| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.4 LAccepted-AOC NO 7 AMMAPETTAI STREET NETTAPAKKAM POST PUDUCHERRY 605 106 | PONDICHERRY | PUDUCHERRY | 605106 | L1 | Accepted-AOC L1 1st lowest tenderer | |
| 2 | L2₹3.6 L+₹15,529.35 (4.53%)Rejected-Finance NO 28 NEW STREET BHARATHIPURAM PUDUCHERRY 605 001 | PONDICHERRY | PUDUCHERRY | 605001 | L2 | Rejected-Finance IInd lowest |
Tender Value
₹3.3 L
EMD Value
₹6,548
Closing Date
1 Mar 2023, 4:30 pmClosed
Executive Engineer
Office of the Executive Engineer, BRS, PWD, Puducherry
Reconstruction of damaged cross U drain in Vadukuppam road near P.S. Nallurpet in Nettapakkam Commune, Puducherry.
2023_PWDC1_12097_2
No.36/PW/BRS/22-23
Open Tender
Civil Works - Canal
Item Rate
60 days
Vadukuppam
Please refer Tender documents.
3 documents required · 3 mandatory
₹525
₹6,548
15 Mar 2023
24 Feb 2023
2 Mar 2023
24 Feb 2023
1 Mar 2023
24 Feb 2023
Amount
Dismantling manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead - bituminous road
Demolishing R.C.C work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead
Demolishing brick work manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead - in cement mortar
Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead - Nominal concrete 1:4:8 or leaner mix (including equivalent design mix)
Earthwork in excavation of foundation of structure as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remainging earth locally for road work - by mechanical means - depth upto 3m (Ordinary soil)
Supply of Quarry rubbish including stacking to department gauge for premeasurement and spreading required thickness
Cement concrete 1:4:8 mix with stone aggregate 40mm nominal size in foundation upto a depth of 1.5 metres below ground level and upto height of 1.5 above ground/bed level.
Centring and shuttering including strutting , propping etc. and removal of form work for - foundations, footings, bases for columns
Cement concrete 1:3:6 mix with stone aggregates 20mm nominal size mechanically mixed and vibrated in foundation upto a depth of 1.5 metres below ground level and 1.5 metres ground/bed level.
12mm cement plaster finished with a floating coat of neat cement of mix - 1:4 (1 cement :4 fine sand)
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - all work upto plith level - 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry, but excluding the cost of nosing of steps etc .complete - 40mm thick with 20mm nominal size stone aggregate
Neat cement punning
Providing , hoisting and fixing upto plinth level for precast reinforced cement concrete for drain cover slab of length varying upto 1.50m of various thickness including the cost of required centering, shuttering and finishing smooth with 6mm thick cement plaster 1:3 (1 cement 3 fine sand) on all faces of slab but excluding cost of reinforcement with 1:1.5:3 (1 cement 1.5 coarse sand 3 graded stone aggregate 20mm nominal size)
Steel reinforcement for R.C.C. works including bending, binding and placing in position - Thermo Mechanical Treated Bars (TISCON / VIZAG / IISCO / SAIL/JSW) Fe -415 or more
Supplying and filling with gravel (excluding rock) in trenches , plinth, sides of foundations etc . In layers not exceeding 20 cm in depth consolidating each deposited layers by ramming and watering etc .complete including all lead and lift
Desilting the canal by removing silt, slush and debries from the bed of the drain removing the grass , buses etc., complete in unhygenic and foul condition including disposal of the same within an average lead of 1KM without polluting the environment by manual means
A BASKAR
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .