| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.9 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹9.6 L+₹72,699.66 (8.15%)Rejected-AOC | L2 | Rejected-AOC L2 | |
| 3 | L3₹10.9 L+₹2.0 L (22.4%)Rejected-AOC | L3 | Rejected-AOC L3 |
Tender Value
₹11.8 L
EMD Value
₹23,000
Closing Date
13 Dec 2022, 11:00 amClosed
E.E.M.G.C.C.D.5, Bijnor
E.E.M.G.C.C.D.5, Bijnor
Construction of V.R.B at km. 7.940 of Dakiya Dy. under Madhya Ganga Canal stage-II.
2022_UPIDC_750520_21
03/EE/2022-23
Open Tender
Civil Works - Bridges
Item Wise
90 days
Dhakiya
Please refer Tender documents.
2 documents required · 2 mandatory
₹766
₹23,000
17 Feb 2023
7 Dec 2022
13 Dec 2022
7 Dec 2022
13 Dec 2022
7 Dec 2022
Earth work in excavation foundation in ordinary soil (lomy,clay or sand) including lift 1.50 M & lead upto 30 M and including filling watering and ramming of excavation earth into the trench.
Cement concrete in footing 1:3:6 including all cost of material,labour,T&P etc .
Cement concrete in 1:6:12 including all cost of material, labour , T&P etc. for completion of work .
First class brick work in 1:4 C.M. including all cost of material, labour and T&P etc. for proper completion of work.
Centering & Shuttering including all cost of material, labour and T&P etc. for proper completion of work.
for R.C.C. work
for C.C. work
Cement concrete with stone ballast in R.C.C. 1:1.5:3 (M-20) including all cost of material, labour , T&P etc. for completion of work.
Cement concrete with stone ballast in R.C.C. 1:1:2 (M-25) including all cost of material, labour , T&P etc. for completion of work .
Supply and laying steel reinforcemet with cutting, binding, & placing includign cost of binding wire, steel, labour and T&P etc. complete.
Cement pointing in 1:2 (struck deep) on brick masonry i/c cost of all material, labour, T&P etc for completion of work.
Supply and laying Tarfelt sheet in two layers on Bed Block including all cost of material, labour and T&P etc. complete.
Supply and laying thermocoal sheet in expansion joint including all cost of material, labour and T&P etc. complete.
Supply and fixing wheel gaurd including all cost of material, labour and T&P etc. complete.
Earth work in filling in ramp and diversion including ramming and dressing the surface to be required level and slope including carriage 600 M up to work site with all lead and lift.
Dry brick on edge soling laid dry filling joint including all cost of material, labour and T&P etc. all complite
Supply and Laying of Rever Bed Material I/C Cost of material Labour T&P etc. required for proper completion of work.
Filling of expansion joint with bitumen and saw dust including all cost of material, labour and T&P etc.
Removal of diversion including 1.50 m lift and up to 100 m lead
Supply and Fixing sign board size 1.50x1.00M, Including cost of all materials, labour, T&P etc. required for proper completion of work/ No.
MS ANIL KUMAR CONSTRUCTION
JS cONSTRUCTIONS
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .