| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹11.3 LAdmitted-Finance | -21.20% | ₹11.3 L | L1 | Admitted-Finance |
| 2 | L2₹13.9 LAdmitted-Finance | -3.30% | ₹13.9 L | L2 | Admitted-Finance |
| 3 | L3₹14.1 LAdmitted-Finance | -1.99% | ₹14.1 L | L3 | Admitted-Finance |
| 4 | L4₹14.2 LAdmitted-Finance | -1.00% | ₹14.2 L | L4 | Admitted-Finance |
| 5 | Rejected-Technical | - | - | - | Rejected-Technical Not responsive |
Tender Value
₹14.3 L
EMD Value
₹28,700
Closing Date
15 May 2026, 4:00 pmClosed
Er Rajesh Kumar
Executive Engineer PWD R and B Division Basohli
Please refer in BOQ
2026_PWDJK_309589_1
e-NIT No. 11 of 2026-27 dated 09-05-2026
Open Tender
Civil Works
90 days
Kgrore
Please refer Tender documents.
2 documents required · 2 mandatory
₹600
Executive Engineer PWD R and B Division Basohli
₹28,700
19 May 2026
9 May 2026
16 May 2026
10 May 2026
15 May 2026
10 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables, etc. (not exceeding 1.5m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5m including getting out excavated earth and disposal of surplus excavated earth as directed lead upto 1mtr. from cutting edge. a) All kinds of soil. | 33.03 | Cum | 479.3 | ₹15,831.28 |
| 2 | Providing and laying cement concrete of specified grade including curing but excluding the cost of centering and shuttering. All work upto plinth level with: a) 1:5:10 (1 cement:5 coarse sand:10 graded stone aggregate 40mm nominal size). | 7.06 | Cum | 4,826.5 | ₹34,075.09 |
| 3 | Providing and laying in position specified grade of reinforced cement concrete including curing but excluding the cost of centring ,shuttering, finishing and reinforcement. All work upto plinth level with: a) 1:1.5:3 (1 cement:1.5 coarse sand:3 graded stone aggregate 20mm nominal size). | 6.56 | Cum | 7,788.4 | ₹51,091.9 |
| 4 | Providing and laying cement concrete of specified grade including curing but excluding the cost of centering and shuttering. All work upto plinth level with: a) 1:3:6 (1 cement:3 coarse sand:6 graded stone aggregate 20mm nominal size) | 26.47 | Cum | 5,733.6 | ₹1,51,768.39 |
| 5 | Brick work with common burnt clay (non modular) bricks of class designation 7.5 in foundation and plinth including curing in cement mortar 1:6 (1 cement:6 coarse sand). | 24.22 | Cum | 7,571.55 | ₹1,83,382.94 |
| 6 | Extra for brick work with common burnt clay bricks / cement concrete bricks in superstructure above plinth level upto floor five level. | 24.22 | Cum | 1,455.65 | ₹35,255.84 |
| 7 | Providing wood work in frames of doors, windows, clerestory windows and other frames, wrought framed and fixed in position with hold fast lugs or with dash fasteners of required dia and length (hold fast lugs or with dash fasteners shall be paid for separately). a) Sal Wood. | 0.29 | cum | 1,42,085.65 | ₹41,204.84 |
| 8 | Reinforced cement concrete work in walls (any thickness) including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts upto floor five level including curing but excluding cost of centering shuttering, finishing and reinforcement. a) 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size). | 0.92 | Cum | 9,395.7 | ₹8,644.04 |
| 9 | Reinforced cement concrete work in beams, suspended floors, roofs having slope upto 15°,landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases upto five level including curing but excluding the cost of centring, shuttering, finishing and reinforcement with:
a) 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size) | 10.69 | Cum | 9,821.85 | ₹1,04,995.58 |
| 10 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in
position and binding all complete above plinth level: a) Thermo-Mechanically Treated bars of grade Fe-500D or more. | 1,817.41 | Kg | 123.2 | ₹2,23,904.91 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.24 MB
BOQ_1002138.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid