, specials. (a) For Exposed Work (i) CPVC Pipes Class-1, SDR-11 (Dia) 15 mm
PLUMBING WORKS (A)-(II) G.I. PIPE WORKS AND FITTINGS 19(II) Supplying, fitting and fixing PVC pipes for underground work of approved make of Schedule 80 (medium duty) conforming to ASTMD - 1785 and threaded to match with GI Pipes as per IS : 1239 (Part - I). with all necessary accessories, specials viz. socket, bend, tee, union, cross, elbo, nipple, longscrew, reducing socket, reducing tee, short piece etc. fitted including cost of all materials ,jointing materials, cutting pipes, making threads ,cutting trenches upto 1.5 metre below surface in all sorts of soil and refilling the same as directed complete in all respect. (Payment will be made on the centre line measurement of the total pipe line including all specials No separate payment will be made for accessories, specials.) PVC Pipes (Dia) (b)20 mm
PLUMBING WORKS (A)-(III) CPVC PIPE WORKS AND FITTINGS (A)-(III) CPVC PIPE WORKS AND FITTINGS Supplying, fitting and fixing CPVC (Chlorinated Polyvinyl Chloride) pipes of approved make conforming to IS-15778: 2007 . with all necessary accessories,specials viz. socket,bend,tee,union,cross,elbo,nipple,longscrew, reducing socket,reducing tee, short piece etc.fitted with holder bats clamps, including cutting pipes,fitting, fixing etc.complete in all respect including cost of all necessary fittings as required,jointing materials in any position above ground. (Payment will be made on the centre line measurements of total pipe line including all specials. No separate payment will be made for accesories, specials. (a) For Exposed Work (i) CPVC Pipes Class-1, SDR-11 (Dia) 25 mm
PLUMBING WORKS (A)-(II) G.I. PIPE WORKS AND FITTINGS 2. Supplying, fitting and fixing in position G.I. pipes of TATA make for underground works with all necessary accessories,specials viz.socket, bend, tee, union, cross, elbow, nipple, short piece etc.including cost of all materials,jointing materials ,cutting pipes,making threads,cutting trenches upto 1.5 metre below surface in all sorts of soil and refilling the same as directed with two coats of painting on G.I. pipes and specials with bituminous paint complete in all respect. (Payment will be made on the centre line measurement of the total pipe line including all specials No separate payment will be made for accessories, specials.Payment for painting will be made seperately) (vi) 50 mm dia. medium quality
BUILDING WORKS(M) DRAIN, DOWN PIPES, CHIMNEY ETC?.(C). ADDITIONAL RATE?(21)Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete.A) UPVC Pipes: (iii) 160 mm. Dia.
BUILDING WORKS(M) DRAIN, DOWN PIPES, CHIMNEY ETC?.(C). ADDITIONAL RATE?(21)Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete.A) UPVC Pipes:(ii) 110 mm. Dia.
BUILDING WORKS(M) DRAIN, DOWN PIPES, CHIMNEY ETC?.(C). ADDITIONAL RATE?(21)Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete.B) UPVC Fittings: a) Plain Tee.(iii) 160 mm. Dia.
BUILDING WORKS(M) DRAIN, DOWN PIPES, CHIMNEY ETC?.(C). ADDITIONAL RATE?(21)Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete.B) UPVC Fittings:a) Plain Tee(ii) 110 mm. Dia.
BUILDING WORKS(M) DRAIN, DOWN PIPES, CHIMNEY ETC?.(C). ADDITIONAL RATE?(21)Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete.B) UPVC Fittings:b) Plain Y.(ii) 110 mm. Dia.
BUILDING WORKS(M) DRAIN, DOWN PIPES, CHIMNEY ETC?.(C). ADDITIONAL RATE?(21)Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete.B) UPVC Fittings:b) Plain Y.(iii) 160 mm. Dia
BUILDING WORKS(M) DRAIN, DOWN PIPES, CHIMNEY ETC?.(C). ADDITIONAL RATE?(21)Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete.B) UPVC Fittings:c) Bend 87.5 degree. (ii) 110 mm. Dia
BUILDING WORKS(M) DRAIN, DOWN PIPES, CHIMNEY ETC?.(C). ADDITIONAL RATE?(21)Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete.B) UPVC Fittings:c) Bend 87.5 degree. (iii) 160 mm. Dia.
PLUMBING WORKS (A)-(II) G.I. PIPE WORKS AND FITTINGS 7. Supplying, fitting and fixing bib cock or stop cock. (g) Supplying, fitting and fixing alloy iron with brass spindle bib cock/ stop cock of approved brand and make, spray painted and tested to 21 kg per sq. cm. (ii) 20 mm
PLUMBING WORKS (A)-(II) G.I. PIPE WORKS AND FITTINGS 7. Supplying, fitting and fixing bib cock or stop cock. (e) PTMT (Polytetra Bib Cock / Stop Cock ( Prayag or equivalent) 15 mm
BUILDING WORKS ( C ) Brickworks,Concrete Works etc B. CONCRETE WORKS 3. Making one set of scaffolding only for replacing glass panels, painting, uprooting plant and another repairing works of building and S&P works for external works only with 10 cm. dia bamboo as main posts at the rate of 1 metre centre to centre and 7.5 cm. dia bamboo ties @ 0.75 metre apart fitting and fixing with necessary coir, nails etc. as per direction of the Engineer-incharge. (This item should be executed only after prior approval of the Engineer-incharge). Firstly, one number to be paid and then labour rate for shifting up to further nineteenth (19) times @ 10% each time to be considered. If necessary further after twenty times of total use, another one number new and labour rate for shifting to be considered accordingly a) 3.90 metre height
BUILDING WORKS ( C ) Brickworks,Concrete Works etc B. CONCRETE WORKS 3. Making one set of scaffolding only for replacing glass panels, painting, uprooting plant and another repairing works of building and S&P works for external works only with 10 cm. dia bamboo as main posts at the rate of 1 metre centre to centre and 7.5 cm. dia bamboo ties @ 0.75 metre apart fitting and fixing with necessary coir, nails etc. as per direction of the Engineer-incharge. (This item should be executed only after prior approval of the Engineer-incharge). Firstly, one number to be paid and then labour rate for shifting up to further nineteenth (19) times @ 10% each time to be considered. If necessary further after twenty times of total use, another one number new and labour rate for shifting to be considered accordingly b) Extra for additional 3.6 height or part thereof
BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. A. ORIGINAL WORKS 2A. M.S. structural works with hollow sections (square or rectangular shape) conforming to IS: 806-1968 & IS:1161-1998) connected to one another with bracket, gusset, cleat as per design, drawing & direction of Engineer-in-Charge complete including cutting to requisite shape & size, fabrication including metal arc welding conforming to IS: 816-1969 & IS: 9595 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and erection all complete. The rate includes the cost of all M.S. Hollow section, all consumables such as electrodes, gas and hire charges of all tools and plants and labour reqired for execution and all incidental chages (such as electricity, labour insurance) etc. complete. Payment to be made on the basis of calculated weight of structural memebrs of MS Holow Section as specified in relevent IS code in finished work. Payment for gusset, bracket, cleat may be made by adding the actual weight of such items with weight of finished structural members. The rates are considered for a hight of erection 8 m. / 2nd floor level from the ground. Add 1.5 % extra over the rate for each additional floor or 4m. beyond the initial 8 m. or part thereof. i) For roof truss works a) Span up to 12 Mtr
SECTION 1. ------------BUILDING WORKS (K) PAINTING, VERNISHING ETC A. ORIGINAL WORKS 1 (a) Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc (This item is applicable to new work or old work when the original surface has been exposed by removal of old paint.)
BUILDING WORKS (K) PAINTING, VERNISHING ETC?(A) ORIGINAL WORKS.(2)(A) Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary :(b) On steel or other metal surface :With super gloss (hi-gloss) -(iv) Two coats (with any shade except white)
SECTION 1. ------------BUILDING WORKS (J)WHITE WASH, COLOUR WASH, DISTEMPER B. MISCELLANEOUS ITEMS 4 Removing old scales, blisters etc. of interior surface of walls,ceiling by scraping etc. and preparing smooth and even surface with rendering or cement mortar (1:2) (as necessary), to make the surface suitable for receiving distemper. (Payment against this item will be made only when this has been done on the specific direction of the Engineer-in-charge).
SECTION 1. ------------BUILDING WORKS (J)WHITE WASH, COLOUR WASH, DISTEMPER 7 Applying Interior grade Acrylic Primer of approved quality and brand on plastered or cencrete surface old or new surface to receive Distemper/ Acrylic emulsion paint including scraping and preparing the surface throughly, complete as per manufacturer's specification and as per direction of the EIC. (In Ground Floor) (b) Two Coats i) Water based interior grade Acrylic Primer[This item to be done under specific instruction of the Superintending Engineer]
SECTION 1. ------------BUILDING WORKS (J)WHITE WASH, COLOUR WASH, DISTEMPER A. ORIGINAL WORKS 10 Acrylic Distemper to interior wall, ceiling with a coat of solvent based interior grade acrylic primer (as per manufacturer's specification) including cleaning and smoothning of surface. Two Coats
BUILDING WORKS. (T)MISCELLANEOUS WORKS: A. SPECIAL WORKS. III. EVENT MANAGEMENT : 6) Hire and labour charges for 100 mm dia bamboo railing on 150 mm dia Jhau/Eucalyptus or other approved timber posts each 2.0 m in length, tied 2 number post strongly with coir ropes in the fashion of a scissor with a spacing of 1.8 m over pacca road without damaging the surface and tying strongly 3 (three) rows of bamboo railing on each leg and 1 (one) railing connecting all the pivot junctions including cost of loading unloading, stacking & carriage of all materials and labour complete, and maintaining barricading for a period beyond 5 (five) days after the reported & recorded time of completion of the entire work to the satisfaction of Engineer-in-charge. (Note: This work should not be executed without specific permission of Superintending Engineer). (100 mm. dia bamboo railing & 150mm. dia Jhau/Eucalyptus/other approved timber posts @ 1.80m apart). (ii) Railing 3 row on each leg and 1 at pivot point.
Construction of special inspection chamber pit of size 900mm. X 600mm. (inside measurement) without shaft with 250mm. thick cement brick work (1:4) over150mm. thick jhama cement conc. (1:4:8) bed over a layer of brick flat soling including providing 150mm. thick R.C.C. slab with ordinary cement concrete (mix 1:1.5:3) with reinforcement as per standard drawing over the chamber, brick on edge flooring with ordinary cement concrete (mix 1:2:4) in the invert with 20mm. thick cement plaster (1:4) finished fine with 1.5 mm. thick neat cement in the inside walls and invert including supplying, fitting and fixing 450mm. dia. (15 M.T.) heavy duty R.C.P.C. cover and frame (15 M.T. load-bearing capacity) with ordinary cement concrete (mix 1:2:4) and C.I. steps (4 kg. each) including cutting hard crust, excavation, dewatering, back filling and removal of spoils but excluding shoring as per standard drawing .(depth of invert between 1.15m. to 1.80m. below G.L.) i) Average depth of invert 1.15 m. below G.L.
23.Construction of Catch pit 600mmX525mm. (inside measurement) and depth of invert 1000mm. below G.L. with 250mm. thick cement brick work (1:4) over 100mm. thick jhama cement concrete (1:4:8) bed over a layer of brick flat soling including providing 100mm. thick R.C.C. slab with ordinary cement concrete (mix 1:1.5:3) with reinforcement as per standard drawing, brickon- edge flooring with 20 mm. thick cement plaster (1:4) finished fine with 1.5 mm. thick neat cement in the inside walls and invert including supplying and fixing R.C.P.C. gully grid (5 M.T.load bearing capacity) and 150 mm. dia. C.I. Syphone including cutting hard crust, excavation, dewatering, back filling and removal of spoils as per standard drawing
(B) - SANITARY AND DRAINAGE WORKS.(B)-(III) WATER CLOSETS AND URINALS.a) Original Works.(4)Supplying, fitting and fixing Orissa pattern water closet in white glazed vitreous chinaware of approved make in position complete excluding 'P' or 'S' trap (excluding cost of concrete for fixing).(ii) 530 mm X 410 mm
SECTION(A) PLUMBINGWORKS (A)(V) BASIN AND SINKS WITH PARTS (a) Original Works 2 Supplying, fitting and fixing white vitreous china best quality approved make wash basin with C.I. brackets on 75 mm X 75 mm wooden blocks, C.P. waste fittings of 32 mm dia., one approved quality brass C.P. pillar cock of 15 mm dia., C.P. chain with rubber plug of 30 mm dia., approved quality P.V.C. waste pipe with C.P. nut 32 mm dia., 900 mm long approved quality P.V.C. connection pipe with heavy brass C.P. nut including mending good all damages and painting the brackets with two coats of approved paint. (ii) 550 mm X 400 mm size
SECTION (A) - PLUMBING WORKS (A)-(IV) CISTERN, G.I.TANKS WITH PARTS Item No. (a) Original Works Supplying, fitting and fixing 10 litre porcelain low-down cistern of approved make without fittings and brackets.
(B) - SANITARY AND DRAINAGE WORKS.(B)-(III) WATER CLOSETS AND URINALS.a) Original Works.(7)Supplying, fitting and fixing Squating plate with integral flushing in white vitreous chinaware of approved make in cement concrete (6:3:1) with jhama chips complete. (Payment of concrete will be paid seperately). (i) 450 mm X 350 mm
(B) - SANITARY AND DRAINAGE WORKS.(B)-(III) WATER CLOSETS AND URINALS.a) Original Works.(13)Supplying, fitting and fixing 18 mm thick marble partition slab with chawk doongri marbel square cut, both sides polished with two front corners rounded and edges polished.
SECTION(B) - SANITARY AND DRAINAGE WORKS.(B)-(III) WATER CLOSETS AND URINALS.a) Original Works.(2)Supplying, fitting and fixing E.W.C. in white glazed vitreous chinaware of approved make complete in position with necessary bolts, nuts etc.(a) With 'P' trap
(B) - SANITARY AND DRAINAGE WORKS.(B)-(III) WATER CLOSETS AND URINALS.a) Original Works.(6)Supplying, fitting and fixing Flat back urinal (half stall urinal) in white vitreous chinaware of approved make in position with brass screws on 75 mm X 75 mm X 75 mm wooden blocks complete.(i) 635 mm X 395 mm X 420 mm
(B) - SANITARY AND DRAINAGE WORKS.(B)-(III) WATER CLOSETS AND URINALS.a) Original Works.(8)Supplying, fitting and fixing Half round channel with or without outlet as required set in cement concrete (6:3:1) with jhama chips complete. (Payment of concrete will be paid seperately).(ii) 600 mm X 150 mm.(b) White vitreous chinaware
BUILDING WORKS ( C ) BRICKWORKS, CONCRETE WORKS Etc. A. BRICK WORKS 1. Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand.
35mm thick Cement Concrete Pavement (1:2:4) in floor/footpath etc. with graded stone chips 11.2mm down,properly leveled with 3mm thick screen on top by cement slurry [email protected] cement per Sqm. Rounding off corners, chequering as required including taking necessary protective measure complete in Gr.floor/footpath.
BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. A. ORIGINAL WORKS 18. Collapsible gate with 40mm x 40mm x 6mm Tee as top and bottom guide rail, 20mm x 10mm x 2mm vertical channels 100mm apart in fully stretched position 20mm x 5mm M.S. flats as collapsible bracings properly rivetted and washered including 38mm steel rollers including locking arrangements, fitted and fixed in position with lugs set in cement concrete and including cutting necessary holes, chasing etc. in walls, floors etc. and making good damages complete. (Add extra @ 1% for each addl. floor upto 4th floor and @ 1.25% for each addl. floor above 4th floor) In ground floor. (Payment will be made on the area of the gate covered by two guard rails and two extreme channels) (3rd Corrigenda & addenda dated 04.06.2018)
BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. B. REPAIRING 11. Labour for taking out rolling shutter (only shutter portion)dismantling by parts for repair or (replacement of damaged parts only), rehanging and refitting the same in position after necessary repairs (excluding the cost of supply of new parts).
BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. B. REPAIRING 14. Oiling and greasing of rolling shutter and repair to in side lock.
BUILDING WORKS (G) WOOD AND PVC WORKS A. DOOR WINDOW FRAME 3. Supplying, fitting and fixing fibre reinforced polymer (FRP) Composite door frame as per approved section with glass fibre reinforced plastic moulded skins and a special sandwich core, so as to impart monolitaheic composite structure as per approved technology of Department of Science and Technology (DST) to safisfy IS: 4020 door testing performance criteria (i) 66mm x 90mm
BUILDING WORKS (G) WOOD AND PVC WORKS B. DOOR WINDOW SHUTTER 14. Supplying, fitting & fixing fibre reinforced polymer (FRP) Composite door shutters as per approved design with glass fibre reinforced plastic moulded skins and a special sandwich core, so as to impart monolitaheic composite structure as per approved technology of Department of Science and Technology (DST) to satisfy IS:4020 door testing performance criteria. In ground floor (i) 32 mm thick. (For upper floors refer to item H(4) also)
SECTION(B) - SANITARY AND DRAINAGE WORKS.(B)-(II) SOIL PIPE AND FITTINGS.(a) Original Works.(14)Supplying,fitting and fixing cast iron 'P' or 'S' trap conformimg to I.S. 3989/ 2009 and 1729/ 2002 including lead caulked joints and painting two coats to the exposed surface. (Painting to be paid seperately).(A) 'P' Trap.(iii) 100 mm.
BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. A. ORIGINAL WORKS 13. (a) M.S.or W.I. Ornamental grill of approved design joints continuously welded with M.S, W.I. Flats and bars of windows,railing etc. fitted and fixed with necessary screws and lugs in ground floor. (Add extra @ 1% for each addl. floor upto 4th floor and @ 1.25%for each addl. floor above 4th floor) (i) Grill weighing above 10 Kg./sq.mtr and up to 16 Kg./sq. mtr. (MODE OF MEASUREMENT):-The weight of grill per sq.m. will be determined by taking thephysical weight of fabricated grill and dividing the same by covered area of the same. N.B. No shop priming will be allowed to facilitate inspection of workmanship. Weight of grill is to be taken after final grinding and finishing the weld.
BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT 4. (B) Do - by fine sand
SECTION(B) - SANITARY AND DRAINAGE WORKS.(B)-(II) SOIL PIPE AND FITTINGS.(a) Original Works.(16.)Supplying, fitting and fixing with cement jointing (3:1) salt glazed stoneware pipe including excavation of earth upto 1.50 metre depth in all sorts of soil both mixed or unmixed and refilling (but excluding concreting at bottom and sides).(iii) 150 mm
BUILDING WORKS(L) GLAZIER'S WORK?..(A)... ORIGINAL WORKS?(7)Supplying, fitting and fixing in position fibre glass panes of approved quality with resin, nail, clip etc. as per IS:12866-1989. (In all floors for internal wall & upto 6 m height for external wall)(e) 4.0 mm thick (6.72 Kg/Sq.m)
BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. A. ORIGINAL WORKS 22. Supplying, fitting and fixing Stainless Steel railing consist of 38mm dia and 900mm height vertical balustrade at every two alternative steps, 50mm dia top rail, 3 (three) nos 19mm dia horizontal Strainless steel pipe and base/cover plate with Strainless Steel GRADE 304 containing 7.5% nickle (Interior Grade) Brushed/Mat finish, complete as per direction of the Engineer-in-charge.Weight of Strainless Steel railing per metre 6.5 Kg (approx) (3rd Corrigenda & addenda dated 04.06.2018)
BUILDING WORKS (G) WOOD AND PVC WORKS D. ACCESSORIES 4. Supplying, fitting and fixing M.S. clamps for door and window frame made of flat bent bar, end bifurcated with necessary screws etc. by cement concrete(1:2:4) as per direction. (Cost of concrete will be paid separately) (a) 40mm X 6mm, 250mm Length (The concreting will have to be done for equivalent thickness of 2 layers of brick work and for the entire width of the wall. No deduction on brick work will be made).
BUILDING WORKS (G) WOOD AND PVC WORKS D. ACCESSORIES 5. Iron butt hinges of approved quality fitted and fixed with steel screws, with ISI mark (iv) 75mm. X 47mm. X 1.70mm (Add Extra 30% for Oxidised Fittings)
BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 13. Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge
BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. A. ORIGINAL WORKS 10. Ordinary grating bars made of round or square M.S. rods fitted and fixed in holes of window frames etc, complete In ground floor. (Steel materials will not be issued by the Deptt.) (Add extra @1% for each additional floor upto 4th floor. @1.25% for each additional floor above 4th floor). (3rd Corrigenda & addenda dated 04.06.2018)
BUILDING WORKS (D) Flooring B. REPAIR AND REHABILITATION 7. Polishing only of old marble or terrazo work with oxalic acid powder using 33 gms/ sq.m. by manual labour / machine where necessary
SECTION(A) PLUMBING WORKS (A)-(VI) TUBE WELL (a) Original Works 12 Supplying,fitting and fixing check valve (horizontal) G.M. tested to 21 kg per sq. cm.(vi) 50 mm
BUILDING WORKS(R) ALUMINIUM WORKS??(15)Supplying,fitting & fixing of 2-Track / 3-Track Aluminium sliding Window of all Aluminium sections viz. window frame (top,bottom & side frame), shutter (top, bottom, side & interlock member) made of aluminium alloy extrusions conforming to IS 733-1983 & IS 1285-1975, annodised conforming to IS 1868-1983, fitted with all other accessories viz. PVC roller, EPDM gasket, maruti lock, screws etc. including labour charges for fitting & fixing of aluminium 2-track/3-track sliding window with fixing of glass (excluding cost of glass) all complete as per architectural drawings and direction of Engineer-in-charge. 10-12 Micron thickness Annodizing film Natural white. For 2-Track window : Members for Bottom frame @ 0.875 Kg per Mtr. and for Top and Side frame @ 0.778 Kg per Mtr. and for shutter Bottom and Top member @ 0.472 Kg per Mtr., Style side member @ 0.493 Kg per Mtr. and Interlock member @ 0.612 Kg per Mtr. For 3-Track window : Members for Bottom frame @ 1.233 Kg per Mtr.and for Top and Side frame @ 1.067 Kg per Mtr. and for shutter Bottom and Top member @ 0.472 Kg per Mtr., Style side member @ 0.493 Kg per Mtr. and Interlock member @ 0.612 Kg per Mtr. [Note : for estimate purpose construction wing may consider weight of 2-track Aluminium window @ 5.5 Kg per Sq.M.and 3-track Aluminium window @ 6.5 Kg per Sq.M]
BUILDING WORKS(R) ALUMINIUM WORKS??(24)Supplying bubble free float glass of approved make and brand conforming to IS: 2835-1987;(A) clear, toughened glass conforming to IS: 2553-1992 (part-II) (ii) 8mm thick
BUILDING WORKS (G) WOOD AND PVC WORKS C. MISCELLANEOUS WOODWORK 10. Square or hexagonal mesh netting made with 18 B.W.G. galvanised wire, fitted and fixed complete as per design (excluding the supporting framework but including local sal wood battens of size 37.5mmx25mm). In ground floor. (a) 19mm mesh (For upper floors refer to item H(4) also)
BUILDING WORKS (G) WOOD AND PVC WORKS C. MISCELLANEOUS WOODWORK 3. Wood work in upper rails of railing, hand rail of staircase, balcony etc. includig necessary bend, moulding fitted and fixed complete (for purpose of payment section will be measured in the square). (c) Sishu, Gamar, Champ, Badam, Bhola, Morga, Hallak Note: Extra for Lifting Charges:-i) upto 4th floor Rs. 200/- per Cu.m per Floor ii) Above 4th floor Rs. 250/- per Cu.m per Floor
SECTION 1. ------------BUILDING WORKS (J)WHITE WASH, COLOUR WASH, DISTEMPER A. ORIGINAL WORKS 8 Applying Exterior grade Acrylic primer of approved quality and brand on plastered or cencrete surface old or new surface to receive decorative textured (matt finish) or smooth finish acrylic exterior emulsion paint including scraping and preparing the surface throughly, complete as per manufacturer's specification and as per direction of the EIC. In Ground Floor: (b) Two Coats [This item to be done under specific instruction of the Superintending Engineer]N.B.:-Extra for each additional floor in external walls refer item 1 of subhead C
BUILDING WORKS (E) ROOFING, SHEET WALLING &WATERPROOF TREATMENT . A. ROOFING & SHEETWALLING 13. Galvanised plain sheet works (excluding supporting framework) fitted and fixed with 6 mm. dia J or L hook-bolts and nuts, sheet-bolts, limpet and bitumen washers and putty with 150 mm. end lap & 50 mm minimum side lap complete (b) In wall: with 0.63 mm. sheets.
BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. A. ORIGINAL WORKS 8. M.S. works in brackets made from flats, angles, tees etc. to sizes specialy bent, twisted, forged; making holes drilled and fitted to rafter of trusses with necessary bolts, nuts, washer or screws etc. (length of straight not less than 230 mm) (To be used for repair works only) (3rd Corrigenda & addenda dated 04.06.2018)
BUILDING WORKS (K) PAINTING, VERNISHING ETC?(B)MISCELLANEOUS ITEMS.(3)Removing old paint from blistered painted surface of steel or other metal by chipping including scraping and cleaning and exposing the original surface.N.B.:(Payment against item (1, 2, 3, 4) of subhead B will be made only when done at specific direction of the Engineer- in-charge. Cost of taking out shutter etc.for this item and rehanging the same or changing glass panes cracked or broken in the operation will be deemed to be covered by the rate of this item and no seperate payment therefore shall be made.)
Sub Total
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.52 MB
SPEC.pdf
Tender Documents • 1.06 MB
BOQ_2440202.xls
BOQ • 0.46 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .