Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Tender Value
₹21 Cr
EMD Value
₹31.5 L
Closing Date
9 Feb 2026, 12:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SUPERINTENDING ENGINEER
OFFICE OF SE UNNAO CIRCLE PWD UNNAO
WIDENING AND STRENGTHENING OF GAUSHALA NEER PARASPUR ROAD (O.D.R) FROM CH- 0.000 TO 11.200 (LENGTH 11.200KM) IN DIST. HARDOI WITH FIVE YEAR MAINTENANCE
2026_CEUCZ_1111513_1
396/M/1MT/E-TENDER/UC/2026 DT 24.01.2026
Open Tender
Civil Works - Roads
Item Rate
455 days
HARDOI
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,715
₹31.5 L
Yes
SUPERINTENDING ENGINEER
17 Mar 2026
2 Feb 2026
9 Feb 2026
2 Feb 2026
9 Feb 2026
2 Feb 2026
5 Feb 2026
Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections and transporting to the embankment location within all lifts and lead upto 1000 m. (Including Labour Cess but excluding GST)
Construction of embankment with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table No 300.2 (Compaction only) (Including Labour Cess but excluding GST)
Construction of embankment with approved material obtained from pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table No 300-2 (Including Labour Cess but excluding GST)
Construction of subgrade and earthen shoulders with approved material obtained from pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table No 300.2 (Including Labour Cess but excluding GST)
Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 (in 2 Layer) (Including Labour Cess but excluding GST)
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mix plant carriage of mixed material by tipper to site, laying in uniform layers with paver in subbase/base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (Including Labour Cess but excluding GST)
Providing and applying primer coat with bitumen emulsion (SS) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70 to 1.00 kg/sqm usingmannual means. (Including Labour Cess but excluding GST)
Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects. (Including Labour Cess but excluding GST)
Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom as per Mort&H 503 (Including Labour Cess but excluding GST)
Providing and laying bituminous concrete with higher capacity batch type hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects (Including Labour Cess but excluding GST)
Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with approve grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing (Including Labour Cess but excluding GST)
Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single Row Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets Clause 1106. B 1000 mm dia (Including Labour Cess but excluding GST)
Earthwork in excavation of foundation of structures as per drawing and technical specifications including setting out, construction of shoring and bracing, removal of stumps and other deleterious materials. dressing of sites and bottom and backfilling with approved material. (Including Labour Cess but excluding GST)
Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. (Including Labour Cess but excluding GST)
Brick Masonry Work in Cement Mortar 1:3 in Foundation complete excluding Pointing and Plastering, as per Drawing and Technical Specifications. (Including Labour Cess but excluding GST)
Providing weep holes in brick masonry/plain/reinforceed concrete abutment, wing wall, return wall with 100mm dia AC pipe extending through the full width of the structure with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification. (Including Labour Cess but excluding GST)
RCC Grade M 25 Furnishing and placing reinforced cement concrete in super structure as per drawing and Technical Specifications. (Including Labour Cess but excluding GST)
RCC Grade M 20 Furnishing and placing reinforced cement concrete in super structure as per drawing and Technical Specifications.(Including Labour Cess but excluding GST)
Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications. (Including Labour Cess but excluding GST)
Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical Specifications (Including Labour Cess but excluding GST)
Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements laid down in clause 2504.2.2. of MORT&H specifications to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall and return wall to the full height compacted to a firm condition complete as per drawing and Technical Specification. (Including Labour Cess but excluding GST)
Maintenance of constructed road for next five years after the actual date of completion. The amount to be paid as total maintenance cost for Next five years in the form of installment as given below. (Rates are including labour cess but excluding GST) for 2nd year after the actual date of completion @ 0.25% of total Construction cost.
Maintenance of constructed road for next five years after the actual date of completion. The amount to be paid as total maintenance cost for Next five years in the form of installment as given below. (Rates are including labour cess but excluding GST) for 3rd year after the actual date of completion @ 0.50% of total Construction cost
Maintenance of constructed road for next five years after the actual date of completion. The amount to be paid as total maintenance cost for Next five years in the form of installment as given below. (Rates are including labour cess but excluding GST) for 4th year after the actual date of completion @ 0.75% of total Construction cost
Maintenance of constructed road for next five years after the actual date of completion. The amount to be paid as total maintenance cost for Next five years in the form of installment as given below. (Rates are including labour cess but excluding GST) for 5th year after the actual date of completion @ 1.00% of total Construction cost
stage.html
html • 0.02 MB
cancelled_1.pdf
pdf • 0.26 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.94 MB
BOQ_2053870.xls
BOQ • 0.31 MB
ADDENDUM.pdf
Tender Documents • 1.40 MB
SBD.pdf
Tender Documents • 1.62 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .