| 1 | Supply of Complete bucket wheel Stacker cum Reclaimer Machine with complete accessories , all Electrical, C and I items required for Machine as per NIT specifications | Complete bucket wheel Stacker cum Reclaimer Machine with accessories (including Design(i.e. preparation and submission of drawing /documents including As Built drawings and O&M manuals), Engineering, Manufacturing, Inspection and testing at vendors & sub-vendors works, painting, maintenance tools & tackles, spares for erection, start-up and commissioning as required, fill of lubricants & consumables and till COD of the units, forwarding, proper packing, shipment and delivery at site for project and package complete with all accessories for the total scope defined as per BHEL NIT & tender technical specification, amendment & agreements till placement of order. Supply of Mechanical and electrical and C&I accessories as per the scope mentioned in technical enquiry specifications,Common rails, rail accessories, foundation bolts, clamps, fixtures, splice plate, end stops etc. for above machines , including belting for boom conveyor, belt weigher, end stops, storm anchors, air conditioning for operator cabins, all electricals, hydraulic drives ( as applicable ) , with complete accessories , all Electrical and C& I items required for Machine as per NIT specifications. | 2 | Sets | 6138500 | 1140 |
| 2 | Supply of Machine Mounted DS system for bucket wheel Stacker cum Reclaimer Machine | Machine Mounted DS system for bucket wheel Stacker cum Reclaimer Machine | 2 | Sets | 6138500 | 1140 |
| 3 | Supply of Mechanical Mandatory spares as per Annexure-7 of Technical Specifications | Mechanical Mandatory spares for Stacker Reclaimer Machine ( as per Annexure-7)
Note-1- if any item appears in more than one place same shall be considered by the bidder irrespective of duplicity and price shall be considered accordingly.
Note 2- Bidder shall not indicate NOT APPLICABLE against any of the spare (except for those items for which IF APPLICABLE is specified). In case of not applicability, functionally equivalent spare to be mentioned with price in the relevant price schedules | 1 | Lot | 6138500 | 1140 |
| 4 | Supply of complete Stockyard Management System as per NIT specifications | Stockyard Management System shall be provided complying completely with the requirements as per NIT specification and C&I Annexure to sub section A-20, Part-B consisting of-
a) 3D Coal Stockpile Mapping and Visualization
b) Hotspot Detection system and interfacing for automatic Sprinkler Operation
c) Readiness for Unmanned Operation of Stacker & Reclaimer Machine
d) Operating modes for Stacker & Reclaimer Machine in Stockyard Management System
e) Features of Automatic operation
f) CCTV
g) Interfacing with Other Systems and Packages at Site
h) System Hardware
i) Online Healthiness Monitoring of Bearings & Gearboxes of Stacker & Reclaimer Machine | 1 | Lot | 6138500 | 1140 |
| 5 | Supply of Electrical, C and I Mandatory spares as per Annexure-7 of Technical Specifications | Electrical and C& I Mandatory spares for Stacker Machine ( as per Annexure-7)
Note 1- if any item appears in more than one place same shall be considered by the bidder irrespective of duplicity and price shall be considered accordingly.
Note 2- Bidder shall not indicate NOT APPLICABLE against any of the spare (except for those items for which IF APPLICABLE is specified). In case of not applicability, functionally equivalent spare to be mentioned with price in the relevant price schedules | 1 | Lot | 6138500 | 1140 |
| 6 | Total Freight-Transportation charges for supply of all plant and equipment including spares | Total Freight/ Transportation charges for supply of all plant & equipment including spares | 1 | Lot | 6138500 | 1140 |
| 7 | Installation Services of Complete BUCKET WHEEL STACKER CUM RECLAIMER MACHINE including all equipment and sub-systems as per scope defined in NIT specification | Installation Services of Complete BUCKET WHEEL STACKER CUM RECLAIMER MACHINE including all equipment/sub-systems as per scope defined in NIT specification comprising of receipt, unloading, handling & storage at site, lifting/shifting to closed/open storage, in-site transportation, to make approach road wherever required, Round the clock security at open storage yard , closed storage shed & erected material till completion of work, assembly, complete Erection, alignment, carrying out Pre-Commissioning, Commissioning, trial run at site and carrying out Performance Guarantee Tests, Reliability Test Run, Smart Project Management system , Functional/Demonstration tests at site (As applicable for obtaining Provisional Acceptance Certificate (PAC), Final Acceptance Certificate (FAC) and handing over of BUCKET WHEEL STACKER CUM RECLAIMER MACHINE including equipment & sub-systems ,complete with all accessories for the total scope defined as per BHEL NIT & tender technical specification, amendment & agreements till placement of order.
Note- PLC expert commissioning engineer shall be deputed to site for Software commissioning and handing over. This shall include minimum following activities but not limited to
1. 100% IO testing , commissioning & demonstration from HMI with interlocks, alarms, SOE , report generation as per approved document BLD , IO list (For this a BBU line item shall be available with quantity of IOs mentioned in NUMERS)
2. Communication with all third parties like Relays, Encoders, and CHP-DCS/Station Lan
3. Time synchronization of SCR PLC with BHEL Master Clock system | 1 | Lot | 6138500 | 1140 |
| 8 | Construction of temporary open storage yard and closed storage shed as per specfication | Construction of temporary open storage yard and closed storage shed as per specfication for storing the items/ sub-assemblies of BUCKET WHEEL STACKER CUM RECLAIMER MACHINE despacthed to site. | 1 | Lot | 6138500 | 1140 |
| 9 | Touch- Up painting at site after erection | Touch- Up painting at site after erection. | 1 | Lot | 6138500 | 1140 |
| 10 | Safety Training as per Tender Specifications | Safety Training- After the design and installation are developed and supervised by qualified engineers familiar with recognized safety features and requirements, the next priority should be personnel training. Operating and maintenance personnel and their supervisors should be initially and then periodically retrained in safe operating procedures, recognizable hazards, precautions and the maintenance of a safe work place. Accordingly, Contractor to provide the list of proper tools and tackles to operate and maintain the machine in an adequately safe condition. Employees should be made aware of, and forbidden to enter, hazardous areas. The training proposal by contractor must include safety training module for site personnel. | 1 | Lot | 6138500 | 1140 |