Executive Engineer, Cooch Behar Highway Division
Office of the E.E., Cob. Hwy. Divn., Cooch Behar
Emergent rain damage Slope Restoration work of RUB Approach Road of Sonapur-Pundibari Road Stretch at 8.50 KMP chainage due to huge raincut under sloped embankment portion under Cooch Behar Highway Division in the District of Cooch Behar.
2026_WBPWD_5016377_2
NIT/07E/2026-27/EECHD/PWRD
Open Tender
CIVIL WORKS
15 days
Cooch Behar
Please refer Tender documents.
6 documents required · 6 mandatory
₹19,975
Yes
Office of the E.E., Cob. Hwy. Divn.
3 Jul 2026
3 Jul 2026
15 Jul 2026
7 Jul 2026
13 Jul 2026
7 Jul 2026
8 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Patching of damaged concrete surface with
polymer concrete (25 mm nominal thick) and
curing compounds, initiator and promoter,
available in present formulations, to be applied as
per instructions of manufacturer and as approved
by the Engineer. | 72 | m² | 1,391 | ₹1,00,152 |
| 2 | Repair of Steel Railing
Repair of steel railing to bring it to the original
shape. | 200 | mtr. | 292 | ₹58,400 |
| 3 | Close Bamboo Walling made of 65mm to 75mm dia. bamboos (in single line) driven about half-length into the ground side by side, with stout stays at an interval of 1m, 3nos. of half split bamboo runner of same dia fitted and fixed with nails etc. complete as per direction. (Measurement to be taken along the length of piling after finishing the works). (iii) With bamboos of length above 2.50 m and upto 3.00 m | 290 | mtr. | 587 | ₹1,70,230 |
| 4 | Supplying & filling empty Cement bags with silver sand, stitching the bag (cost of thread included) and carrying and placing them in position and all incidental charges complete including cost of sand and gunny bags. | 10,000 | Bags | 14.81 | ₹1,48,100 |
| 5 | Dressing and chilchalling Road flanks including cutting and filling with earth up to 150 mm average thickness finished with outward cross-grade of 1 in 30. | 1,400 | m² | 12.2 | ₹17,080 |
| 6 | Restoration of Rain Cuts
Restoration of rain cuts with soil, moorum gravel or a mixture of these, clearing the loose soil, benching for 300mm width laying fresh material in layers not exceeding 250 mm and compaction with plate compactor or power rammer to restore the original alignment, level and slopes as per drawings and technical specifications Clause 1902 for Rural Roads of MORD. | 126 | m³ | 140 | ₹17,640 |
| 7 | Earthwork in excavation from borrow pits
Earthwork in excavation from borrow pits (land owned i.e. by the Agency ) and depositing in layers of 250 mm. including breaking clods in embankment works and to fill up back of abutments, depressions and ruts with an initial lead up to 50 m and initial lift up to 3.0 m making bunds at top as directed dressing complete.
1. carriage above 2.00 Km and up to 3.00 Km (Payment will be made on loose net volume) | 1,050 | m³ | 210.76 | ₹2,21,298 |
| 8 | Construction of Sub Base using Local Materials:
Construction of Sub Base using Local Materials, spreading in uniform layers with Motor grader on prepared surface, including screening the metal as necessary, mixing by mix in place method with Rotavator at OMC, and compacting with vibratory roller to achieve the desired density, lighting, guarding and barricading including cost and carriage of all materials and making necessary earthen bundh of one metre wide on each side to protect the edges complete as per Clause 401 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).
(iv) For Construction of Sub Base by compacting river bed materials. | 74 | m³ | 1,420.35 | ₹1,05,105.9 |
| 9 | Add GST@18% on Rs . 838006.00 i.e. total amount over item no1 to 8 | - | % percentage | 18 | - |
| 10 | Add Labour Welfare Cess @1% of Rs. 988847.00 i.e. total amount of Item No. 1 to 9 | - | % percentage | 1 | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 20.09 MB
Tendernotice_2.pdf
PDF • 2.22 MB
BOQ_5085801.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid