| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.4 CrAccepted-Finance MORANROAD CHANDERNAGORE | CHANDERNAGORE | ₹2.4 Cr | L1 | Accepted-Finance LOWEST BID VALUE |
| 2 | L2₹2.4 CrRejected-Finance | ₹2.4 Cr | L2 | Rejected-Finance HIGH BID VALUE |
| 3 | L3₹2.7 CrRejected-Finance | ₹2.7 Cr | L3 | Rejected-Finance HIGH BID VALUE |
| 4 | L4₹3.0 CrRejected-Finance MOHANTAPARA P O DIST JALPAIGURI W B PIN 735101 | JALPAIGURI | JALPAIGURI | WEST BENGAL | 735101 | ₹3.0 Cr | L4 | Rejected-Finance HIGH BID VALUE |
Tender Value
₹2.6 Cr
EMD Value
₹5.1 L
Closing Date
27 Feb 2026, 5:30 pmClosed
Superintending Engineer attached to Chief Engineer
Chief Engineer, North East Irrigation and Waterways Directorate Club Road, Jalpaiguri
Protection work along the right bank of river Balason for a length of 950.00 m at Panthabari under Block Naxalbari, Dist. Darjeeling.
2026_IWD_997228_4
WBIW/SE/CE(NE)/NIT-03(e)/25-26
Open Tender
CIVIL WORKS
Percentage
90 days
Panthabari under Block Naxalbari, Dist. Darjeeling
Please refer Tender documents.
5 documents required · 5 mandatory
₹5.1 L
Yes
24 Jul 2026
5 Feb 2026
2 Mar 2026
5 Feb 2026
27 Feb 2026
5 Feb 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earthwork in excavation in the canals / drainage channels / borrow pits /River bed / slope of bank as noted below as per designed section &throwing the spoils in layers of 25 cm. for making banks as per profile or to deposit the same in any other place within an initial lead of 30 metre and initial lift of 1.5 metre including breaking clods, rough dressing etc.complete as per direction of the Engineer-in-charge.
Gravel / moorum / kankar / compact moorum / very much weather rock / sticky soil mixed with moorum / soil mixed with Shingles. | 17,598 | Cum | 147.78 | ₹26,00,632.44 |
| 2 | Labour charges for collecting loose scattered laterite and stone boulders from slope, bed or apron and stacking the same above ground level within a lead of 100 metre and all lifts as per direction of the Engineer - in-charge. | 453 | Cum | 244.32 | ₹1,10,676.96 |
| 3 | Supply of G.I wire netting of different mesh and made with different SWG G I wire at site as per direction of the Engineer-in-charge. Mesh size 150 mm x 150 mm with 10SWG wire | 20,187 | SqM | 95.34 | ₹19,24,628.58 |
| 4 | Making rectangular / circular sausage cage with 10 SWG galvanized iron wire of 150 mm. x 150 mm. mesh wire netting with proper lapping of minimum 150 mm including sewing the joints with 12 SWG G I wire and supply of all materials and equipments including placing the sausage cage in position, filling the same with boulder or lump aggregates complete as per direction of the Engineer-in-charge but excluding the cost of boulder / lump aggregates and its carriage upto site.(Cost is excluding the cost of end pieces) . 0.90 metre x 0.60 metre nominal section. | 118 | Mtr | 481.49 | ₹56,815.82 |
| 5 | Supplying,fitting,fixing end pieces for rectangular/square/circular sausages at the ends, with 10 SWG / 8 SWG GI wire-net of different mesh sizes tying & sewing the same maintaning a lap langth of 150 mm all around with 12 SWG GI wire complete, including the cost of supply of wire-netting, fitting etc, complete as per direction of the Engineer-in-charge. Mesh size 125 mm x 125 mm with 10 SWG wire | 8,458 | Sqm | 128.71 | ₹10,88,629.18 |
| 6 | Labour charges for constructing sausage crates with 8 Guage/ 10 Guage dia. G.I. wirenetting of different shapes and sizes in embankment, apron, slope etc. including binding with 12 S.W.G., G.I. wire and tied at required interval as per direction of Engineer-in-Charge (rate excludes cost of wirenet and laying of boulders but includes cost of binding wire). | 7,515 | Cum | 220.95 | ₹16,60,439.25 |
| 7 | Making rectangular / circular sausage cage with 10 SWG galvanized iron wire of 150 mm. x 150 mm. mesh wire netting with proper lapping of minimum 150 mm including sewing the joints with 12 SWG G I wire and supply of all materials and equipments including placing the sausage cage in position, filling the same with boulder or lump aggregates complete as per direction of the Engineer-in-charge but excluding the cost of boulder / lump aggregates and its carriage upto site.(Cost is excluding the cost of end pieces). 1.20 Metre x 0.60 metre nominal section . | 7,521 | Mtr | 595.9 | ₹44,81,763.9 |
| 8 | Quarrying, Carrying, Supplying stone boulders/shingles from the Engineer-in-charge selected quarrying site to the site of work including cost of material, loading, unloading and carriage including all incidental charges like Royalty and labour charges for laying boulder in apron or within wire netting of sausage for slope pitching and all lifts & dressing the exposed faces etc. complete as per direction of the Engineer-in-charge. (Quarry belongs to Forest Deptt. Govt of W.B). Certificates in original from competent authority are to be submitted along with the bill otherwise amount due towards Royalty ( including other charges whereever applicable but excluding GST ) will be deducted from the bill of works. For Forest area total charges Rs. 178.30 including Royalty(Rs. 75.00), Entry Fees and transit permit. Boulder above 30Kg -60% . 20 kg - 30% and 10 kg- 10%. | 6,282 | Cum | 1,371.17 | ₹86,13,689.94 |
| 9 | Quarrying carrying, Supplying Stone boulders/ shingles from the Eigineer-in charge selected quarrying site to the site of work including cost of material, loading, unloading, and carriage and including all incidental charges like Royalty and labour charges for laying boulder in Sasuage or within wire netting of saussage for slope pitching and all lifts & dressing the exposed faces etc. complete as per direction of Engineer-in-charge. (Quarry belongs to Forest Deptt. Govt of W.B) . Certificates in original from competent authority are to be submitted along with the bill, otherwise amoun t due towards Royalty( including other charges wherever applicable, but excluding GST) will be deducted from the bills of works. For Forest area total charges Rs. 178.30 including Royalty(Rs. 75.00), Entry Fees and transit permit. Comprising Boulder above 30Kg -60% .+ 20 kg - 30% and 10 kg- 10% | 4,696 | Cum | 1,091.1 | ₹51,23,805.6 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.10 MB
Bar4.pdf
Tender Documents • 0.85 MB
BOQ_2442656.xls
BOQ • 0.34 MB
Form2911s4.pdf
Tender Documents • 0.68 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].