Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹68.3 LAdmitted-Finance | ₹68.3 L | L1 | Admitted-Finance |
| 2 | L1₹68.3 LAdmitted-Finance | ₹68.3 L | L1 | Admitted-Finance |
| 3 | L2₹70.3 LAdmitted-Finance GRAM AEMANPUR DISTRICT BULANDSHAHR UTTAR PRADESH | BULANDSHAHR | BULANDSHAHR | UTTAR PRADESH | ₹70.3 L | L2 | Admitted-Finance |
| 4 | L3₹76.3 LAdmitted-Finance | ₹76.3 L | L3 | Admitted-Finance |
| 5 | L4₹78.7 LAdmitted-Finance | ₹78.7 L | L4 | Admitted-Finance |
| Sl No | Description | Qty | Unit | M/S AARADHYA AND ADHYATM ASSOCIATES L3 | M/S A.G. ENTERPRISES L6 | S M ENTERPRISES L1 | Sidhi Enterprises L1 | NATIONAL CONTRACTOR & GENERAL ORDER SUPPLIER L5 | RAJ ENTERPRISES L4 | SINGH ENTERPRISES L2 |
|---|---|---|---|---|---|---|---|---|---|---|
| 1.00Safe loading & carriage including unloading & proper stacking of following store materials from ESC Daliganj/JE store to site of work. | ||||||||||
| 1.01 | 33KV 3X300 SQ MM XLPE CABLE | 5,600 | Mtr | 6 ₹33,600 | 1,675 ₹93.8 L | 10 ₹56,000 | 10 ₹56,000 | 20 ₹1.1 L | 14 ₹78,400 | 10 ₹56,000 |
| 1.02 | 33KV END TERMINATION O/DOOR 3X300 SQ MM | 22 | No | 100 ₹2,200 | 9,000 ₹2.0 L | 201 ₹4,422 | 200 ₹4,400 | 50 ₹1,100 | 150 ₹3,300 | 50 ₹1,100 |
| 1.03 | 33 KV ST/TH C/J KIT 3X300 SQ MM | 23 | NO | 100 ₹2,300 | 3,000 ₹69,000 | 301 ₹6,923 | 300 ₹6,900 | 100 ₹2,300 | 200 ₹4,600 | 60 ₹1,380 |
| 1.04 | ACSR PANTHER CONDUCTOR | 33.33 | KM | 5,000 ₹1.7 L | 1,55,000 ₹51.7 L | 1,180 ₹39,329.40 | 1,200 ₹39,996 | 5,000 ₹1.7 L | 3,000 ₹99,990 | 2,000 ₹66,660 |
| 1.05 | 33 KV Feeder control Panel | 1 | No | 2,000 ₹2,000 | 1,50,000 ₹1.5 L | 3,500 ₹3,500 | 4,000 ₹4,000 | 3,000 ₹3,000 | 3,500 ₹3,500 | 800 ₹800 |
| 1.06 | 33 KV VCB | 1 | No | 2,000 ₹2,000 | 2,30,000 ₹2.3 L | 3,500 ₹3,500 | 4,000 ₹4,000 | 3,000 ₹3,000 | 4,500 ₹4,500 | 800 ₹800 |
| 1.07 | 33 KV CT 400/200/1 A | 3 | No | 2,000 ₹6,000 | 30,000 ₹90,000 | 201 ₹603 | 200 ₹600 | 500 ₹1,500 | 800 ₹2,400 | 150 ₹450 |
| 1.08 | 33 KV Bus Isolator | 1 | No | 2,000 ₹2,000 | 40,000 ₹40,000 | 2,000.5 ₹2,000.50 | 2,000 ₹2,000 | 500 ₹500 | 1,500 ₹1,500 | 200 ₹200 |
| 1.09 | 33 KV Line Isolator | 1 | No | 2,000 ₹2,000 | 50,000 ₹50,000 | 2,000.5 ₹2,000.50 | 2,000 ₹2,000 | 500 ₹500 | 1,500 ₹1,500 | 200 ₹200 |
Tender Value
₹1.2 Cr
EMD Value
₹1.3 L
Closing Date
15 Oct 2020, 5:00 pmClosed
S.E EUCC(V) LESA Cis-gomti Lucknow
Lesa Bhawan Near Residency Kaiserbagh, Lucknow
Construction of 33 kv Overhead and Underground feeder from 132/33 kv S/S Bijnaur to 33/11 kv substation Bani and Construction of One line Bay.
2020_MVVNL_519018_1
21/EUCC(V)/LESA/2020-21
Open Tender
Electrical Works
180 days
132/33 kv S/S Bijnaur to 33/11 kv substation Bani
As per tender documents
2 documents required · 2 mandatory
₹5,900
A/c.No. 10101985364, IFSC CODE No. SBIN0003347 SBI
₹1.3 L
6 Nov 2020
8 Oct 2020
16 Oct 2020
8 Oct 2020
15 Oct 2020
8 Oct 2020
Amount
Safe loading & carriage including unloading & proper stacking of following store materials from ESC Daliganj/JE store to site of work.
33KV 3X300 SQ MM XLPE CABLE
33KV END TERMINATION O/DOOR 3X300 SQ MM
33 KV ST/TH C/J KIT 3X300 SQ MM
ACSR PANTHER CONDUCTOR
33 KV Feeder control Panel
33 KV VCB
33 KV CT 400/200/1 A
33 KV Bus Isolator
33 KV Line Isolator
STP 11 M long
33 KV pin insulator
Top chanel 100X50 MM 10 kg / mtr
MS angle 65x65x6MM 5.8 kg / mtr
33 KV pin with nut
M S Earthing Rod 20x2500 mm
STAY WIRE 7/8 SWG
11 KV DISC INSULATOR B&S
Single core PVC Cable 1X400
CROSS ARM CHANNEL 100X50 MM
MS CHANNEL 125X65 MM
GI WIRE 6 SWG
STAY 20X1800 MM
MS ANGLE 75X75X6 MM
MS ANGLE 65X65X6 MM
Fabrication & erection of single pole for 33 KV line on 11 M long ST Pole with fixing of necessary clamp & other acessories like 1 no. Channel cross arm, Danger board, No Plate, barbed wire etc. contractor shall provide, necessary clamps, F-Bracket etc. as per RESPO norms.
Fabrication & erection of 33 KV cable exposure type double pole with the provission of separate bus bar for each cable with fixing of necesory clamps and other acessories like danger board,number plate,barbed wire, 9 no. pin insulators with pins,2 no. channels 125x65 mm (1600mm each),1 no.MS channel 125x65mm(3200mm in length) and 2 no.MS angle 65x65x6 mm (each 3200mm in length ) for supporting the hoisting of cable & poles.its jumpering by single core PVC aluminium cable with proper size of lug. (all material arranged by contractor except steel,pole,PVC aluminium cable & insulator).as per RESPO norms.
End Type Double Pole- Fabrication, erection, of double pole of end terminations with one side cable exposure for 33 KV line on 11 M long ST pole with fixing of necessary clamps & other accessories like disc insulator, 1 no. top chennel 125×65 mm - 3.20M & 1 no. gaurding angle and 1 no. X bracing,disc fittingits,33kv pin with pin insulator ,danger board,number plate,barbed wire,jumpering by PG clamp 4 no stay complete work (all material arranged by contractor except steel,insulator,disc insulator with fitting & pole).as per RESPO norms.
Sectional Double Pole-Fabrication, erection, of double pole for 33 KV line on 11 M long ST pole with fixing of necessary clamps & other accessories like ,disc insulator, 1 no. top chennel 125×65 mm - 3.20M & 1 no. gaurding angle and X bracing,disc fittingits,33kv pin with pin insulator ,danger board,number plate,barbed wire,jumpering by PG clamp 8 no Stay set etc.(all material arranged by contractor except steel,insulator,disc insulator GI Pin, Disc Fitting & pole).as per RESPO norms.
Fabrication, erection, of Tri pole for 33 KV line on 11 M long ST pole with fixing of necessary clamps & other accessories like ,disc insulator, 3 no. top chennel 125×65 mm - 3.20M & 2 no. gaurding angle and 3 side X bracing,disc fittingits,33kv pin with pin insulator ,danger board,number plate,barbed wire,jumpering by PG clamp 8 no stay set etc. (all material arranged by contractor except steel,insulator,disc insulator GI Pin, Disc Fitting & pole).as per RESPO norms.
COnversion of existing single pole support into Double Pole-Fabrication, erection, of single pole in alignmnet of existing single pole to convert into double pole pole for 33 KV line on 11 M long ST pole with fixing of necessary clamps & other accessories like ,disc insulator, 1 no. top chennel 125×65 mm - 3.20M & 1 no. gaurding angle and X bracing,disc fittingits,33kv pin with pin insulator ,danger board,number plate,barbed wire,jumpering by PG clamp etc. (all material arranged by contractor except steel,insulator,disc insulator GI Pin, Disc Fitting & pole).as per RESPO norms.Dismantling of accessories of existing pole like X-arm 33 KV pin insulators and pins etc also include in this work,
Making Section & Holding of exsting 33 KV overhead line on exsting D/P or S/P for enabling removal of conductor on one side of 33 KV overhead line ,its stringging on D/P .(agency also to provide temporary stay at the time of dismantaling of overhead line)
Erection of single stud pole support one ST pole 11 M long with fixing of necessary clamps and other accessories required for erection.
Making proper markig of cable by markig tape/marking tag at proper interval (every 2 mtr underneath) marking tape /tag provided by contractor
Laying of 33 KV XLPE cable
D/C Cable laying in normal soil by digging of trench 1100 mm deep, 750 mm wide including supply of required material as fine sand, 1st class bricks, stone slab. Inter axial spacing between the two cable should be in between 0.25 m to 0.40m. the two cables should be seprated by a partition of single bricks (All the material required for laying will be supplied by the contractor except 33 KV XLPE cable)
Laying of 33 KV Single cable in normal Soil
Laying of 33 KV XLPE Single cable in Pakka metallic Road
Cable laying By dirll method Single circuit
Cable laying By dirll method Single circuit with MS/ GI Pipe 160 mm dia
In RCC pipe single circuit.
In GI pipe 160 mm dia single circuit.
In HDPE Pipe 160 mm Dia
Laying in already existing trench S/C
Digging of Pit in kachcha/Pakka land in 1.2 mtr deep 3 mtr long and 2 mtr wide for 33 KV ST/TH 3x300 sq mm and boxing with brick sand and stone slab as per norms.
Hoisting of 33KV XLPE cable on double pole with MS pipe of size 5/6" dia 3 M long including its jumpering complete with clamps, nuts and bolts(all material arranged by contractor).
Hoisting of 33 KV Cable on cable stand
Fixing of cable marker and dipitching of feeder name and voltage on this
Plotting of cable layout rute on graph paper (i.e. depth underneath and distance from either side from prominent reference fixed point ) the reference point must not be more than 100 mtr.
Stringing & Sagging of three phase 33 kv line on ACSR Panther conductor as per RESPO Norms.
Stringing and sagging of three nos. Earth/GI wire withh caddle guarding of above 33 kv line as per RESPO Norms. Shifting of existing line conductor of 11 Kv/LT lines to maintain proper clearence in between both lines.
Guarding of O/H Line (50 Mtr span)- Fabrication and fixing of gaurding angle on single/double Polesr as per RESSPO Norms including provision of all necessary clamps and hooks.Shifting of existing line conductor of 11 KV/LT lines to maintain proper clearence in between both Lines.(all the material arranged by contractor except steel and GI wire 6 swg)
Ordinary Earthing of pole by M.S. Earthing Rod 20x2500 mm as per Resspo Norms only earting rod provided by deptt
Extra Stay Set - Nozzillling & grouting of stay set .(all the material except stay set will be arranged by the contractor )
Construction of masonry type plinth for 33KV VCB of size 1.6x1.6x1 M brick, sand, cement and stone grit including grouting of 4Nos foundation volts for erection of 33KV VCB.
Isolator Structure-Fabrication of Isolator structure minimum 3.5 mtr overall height and 2.5 mtr above ground level as per RESSPO drawing, with help of M.S channel 125x65 mm two pieces of M.S channel joined to each other by M.S flat 50x6 mm, diagonally at the interval of 0.5 mtr and top & bottom of the structure. Grouting of Isolator structure in CC (cement ,coarse sand and stone grit of 20 mm gauge) including supply of necessary T&P and painting os structure complete.(only M.S channel and angle provided by the deptt)
Lightning Arrestor/ CT structure/ PT structure : - Fabrication of lightning arrestor/CT structure/ PT structure as per RESSPO drawing with the help of 2 nos M.S channel 125x65 mm minimum 3.5 mtr long grouting 1 mtr deep from ground level in cc in ratio 1:4:8. complete in all respect.
Fabrication of structures, grouting, plinthing and painting of structures for following equipment.
Cable stand
Mounting of accessories/equipment on fabricated structure complete work with making proper alignment and tightening the work includes fabrication work if required for proper operation of equipment .
33 KV VCB
Bus/Line Isolator
Dragging of 33 KV T/F/ Feeder Control Panel from unloading place upto control room and placement, erection, and grouting commissioning of the same as per RESPO Norms
Feeder control panel
Construction of cable trench of size 150 mm wide 300 mm deep with brick work along with provision trench cover M.S strip at the interval of 0.30 M and M.S angle at both the edge of the trench.
Construction and fixing of trench cover0.5 M wide 0.75 mm thick with cement, coarse sand & stone grit in ratio 1:2:4 for covering of cable trench150 mm wide with provision of M.S Angle and MS Bar as per RESPO Norms
Laying of copper control cable of following sizes its proper dressing ,ferruling and connection with the system.
2x2.5 sq mm
4x2.5 sq mm
6x2.5 sq mm
Earthing of Substation equipment by way of boring and lowering of G.I pipe 1.5" dia up to water level and minimum 20 M deep from the ground level connection in between GI pipe and equipment with GI strip of size 50x6 mm.
Jumpering of Complete line bay by ACSR Panther conductor with the help of connectors and PG clamp
Fabrication of teniss net type switchyard fencing with toe wall with help of wiremesh10 SWG (37mmx50mm) as per drawing along with Fabrication of one number gate made of MS Angle, MS Channel, MS Flat together with locking arrangement, its Installation including the cost of civil material, angle 50x50x6mm, Channel Etc
Laying of Interlocking tiles at yard area as per norms
Grouting,Plinting and Painting of new erected 11M long ST poles of single pole support,double pole cable exposures and end type poles of 33 KV lines
Digging of Pit in kachcha/Pakka land in depth upto 1/6 length of Pole, Dragging of STP from near by place/Dump, Erection of Single pole along with stone pad in bottom with proper alignment of line for 33 KV line on 11 M long ST Pole and refilling with ramming of earth.
Grouting of pole in depth of 1/6 the length of pole in ratio 1:4:8 in cement sand and brick balast as per RESPO norms.
Construction of pole plinth 300mm x 450 mm above ground level in 1:2:4 in cement, coarse sand and stone gritt as per RESPO norms.
Painting of new erected ST pole with two coat of red oxide paint,PO red paint at top of pole 2 M & balance by two coats of best quality aluminium paint ISI of Burger/Nerolac/Asian mark as per norms.
High Pressure Testing of 33 cables/line as per norms
Tree branches cutting and chopping where required aprox 2 KM .
Sidhi Enterprises
SINGH ENTERPRISES
M/S AARADHYA AND ADHYATM ASSOCIATES
RAJ ENTERPRISES
NATIONAL CONTRACTOR & GENERAL ORDER SUPPLIER
M/S A.G. ENTERPRISES
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.05 MB
docs.pdf
Tender Documents • 1.00 MB
BOQ_779410.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid