BHUPENDER SINGH
DIV 1 Hissar
ANNUAL MTC. ESTIMATE OF INTERNAL SWD SCHEME FOR SECTOR-1,4,3,5, 27-28, HISAR
2026_HBC_525673_1
2026130FFA15 1B04 4FD4 86FC 0CAAB7F74C59259HSV
Open Tender
Civil Works
120 days
Hisar
Repairing of Storm Water Drains and Construction of road gullies at various locations in Sector 1and4, Hisar and all others works contingent thereto
2 documents required · 2 mandatory
₹500
Yes
₹34,000
Yes
1 Jun 2026
1 Jun 2026
9 Jun 2026
1 Jun 2026
8 Jun 2026
1 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | [11.5.1]12 mm cement plaster of mix : 1. 1:2 (1 cement: 2 fine sand) | 560 | Sqm | 139 | ₹77,840 | BI01010001010000000000000515BI0100001115 |
| 2 | [11.52]Cement rendering on plaster 1 mm thick | 560 | Sqm | 28 | ₹15,680 | BI01010001010000000000000515BI0100001116 |
| 3 | [21.87.1.2]Constructing brick masonry road gully chambers as per standard drawings (as per sizes given below) including dressing of beds and sides of chambers to exact profiles, 15cm thick lime concrete 16:24:100 (as per specified in item No.10.6) in foundations 1st class brick work laid in cement sand mortar 1:5, 40 mm thick cement concrete 1:2:4 topping inside the chamber with a floating coat of 1.5mm thick neat cement laid in one operation to the topping, the entire inner surface of the chamber rendered with neat cement not less than 12mm in thickness of 1:2 cement sand plaster and finished with floating coat of neat cement 1 mm thick left absolutely smooth polished and correct to templates including labour for fixing the C.I. road gully grating and frame including painting with coal tar (as Specified in item No. Item 21.48) complete to the requirement of the Engineer in-charge 1.2. Single road gully chamber - Size.-610 mmx457 mmx1105mm | 30 | Each | 4,085 | ₹1,22,550 | BI01010001010000000000000515BI0100001117 |
| 4 | [21.87.2.1]Constructing brick masonry road gully chambers as per standard drawings (as per sizes given below) including dressing of beds and sides of chambers to exact profiles, 15cm thick lime concrete 16:24:100 (as per specified in item No.10.6) in foundations 1st class brick work laid in cement sand mortar 1:5, 40 mm thick cement concrete 1:2:4 topping inside the chamber with a floating coat of 1.5mm thick neat cement laid in one operation to the topping, the entire inner surface of the chamber rendered with neat cement not less than 12mm in thickness of 1:2 cement sand plaster and finished with floating coat of neat cement 1 mm thick left absolutely smooth polished and correct to templates including labour for fixing the C.I. road gully grating and frame including painting with coal tar (as Specified in item No. Item 21.48) complete to the requirement of the Engineer in-charge 2.1. Double Road Gully Chamber - Size 1448mm x 457mm x 800mm | 20 | Each | 5,338 | ₹1,06,760 | BI01010001010000000000000515BI0100001118 |
| 5 | [6.25.1]Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer-in-charge. 1. All works up to plinth level | 76.5 | cum | 4,464 | ₹3,41,496 | BI01010001010000000000000515BI0100001119 |
| 6 | [6.30.3]Centering and shuttering including strutting, propping etc. and removal of form for 3. Suspended floors, roofs, landings, balconies and access platform | 552.5 | Sqm | 208 | ₹1,14,920 | BI01010001010000000000000515BI0100001120 |
| 7 | [6.34.6]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect above plinth level Note:- Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 6. Thermo-Mechanically Treated bars of grade Fe-500D or more. | 6,885 | Kg. | 68 | ₹4,68,180 | BI01010001010000000000000515BI0100001121 |
| 8 | [7.21.1]Brick work with common burnt clay non-modular bricks of class designation 10.5 in foundation and plinth in: 1. Cement mortar 1:4 (1 cement : 4 coarse sand) | 89.7 | cum | 4,128 | ₹3,70,281.6 | BI01010001010000000000000515BI0100001122 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.96 MB
BOQ_604642.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid