| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹9.4 CrAdmitted-Finance | +5.00% | ₹9.4 Cr | L1 | Admitted-Finance |
| 2 | L2₹9.8 CrAdmitted-Finance VAJIDPUR NIYAY MANIHARI GHAZIPUR | GHAZIPUR | UTTAR PRADESH | 232325 | +8.75% | ₹9.8 Cr | L2 | Admitted-Finance |
| 3 | L3₹10.0 CrAdmitted-Finance | +11.90% | ₹10.0 Cr | L3 | Admitted-Finance |
| 4 | Rejected-Technical | - | - | - | Rejected-Technical Simila Nature Certificate not attached and EMD not receive |
| 5 | Rejected-Technical | - | - | - | Rejected-Technical Simila Nature Certificate not attached |
Tender Value
₹9.0 Cr
EMD Value
₹18.0 L
Closing Date
30 Jun 2026, 3:00 pmClosed
General Manager
office of General Manager, Up State Bridge Corporation, 1/22 Yaman, Sahara Estate, Gorakhpur
Construction of Bridge over River Bansi at Pipra Gola Ghat in District Kushinagar
2026_UPSBC_1155733_1
516/Pipra Gola Ghat/2026-27 Dated 29 /05/2026
Open Tender
Civil Works - Bridges
Percentage
600 days
Kushinagar
please refer tender documents
2 documents required · 2 mandatory
₹20,000
As per Tender Document
₹18.0 L
Deoria
21 Jul 2026
30 May 2026
30 Jun 2026
30 May 2026
30 Jun 2026
30 May 2026
17 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Foundation
Providing and Constructing Temporary Island 24 m diameter for Construction of Well Foundation for 6 m dia. Well.
Assuming depth of water 1.0 m and height of island to be 1.25 m.
(Reference to SR No 12.9 MORT&H Specification-A) | 1 | No. | 1,79,845.65 | ₹1,79,845.65 |
| 2 | Providing and Constructing Temporary Island 24 m diameter for Construction of Well Foundation for 6 m dia. Well.
Assuming depth of water 4.0 m and height of island 4.5 m.
(Reference to SR No 12.9 MORT&H Specification-B) | 2 | No. | 7,40,091.63 | ₹14,80,183.26 |
| 3 | Providing and constructing one span service road to reach island location from one pier location to another pier location for the Ist season.
(Reference to SR No 12.9 MORT&H Specification-C) | 89.08 | RM | 5,041.92 | ₹4,49,134.23 |
| 4 | Providing and constructing one span service road to reach island location from one pier location to another pier location for the IInd season.
(Reference to SR No 12.9 MORT&H Specification-C) | 89.08 | RM | 5,041.92 | ₹4,49,134.23 |
| 5 | Providing and Laying Cutting Edge of Mild Steel weighing 40 kg per metre for Well Foundation complete as per Drawing and Technical Specification.
(Reference to SR No 12.10 MORT&H Specification | 5.37 | MT | 96,113.62 | ₹5,16,130.14 |
| 6 | RCC in Well Curb M-30 Plain/Reinforced Cement Concrete, in Well Foundation complete as per Drawing and Technical Specification using batching plant & manual placing.
(Reference to SR No 12.11 MORT&H Specification-Aiii Case ii) | 139.53 | Cum | 10,411.08 | ₹14,52,657.99 |
| 7 | RCC in Well Steining M-30 Plain/Reinforced Cement Concrete, in Well Foundation complete as per Drawing and Technical Specification using batching plant & manual placing.
(Reference to SR No 12.11 MORT&H Specification-B vii Case ii) | 2,245.41 | Cum | 9,555.61 | ₹2,14,56,262.25 |
| 8 | RCC in False Steining M-30 Plain/Reinforced Cement Concrete, in Well Foundation complete as per Drawing and Technical Specification using batching plant & manual placing.
(Reference to SR No 12.11 MORT&H Specification-B vii Case ii) | 71.84 | Cum | 9,555.61 | ₹6,86,475.02 |
| 9 | PCC in Bottom Plugging M-25 Plain/Reinforced Cement Concrete, in Well Foundation complete as per Drawing and Technical Specification using batching plant & manual placing.
(Reference to SR No 12.11 MORT&H Specification-C Case ii) | 425.84 | Cum | 9,051.62 | ₹38,54,541.86 |
| 10 | PCC in Intermediate Plugging M-20 Plain/Reinforced Cement Concrete, in Well Foundation complete as per Drawing and Technical Specification using batching plant & manual placing.
(Reference to SR No 12.11 MORT&H Specification-D Case ii) | 28.64 | Cum | 7,981.02 | ₹2,28,576.41 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.04 MB
PIPRAGHAT.pdf
Tender Documents • 1.38 MB
BOQ_2165155.xls
BOQ • 0.38 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].