| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹5.9 LAccepted-Finance | 1 | Accepted-Finance lowest pit | |
| 2 | 2₹5.9 L−₹1,566.52 (0.26%)Rejected-Finance | 2 | Rejected-Finance higher pit | |
| 3 | 3₹5.4 L−₹55,330.33 (9.33%)Rejected-Finance | 3 | Rejected-Finance higher pit |
| Sl No | Description | Qty | Unit | RATHINAM BALAMURUGAN L2 | MANIKANDAN N L3 | Muthumari Sundram L1 |
|---|---|---|---|---|---|---|
| 1.00Special Repair of NH7-M.Puliyankulam Road to M.Puliyankulam ( Via High School) Km 0/0 - 0/900-(R71) (VPR) | ||||||
| 2.00 | Clearing the Light jungle including all labour charges for burying and burning etc., complete. | 54 | M3 | 6.36 ₹343.44 | 6.36 ₹343.44 | 6.04 ₹326.16 Lowest |
| 3.00 | Earthwork excavating & depositing on bank with borrow pits in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 A including laying and spreading in layers of 250 mm loose thick each , sectioning , watering and compacting etc, complete as per MOST 301 - 305. | 21.6 | M3 | 140.45 ₹3,033.72 | 140.45 ₹3,033.72 | 125.3 ₹2,706.48 Lowest |
| 4.00 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) 250 mm thick, including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory Soil Compactor to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as pwe clause 406 of MORTH Rev-5 | 24.2 | M3 | 2,538.65 ₹61,435.33 Lowest | 2,538.65 ₹61,435.33 Lowest | 2,580.8 ₹62,455.36 |
| 5.00 | Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 50mm using 45mm IRC size HBG metal | 2.67 | M3 | 4,139.88 ₹11,053.48 | 4,139.88 ₹11,053.48 | 3,850.15 ₹10,279.9 Lowest |
| 6.00 | Providing and laying Tack coat over BT surface using 3Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat | 53.41 | M2 | 33.39 ₹1,783.36 | 33.39 ₹1,783.36 | 31.23 ₹1,667.99 Lowest |
| 7.00 | Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. | 322.5 | M2 | 84.47 ₹27,241.58 | 84.47 ₹27,241.58 | 79.09 ₹25,506.53 Lowest |
| 8.00 | Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., | 322.5 | M2 | 19.44 ₹6,269.4 | 19.44 ₹6,269.4 | 18.06 ₹5,824.35 Lowest |
| 9.00 | BITUMINOUS CONCRETE 25/30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as
per specification using CMP as per clause 507 of MORTH Rev-5 | 8.07 | M3 | 11,445.76 ₹92,367.28 | 11,445.76 ₹92,367.28 | 10,692.69 ₹86,290.01 Lowest |
| 10.00Special Repair of Kallikudi-T.Kallupatti Road to Vadakkampatti - Puliyampatti road Km 0/0 - 2/000-(R106) | ||||||
Tender Value
₹6.4 L
EMD Value
₹6,430
Closing Date
3 Nov 2025, 3:00 pmClosed
BDOBP
BDOBP
Madurai District Special repairs to NH-7 - M.Puliyankulam High.school road , Kallikudi- Kallupatti road to Vadakkampatti-Puliyampatti road,Maravapatti road to Selvapuram ad colony road in Kallikudi Panchayat Union.
2025_RDTN_617765_1
1/Kalli/ RRMS /2025-26
Open Tender
Civil Works
Works
120 days
kallikudi
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹6,430
5 Dec 2025
28 Oct 2025
3 Nov 2025
28 Oct 2025
3 Nov 2025
28 Oct 2025
Amount
Special Repair of NH7-M.Puliyankulam Road to M.Puliyankulam ( Via High School) Km 0/0 - 0/900-(R71) (VPR)
Clearing the Light jungle including all labour charges for burying and burning etc., complete.
Earthwork excavating & depositing on bank with borrow pits in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 A including laying and spreading in layers of 250 mm loose thick each , sectioning , watering and compacting etc, complete as per MOST 301 - 305.
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) 250 mm thick, including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory Soil Compactor to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as pwe clause 406 of MORTH Rev-5
Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 50mm using 45mm IRC size HBG metal
Providing and laying Tack coat over BT surface using 3Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
BITUMINOUS CONCRETE 25/30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Special Repair of Kallikudi-T.Kallupatti Road to Vadakkampatti - Puliyampatti road Km 0/0 - 2/000-(R106)
Clearing the Light jungle including all labour charges for burying and burning etc., complete.
Earthwork excavating & depositing on bank with borrow pits in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 A including laying and spreading in layers of 250 mm loose thick each , sectioning , watering and compacting etc, complete as per MOST 301 - 305.
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) 250 mm thick, including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory Soil Compactor to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as pwe clause 406 of MORTH Rev-5
Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 50mm using 45mm IRC size HBG metal
Providing and laying Tack coat over BT surface using 3Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
BITUMINOUS CONCRETE 25/30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Special Repair of Villur-Maravapatti road to Selvapuram Ad Colony road Km 0/0 - 0/340-(R171) (VPR)
Clearing the Light jungle including all labour charges for burying and burning etc., complete.
Earthwork excavating & depositing on bank with borrow pits in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 A including laying and spreading in layers of 250 mm loose thick each , sectioning , watering and compacting etc, complete as per MOST 301 - 305.
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) 250 mm thick, including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory Soil Compactor to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as pwe clause 406 of MORTH Rev-5
Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 50mm using 45mm IRC size HBG metal
Providing and laying Tack coat over BT surface using 3Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
BITUMINOUS CONCRETE 25/30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
RATHINAM BALAMURUGAN (BID ID -1502080)
MANIKANDAN N (BID ID -1502214)
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.99 MB
BOQ_738284.xls
BOQ • 0.90 MB
1PQ.pdf
Tender Documents • 0.85 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .