Loading…
Loading…
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹3.1 Cr
EMD Value
₹6.1 L
Closing Date
13 Nov 2026, 6:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Superintending Engineer, GTA
OFFICE OF THE SUPERINTENDING ENGINEER DARJEELING CIRCLE Gorkha Ranga Manch Bhawan, 3rd Floor, Right Wing Darjeeling 734101
Package-III under Darjeeling Engineering Division
2026_GTA_5080825_10
NIeT_08( 1st Call)/SDRF/SE/DC/GTA/ 2026-2027(Sl. No. 01 to 17)
Open Tender
CIVIL WORKS
Percentage
180 days
DARJEELING
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹6.1 L
15 Oct 2026
15 Oct 2026
16 Nov 2026
16 Oct 2026
13 Nov 2026
16 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | 3.A. Emergent restoration of Road Connecting Pokhraibong Valley to Siliguri via Cap Dhunga and Bungkulung, Dhajea, Dist- Darjeeling
Land Slide Clearance in Soil learance of land slides in soil and ordinary rock by a bull-dozer D 80 A-12, 180 HP and disposal of the same on the valley side. | 225 | cum | 61.8 | ₹13,905 |
| 2 | Excavation for Structures
Earth work in excavation of foundation of structures
as per drawing and technical specification,
including setting out, removing, spreading or
stacking of spoils within a lead of 150 m. as directed
and including trimming the sides of the trenches,
leveling, dressing and ramming the bottom, and
backfilling with approved material complete as per
direction of the Engineer-in-Charge .
I. In all sorts of soil excluding marshy soil & rocks
(soft or hard) by manual means.
a) upto 3 m depth (iv) Without pumping out water and shoring | 314.68 | cum | 114 | ₹35,873.52 |
| 3 | Plum concrete work with 40 % cement concrete with 30 mm down graded stone metal and 60 % stone boulder of size 150 mm and above, placed in position as directed excluding shuttering if any.
(i) (1:3:6) proportion | 1,283.08 | cum | 3,251.68 | ₹41,72,165.57 |
| 4 | Hire and labour charges for Shuttering with or
without staging upto 4.0 m height using approved
stout props with wooden planks/ply wood/steel
sheet plate with required bracing for any kind of
plain or reinforced concrete works in all sorts of
minor structure including culvert, box culvert, cross
drain etc. The rate is inclusive of fitting, fixing and
striking out after completion of work as per
specification and direction.
(a) 25 mm to 30 mm thick wooden shuttering as per decision & direction of Engineer-In-Charge. | 1,000.02 | Sqm | 214 | ₹2,14,004.28 |
| 5 | Providing weep holes in Brick masonry / Plain / Reinforced concrete abutment, wing wall / return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V:20H towards drawing face. Complete as per drawing and Technical specifications. | 737 | Each | 117 | ₹86,229 |
| 6 | Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification.
A) Granular material | 247.91 | cum | 3,068.28 | ₹7,60,657.29 |
| 7 | Providing and laying Design Mix concrete for plain / reinforced concrete work in any part of bridge (excluding bottom plugging) with coarse aggregates of appropriate nominal size and grading, fine aggregate (sand) conforming to proper grading zone, both of approved quality and cement, as necessary, including labour, cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge and cost for quality control, sampling, testing etc. all complete but excluding cost of labour and materials for formwork & reinforcement works. c) M-25 Grade:
Using concrete mixer. | 228.75 | cum | 5,869.13 | ₹13,42,563.49 |
| 8 | Supplying, fitting and placing HYSD bar reinforcement in Bridge Super-structure including initial straightening, straightening of coils bars, removal of loose rust (if any), cutting to requisite length bending, binding with annealed wire not less than 1 mm in size and conforming to IS 280 at every intersection hooked and bent to correct shape and placed on forms etc. including cost of black annealed wire and cost of loading, unloading, carriage of all steel materials complete as per drawing and technical specifications. | 17.14 | MT | 59,905.65 | ₹10,26,782.84 |
| 9 | Picking up and removing old bituminous layer or sand sealing coat from old black topped surface and cleaning the exposed surface by scraping and stacking the material as directed. (a) By manual means : (i) From 25 mm to 50 mm thick. | 1,271.65 | cum | 22.6 | ₹28,739.29 |
| 10 | Dry Rubble Flooring Construction of dry rubble flooring at cross drainage works for relatively less important works. | 572.25 | cum | 2,672.12 | ₹15,29,120.67 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.75 MB
Tendernotice_2.pdf
PDF • 0.55 MB
BOQ_5188994.xls
BOQ • 0.39 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .