| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹10.0 CrAccepted-Finance | L1 | Accepted-Finance L1 | |
| 2 | L2₹10.6 Cr+₹53.4 L (5.32%)Accepted-Finance | L2 | Accepted-Finance L2 | |
| 3 | L2₹10.6 Cr+₹53.4 L (5.32%)Accepted-Finance | L2 | Accepted-Finance L2 | |
| 4 | L2₹10.6 Cr+₹53.4 L (5.32%)Accepted-Finance | L2 | Accepted-Finance L2 | |
| 5 | L2₹10.6 Cr+₹53.4 L (5.32%)Accepted-Finance | L2 | Accepted-Finance L2 |
Tender Value
₹11.8 Cr
Closing Date
31 Aug 2021, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
CCE, RW Circle, Baripada
CCE, RW Circle, Baripada
OR-21-971 MRL05-Udala to Khuntapal (Dimagadia)
2021_CERWI_112529_39
PMGSY Online N.C.B. No-189
Open Tender
Civil Works - Roads
Percentage
365 days
Baripada
Please refer Tender documents.
4 documents required · 4 mandatory
₹10,000
OSRRA
Exempted
29 Nov 2021
12 Aug 2021
1 Sept 2021
12 Aug 2021
31 Aug 2021
12 Aug 2021
12 Aug 2021 - 27 Aug 2021
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per MoRD Specification for Rural roads Clause 201 by manual means as per the direction of the Engineer in charge. | 71,220 | Sqm | 5.64 | ₹4,01,680.8 |
| 2Dismantling of existing structures like culverts,bridges,retaining walls and other structure comprising of masonry,cement concrete,wood work,steel work,including T&P and scaffolding wherever necessary,sorting the dismantled material,disposal of unserviceable material and stacking theunserviceable material with all lifts and lead of 1000m as per Technical specification clause202.1 | |||||
| 2.01 | R.R. masonary Wall | 145.57 | Cum | 274.74 | ₹39,993.9 |
| 2.02 | Above 600 mm to 900 mm dia Hume pipe | 84.94 | mtr | 262.55 | ₹22,301 |
| 3 | Scarifying existing bituminous road surface to a depth of 150mm and disposal of scarified material with a lift of 3m and lead upto 1000m as per Technical Specification clause 301.4 of MORD by Mechanical means | 34,240.5 | Sqm | 6.79 | ₹2,32,493 |
| 4 | Excavation for road work in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, inaccordance with requirements of lines, grades and cross sections, and transporting to the embankement location with a lift of up to 1.5m and lead up to 1000m as per techincal specification clause 302.3 | 10,383.06 | Cum | 32.84 | ₹3,40,979.69 |
| 5 | Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structure graded and compacted to meet requirement of Table 300.1 and 300.2 as per Technical Specification clause 301.5 . | 10,866.52 | Cum | 28.61 | ₹3,10,891.14 |
| 6Construction of embankment with approved materials obtained from borrow pits with a lift upto 1.5m transporting to site, spreading, grading to required slope and compacting to meet requirement of tables 300.1 and 300.2 as per Technical Specification clause 301.5 | |||||
| 6.01 | By Mechanical means with a lead up to 1000 mtr | 52,792.17 | Cum | 163.16 | ₹86,13,570.46 |
| 7 | Fine dressing and turfing including transportation by mechanical means with all leads and lifts and placing of turfs in position and ramming with thapies including watering and cost of labour and all materials etc.complete as per the direction of the Engineer-in-charge. | 40,419.86 | Sqm | 18.52 | ₹7,48,575.81 |
stage.html
html • 0.07 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
BOQ_181455.xls
BOQ Document • 0.35 MB
81744556.pdf
Tender Document • 8.24 MB
81744559.html
Tender Document • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .