Tender Value
₹3.4 L
EMD Value
₹6,800
Closing Date
30 Sept 2026, 5:00 pm3d left
Executive Engineer
Electrical Division No.II, HPPWD, U.S. Club, Shimla-01.
Comprehensive annual maintenance AMC of EATOn make 125 KVA three phase UPS system installed at New OPD Block under IGMC Shimla for the period of one year.
2026_PWD_143815_1
ED.II.CB.TA.NIT.2804-14 dt.18-09-2026
Open Tender
Electrical Works
Percentage
365 days
Shimla
Please refer to tender documents. Eligibility criteria is mentioned at page No. 6-7, 9-10 of GCC. Documents mentioned in eligibility criteria must be uploaded to qualify the bid.
7 documents required · 7 mandatory
₹350
₹6,800
23 Sept 2026
23 Sept 2026
1 Oct 2026
23 Sept 2026
30 Sept 2026
23 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Comprehensive Annual Maintenance Contract (CAMC) of EATON Make Three Phase UPS Systems installed at New OPD and Trauma Block under IGMC, Shimla for a period of one year, including quarterly preventive maintenance visits, unlimited breakdown attendance, repair/replacement of defective components, battery health check-up, testing, inspection and all allied services as specified in the scope of work. | |||||
| 1.01 | • Cleaning up of Unit, Air Filter, Visual Inspection to check any deformation.
• Checking and Adjustment of Power parameters like input. Output, DC voltage & Current.
• Checking and Adjustment of Control parameters on different PCBs.
• Tightness of all connection, if shut down possible.
• Checking of Rectifiers, Invertors, Fan's, Power supplies, Contactors, Sticking or welded relays and replacement if needed.
(if Shut Down Allowed)Functional Checking up of Inverter section.
• All functional check of load transfer between Mains to battery and vice versa. Discharge test of battery with UPS
load and Redundancy check in case of parallel operation (with Customer approval).
• UPS Output Load balancing evaluation. Suggest for correction if needed. Install or perform Engineering Field Change Notices (FCN) as necessary.
• A report with all details of the service performed and suggestions for any changes will be submitted.
• Battery health Checkup • Inspection of UPS set i/e replacement /repair of fuses/capacitors IGBT/mosfet/BJT panel /card/converter/inverter part/battery inspection ) quaterly visits @ 4 no visits per year. Unlimited breakdown call visits during AMC period. | - | - | - | - |
| 1.02 | Comprehensive Maintenance consists of measures to maintain the equipment in a proper operating condition. Preventive maintenaace includes functional checking, necessary, adjustrments, etc.
Preventive maintenance to be carried out at times planned in advance and during/after working hours | - | - | - | - |
| 1.03 | Breakdown rectification is to be carried out in the event of malfunction, which prevent the operation of the equipment. Work to be carried out during the service coverage time as per the AMC contract/SOS basis. Breakdown includes fault finding, repair or replacement of
defective parts and functional checking. Defective parts discovered during maintenance can either be repaired or replaced by new or as new-parts. Spares replaced should be of the same make | - | - | - | - |
| 1.04 | In addition to above the contractor/appointed technician will attend the complaint when there is fault in UPS set with in 12 hours.It will be responsibillity of the contractor that the UPS functions smoothly during the contract period.. | - | - | - | - |
| 1.05 | Comprehensive Annual Maintenance Contract (CAMC) of EATON Make 125 KVA Three Phase UPS, Sr. No. DN345WAA02, installed at 6th Floor, New OPD Block, IGMC Shimla. | 1 | Job | 3,41,516 | ₹3,41,516 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.71 MB
GCC.pdf
Tender Documents • 5.06 MB
BOQ_213781.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .