CONSTRUCTION OF CC ROAD FROM NH-48 TO INDUSTRIAL AREA KANYAKHERI UNDER BUDGET ANNOUNCEMENT
2026_CEPWD_567716_1
NIT-07/2026-27 PWD MANDALGARH
Open Tender
Civil Works
150 days
MANDALGARH
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,000
Egras Challan Deposit
₹4.1 L
Yes
15 Jun 2026
15 Jun 2026
3 Jul 2026
16 Jun 2026
2 Jul 2026
16 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | (A) Road Work
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per MoRTH Specification Clause 201.
By Mechanical Means
In area of non-thorny jungle | 0.81 | Hect. | 10,374 | ₹8,402.94 |
| 2 | Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 100 m, stacking serviceable and unserviceable materials separately as per MoRTH Specification Clause 202
By Mechanical Means
Bituminous Courses & Granular Courses | 164.25 | Cum | 69 | ₹11,333.25 |
| 3 | Dismantling of cement concrete pavements by mechanical means using pneumatic tools breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled materials upto a lead of 1000 m, stacking serviceable and unserviceable materials separately | 187.5 | Cum | 515 | ₹96,562.5 |
| 4 | Providing laying spreading and compacting specified graded sand, gravel (crushed stone) as per Table 400-1,400-2 or any other course material as per design mix, as per CBR in sub base course including premixing the material at OMC in wet mix plant, carriage of mixed material spreading in uniform layers with motor grader F.E loader on a prepared base and compacting with vibratory roller to achieve desired density (as per I.S.2720) including all material, labor, machinery, lighting guarding, barricading and maintenance of diversion
complete.[MoRTH specification : Clause 401]. By mechanical means.
For Grading-I Material | 1,291.5 | Cum | 773 | ₹9,98,329.5 |
| 5 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with Tractor Mount Grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density,
complete as per MoRTH Specification Clause 401.
For Grading III Material | 922.5 | Cum | 407 | ₹3,75,457.5 |
| 6 | Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a fully automatic computerised batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing. | 861 | Cum | 2,418 | ₹20,81,898 |
| 7 | Construction of un-reinforced , plain cement concrete pavement M30 (Grade), thickness as per design, over a prepared sub base, with 43/53 grade cement as per Clause 602.2.2 , coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a in fully automatic Batching Plant and transported to site in transit mixer for having continous agitated mixer, manufactured as per approved mix design including pumping of R.M.C. from transit mixer to site of laying , with all lead and lift including cost of admixtures in recommended portion as per IS 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer in charge laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using Fixed Form Paver and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days using water finishing to lines and grade as per drawing and MoRTH Specification Clause 602 including vaccum dewatering process with all required equipments (Dowel Bars will be paid seprately). | 2,583 | Cum | 5,160 | ₹1,33,28,280 |
| 8 | Providing and Fixing of Dowel Bars of Mild Steel confirming to IS : 432 of specified length and diameters as per MoRTH Specification IRC 15 & 58 including cutting, placing in position across transverse joint with proper spacing, providing with PVC sleeve complete as per drawing, technical specification and as
per direction of the Engineer-in-charge. | 3,716.16 | Kg | 66 | ₹2,45,266.56 |
| 9 | Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single Row
Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets Clause 2905.
300 mm dia | 37.5 | Mtr. | 612 | ₹22,950 |
| 10 | Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single Row
Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets Clause 2905.
600 mm dia | 37.5 | Mtr. | 1,727 | ₹64,762.5 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 1.43 MB
Tendernotice_2.pdf
PDF • 5.64 MB
Tendernotice_3.pdf
PDF • 7.00 MB
Tendernotice_4.pdf
PDF • 1.17 MB
Tendernotice_5.pdf
PDF • 6.83 MB
Tendernotice_6.pdf
PDF • 1.25 MB
Tendernotice_7.pdf
PDF • 0.33 MB
Tendernotice_8.pdf
PDF • 0.56 MB
Tendernotice_9.pdf
PDF • 1.23 MB
BOQ_1009860.xls
BOQ • 0.31 MB
01-TD-NH48.pdf
Tender Documents • 0.20 MB
Download all tender documents and submit your bid