Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹1.1 Cr
EMD Value
₹2.2 L
Closing Date
3 Nov 2026, 6:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
DEO, SSM, ALIPURDUAR.
DOOARS KANYA, 3RD FLOOR, ROOM NO-320
CONSTRUCTION OF ADDITIONAL CLASS ROOM OF PANCHKOLGURI BFP, PASCHIM SIMLABARI PRY AND PASCHIM SIRUBARI A. P., (6 UNITS) WITHIN ALIPURDUAR-I BLOCK
2026_DSE_1044294_5
NIT NO- 1/ACR/SSM/APD/26-27
Open Tender
CIVIL WORKS
Percentage
90 days
ALIPURDUAR
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹2.2 L
DPO OFFICE, SSM, ALIPURDUAR.
5 Oct 2026
5 Oct 2026
6 Nov 2026
5 Oct 2026
3 Nov 2026
5 Oct 2026
8 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. | - | Cum | 260.3 | - |
| 2 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | - | Cum | 7,878.5 | - |
| 3 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement :
1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | - | Cum | 10,852.95 | - |
| 4 | Providing and laying damp-proof course 40 mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 12.5 mm nominal size derived from natural sources) | - | Sqm | 410.85 | - |
| 5 | Brick work with common burnt clay modular bricks of class designation 7.5 in foundation and plinth in:Cement Mortar 1:6 (1 cement : 6 coarse sand). | - | Cum | 6,295.15 | - |
| 6 | Half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level. Cement mortar 1:4 (1 cement :4 coarse sand) | - | Sqm | 1,123.8 | - |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form work for : Foundations, footings, bases of columns, etc. for mass concrete | - | Sqm | 392.15 | - |
| 8 | Centering and shuttering including strutting, propping etc. and removal of form work for : Lintels, beams, plinth beams, girders, bressumers and cantilevers | - | Sqm | 736.4 | - |
| 9 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.Thermo-Mechanically Treated bars of grade Fe-500D or more. | - | Kg | 107.85 | - |
| 10 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift. | - | Cum | 196 | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.88 MB
BOQ_2561482.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .